Penang LRT Stays Within RM16 Billion Budget - MRT Corp

Anis

Share via

255384.jpg The Penang Mutiara LRT Line will move ahead with a firm budget cap of RM16 billion, despite inflation and escalating construction costs, said MRT Corp chief executive Datuk Mohd Zarif Hashim.

Speaking at a media luncheon, Zarif explained that the earlier RM10 billion estimate, made prior to the federal government's involvement, did not factor in key costs such as land acquisition. He added that even the RM13 billion budget approved by the Cabinet had not fully accounted for inflation, rising material prices, and land-related expenses. Untitled6-3-(3).jpg
“If we included everything without strict cost controls, the project could reach RM19 billion

“But we won’t let that happen. Through competitive tenders and careful planning, we’re determined to keep it under RM16 billion,” he said.

Zarif added that the Mutiara Line is expected to be the most cost-efficient LRT system in the country. To manage land expenses, MRT Corp is working with the Penang government to secure nominal charges for state-owned land.

The 29.5-kilometre line will run from Silicon Island to Komtar, then cross the channel to Penang Sentral in Butterworth. It will feature 21 stations, including a five-kilometre sea bridge standing 62 metres above sea level, designed to accommodate large shipping vessels. lrtee_NSTfield_image_socialmedia.var_1712656401.jpg
The line will also include an open-air walkway for pedestrians and cyclists, which will be closed during adverse weather. An optimised depot site at Pesta has been downsized from 37 acres to 11 acres through design efficiency.

The trains will use a Level 3 autonomous system that operates without a driver but includes an onboard attendant, allowing for reduced operational and maintenance costs.

Zarif said the Mutiara Line must become financially self-sufficient within five years of operation, funded through fare collection and advertising revenue. He added that this would free up public funds for future transit lines.

02nt16economy_1735783392.jpg
“The Mutiara Line won’t solve everything, but it’s a vital first step

“Penang needs at least four LRT lines to see real change. Once all are in place, the impact will be dramatic,” he was quoted as saying.

The Mutiara Line is scheduled for completion in 2031, with the full four-line network expected by 2050.


Tagged:

Penang Mutiara Line LRT Project
Penang public transport
MRT corp
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

Penang Still Waiting For Green Light From MOT For LRT project

Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.

02-07-2025
Auto News

Mutiara LRT Issues Resolved , Earthworks Commencing Soon

Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.

11-06-2025
Auto News

Penang LRT Project Progressing Steadily - MRT Corp

Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.

21-04-2025
Auto News

Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.

Auto News

Penang Mutiara LRT Project Poised To Commence In 2025

Loke announces phase 1 of Penang Mutiara LRT project will commence early next year.

Auto News

Penang Confirms LRT Work Construction To Begin In December

December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.

09-10-2024
Auto News

Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B

The Juru-Sungai Dua Elevated Highway is set to cost RM1.8B, project will be undertaken by PLUS on a Public-Private Partnership basis.

Auto News

Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT

Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.

Latest News

Auto News

BYD Zengzhou Carrier Vessel Made Maiden Voyage to Malaysia

BYD’s own Zengzhou carrier vessel just made its maiden voyage to Malaysia, capable of carrying up to 7,000 vehicles.

06-08-2025
Auto News

JPJ Warns Against ‘Kopi-O’ Licences As Fake Driving School Goes Viral

JPJ warns Malaysians against fake “kopi-o licences” offering driving permits without tests or training.

06-08-2025
Auto News

2025 Proton Saga Details Leaked – New 1.5 4-cyl Engine, No MT, Dual-Screens

Alleged details plus snapshots of new 2025 Proton Saga leaks online, new 1.5 4-cyl engine, no MT option, and dual-screens touted.

06-08-2025
Auto News

KKR: MLFF Will Be Privately Funded Under B2B Model

The MLFF toll system will be delivered through a B2B model, with private firms striking direct deals with highway concessionaires.

Auto News

ETS Segamat–Johor Bahru Extension is On Track, No Delays – MoT

Transport Minister Anthony Loke says the ETS extension project from Segamat to Johor Bahru is on track with no delays.

06-08-2025
Auto News

Report: Malaysia Takes Lead in Southeast Asia’s Auto Market

Malaysia for the first time has surpassed Indonesia in quarterly car sales driven by strong local demand.

Auto News

Zero Tolerance Ahead For Untaxed Luxury Cars - Experts

Road safety experts are urging tougher penalties for luxury car owners who skip road tax and insurance.

06-08-2025
Auto News

KTMB Train Schedule Upgrades Hit Speed Bumps

KTMB's schedule upgrades delayed by train shortages, limited track access, and speed restrictions.

06-08-2025