Penang LRT Stays Within RM16 Billion Budget - MRT Corp

Anis

Share via

255384.jpg The Penang Mutiara LRT Line will move ahead with a firm budget cap of RM16 billion, despite inflation and escalating construction costs, said MRT Corp chief executive Datuk Mohd Zarif Hashim.

Speaking at a media luncheon, Zarif explained that the earlier RM10 billion estimate, made prior to the federal government's involvement, did not factor in key costs such as land acquisition. He added that even the RM13 billion budget approved by the Cabinet had not fully accounted for inflation, rising material prices, and land-related expenses. Untitled6-3-(3).jpg
“If we included everything without strict cost controls, the project could reach RM19 billion

“But we won’t let that happen. Through competitive tenders and careful planning, we’re determined to keep it under RM16 billion,” he said.

Zarif added that the Mutiara Line is expected to be the most cost-efficient LRT system in the country. To manage land expenses, MRT Corp is working with the Penang government to secure nominal charges for state-owned land.

The 29.5-kilometre line will run from Silicon Island to Komtar, then cross the channel to Penang Sentral in Butterworth. It will feature 21 stations, including a five-kilometre sea bridge standing 62 metres above sea level, designed to accommodate large shipping vessels. lrtee_NSTfield_image_socialmedia.var_1712656401.jpg
The line will also include an open-air walkway for pedestrians and cyclists, which will be closed during adverse weather. An optimised depot site at Pesta has been downsized from 37 acres to 11 acres through design efficiency.

The trains will use a Level 3 autonomous system that operates without a driver but includes an onboard attendant, allowing for reduced operational and maintenance costs.

Zarif said the Mutiara Line must become financially self-sufficient within five years of operation, funded through fare collection and advertising revenue. He added that this would free up public funds for future transit lines.

02nt16economy_1735783392.jpg
“The Mutiara Line won’t solve everything, but it’s a vital first step

“Penang needs at least four LRT lines to see real change. Once all are in place, the impact will be dramatic,” he was quoted as saying.

The Mutiara Line is scheduled for completion in 2031, with the full four-line network expected by 2050.


Tagged:

Penang Mutiara Line LRT Project
Penang public transport
MRT corp
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

Penang Mutiara LRT Construction Kicks Off Jan 2026

Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.

19-11-2025
Auto News

Penang Sentral Set to Become Mainland’s Integrated Transport Hub

The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.

Auto News

Penang Defends Mega Projects As Key To Tackling Traffic Woes

Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.

04-09-2025
Auto News

MRT Corp Justifies RM16.8b Penang LRT Budget

MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.

21-08-2025
Auto News

Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke

The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.

19-08-2025
Auto News

Penang Still Waiting For Green Light From MOT For LRT project

Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.

02-07-2025
Auto News

Mutiara LRT Issues Resolved , Earthworks Commencing Soon

Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.

11-06-2025
Auto News

Penang LRT Project Progressing Steadily - MRT Corp

Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.

21-04-2025

Latest News

Auto News

Ops Lancar: Johor Police Issue Over 4,400 Summonses In Two Days

Johor police issued 4,433 traffic summonses in just the first two days of their Christmas and New Year road operations.

26-12-2025
Auto News

MOF Extends OMV Relief: CKD Vehicle Prices Safe Until June 2026

MOF confirms that non-manufacturing costs under OMV remain fully excise-exempt for another six-months.

Auto News

iCaur V23 Earns 5-Star ASEAN NCAP Rating

Newly launched iCaur V23 EV SUV posts strong 91.02-point score in ASEAN NCAP 2021–2025 protocol crash-tests.

Auto News

Chery Tiggo 7 PHEV Earns 5-Star ASEAN NCAP Score

Chery Tiggo 7 PHEV C-SUV earns 5-star ASEAN NCAP rating, posting an impressive 94.68-point score.

Auto News

Updated Fuel Prices From 25 To 31 December

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 25 to 31 December, 2025, the rates are as such.

Auto News

Malaysian EV Market Buzzing Ahead Of Year-End Tax Changes

EV registrations jump as buyers rush to beat the fully imported tax exemption, with Tesla, BYD, and Proton leading the charge.

24-12-2025
Auto News

DBKL Deploys Smart Traffic Light System Worth RM42 Million

DBKL deploys and maintains new ITMAX adaptive, data-driven smart traffic light systems across Kuala Lumpur.

Auto News

Penang Expects 2.2M Vehicles This Christmas, School Holidays

More than 2.2 million vehicles are expected to enter Penang during the Christmas season and school holidays.

24-12-2025