Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister Anthony Loke Siew Fook, announced that all outstanding issues regarding the Mutiara Line Light Rail Transit (LRT) project between the federal and Penang governments have been resolved amicably.
This confirmation followed a meeting chaired by Loke with Penang Chief Minister Chow Kon Yeow at the Transport Ministry in Putrajaya the previous month, where they addressed and resolved remaining matters, notably including the provision of a release letter from the state government.
“Physical work will begin shortly, in one or two months. So we ask them (the state government) to ensure there is a traffic diversion plan when piling work and construction begins to ensure the project doesn’t have a negative impact on road congestion,” he said.
-full_normal.jpg)
The proposed 29.5km Penang Light Rail Transit (LRT) system, estimated to cost RM10.5 billion, features 21 stations and aims to connect the southern region of the island to the northeast, with a link to Penang Sentral in Butterworth on the mainland.
Meanwhile, on Rapid Penang On-Demand service by Rapid Bus Sdn Bhd (Rapid Bus), Loke stated that it is currently operating successfully with 50 vans covering 13 zones in Penang, including six in Seberang Perai and seven on the island.
-full_normal.jpg)
“The average daily users stand at 1,944 people, with an average of 39 passengers per van daily and an average travel time of 16 minutes and a waiting time of 19 minutes,” he said, adding that there were 150 additional drivers to handle the vans to ensure smooth operations and that passengers would enjoy a fare of RM1 per trip.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRC6526
SELANGOR
BSQ8454
JOHOR
JYY7485
PULAU PINANG
PSD1321
PERAK
APJ2503
PAHANG
CFG7912
KEDAH
KGG5216
NEGERI SEMBILAN
NEK6635
KOTA KINABALU
SJS4331
KUCHING
QAB119P
Last updated 20 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Public Review Opens for Revised Penang Mutiara LRT with Cross-Sea Link at Core
MRT Corp opens a three-month public review for the Penang Mutiara LRT, featuring a proposed six-kilometre cross-sea link to Penang Sentral.
23-02-2026
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Latest News
42 Clauses Are Changing: M'sia Is Facing Its Biggest Road Law Overhaul Since 2020, And Yes, It Affects Your Saman
Malaysia is introducing 42 new clauses to the Road Transport Act in its biggest traffic law overhaul since 2020. Here is how it affects your fines and roadblocks.
19-06-2026
Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped
Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.
18-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech
At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.
18-06-2026
It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up
Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.
17-06-2026
Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers
Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.
12-06-2026
15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage
Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.
10-06-2026
Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30
Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.
09-06-2026
Show More
trending_flat