LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

Kumeran Sagathevan

Share via

LRT3-ShahAlam-Line-(1)-full_normal.jpg


Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.

According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.


482007087_633007019374783_2319286765909882135_n.jpg

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.

A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.

Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.


481670118_633007029374782_6626559310987309250_n.jpg


Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.

According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.

Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.

He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.


PANEL-A-Quick-Facts-2.png


As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.

Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.

Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.


Tagged:

LRT3 Shah Alam Line
Light Rapid Transit 3 (LRT3)
Shah Alam Line (LRT3)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Save RM6,000 A Year? We Calculated Your Real Savings By Switching To The New LRT3

LRT3 Shah Alam Line is now open with free rides until July 31. See how switching to public transport can save you RM6,000 annually in fuel, tolls, and parking.

29-06-2026
Auto News

From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares

Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.

25-06-2026
Auto News

It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations

The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.

18-06-2026
Auto News

Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far

The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.

05-03-2026
Auto News

LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays

The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.

24-02-2026
Auto News

LRT3 Shah Alam Line Expected To Open In June

After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.

05-02-2026
Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025

Latest News

Auto News

Do Government Vehicles With Sirens Have The Right To Run Red Lights In Malaysia? Here's What Cops Say

Do emergency warning lights give vehicles carte blanche to run red lights in Malaysia? Bukit Aman clarifies traffic laws following a fatal KL crash.

21-08-2026
Auto News

Immigration Driver Pleads Not Guilty After Running Red Light & Killing Father And Two Daughters

Immigration driver Mohd Akbar Zainol pleads not guilty to 5 charges after running a red light in KL, hitting a car, and killing 3 pedestrians.

20-08-2026
Auto News

PDRM Is Spending RM8 Million On Silent E-Bikes For Border Patrols: Here’s What They Can Do

PDRM receives 375 silent tactical e-bikes worth RM8M! Discover how the 850Nm torque Jebatt F29 will stop border smuggling.

20-08-2026
Auto News

Immigration Truck Runs Red Light In KL: Father & 2 Daughters Killed, Mother In Red Zone

3 family members were killed after an Immigration truck ran a red light and crashed at Maju Junction, KL. Get the latest police details and investigation updates.

19-08-2026
Auto News

‘We Need RM4B, Only Got RM2B’: Ahmad Maslan Explains Why Highways & Potholes Stay Dark And Damaged

Works Ministry receives only RM2B of its required RM4B road maintenance budget. Ahmad Maslan explains why potholes, dark highways, and repairs are delayed in Malaysia.

19-08-2026
Auto News

A Bangladeshi Farmer Was Caught Delivering Veggies In A Mercedes: The Langkawi Duty-Free Loophole

Discover why a Bangladeshi farmer used a Mercedes to haul vegetables in Langkawi. Learn how duty-free taxes, extreme depreciation, and repair traps create cheap island luxury cars.

18-08-2026
Auto News

The Billionaire Who Saved Proton Just Resigned As Geely Chairman—Here’s What’s Happening

Geely founder Li Shufu resigns as Chairman of Geely Auto! Here is what the major executive shakeup means for Proton and Geely's global strategy.

18-08-2026
Auto News

"We Pay Roadtax" — RXZ Organiser Defends LPT Highway Closure By Comparing Convoy To Marathons

RXZ Members organisers defend their LPT highway closure proposal using marathon comparisons following 46 crashes, 11 deaths, and 1,800 summonses at Edition 8.0.

17-08-2026