LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

Kumeran Sagathevan

Share via

LRT3-ShahAlam-Line-(1)-full_normal.jpg


Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.

According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.


482007087_633007019374783_2319286765909882135_n.jpg

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.

A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.

Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.


481670118_633007029374782_6626559310987309250_n.jpg


Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.

According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.

Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.

He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.


PANEL-A-Quick-Facts-2.png


As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.

Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.

Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.


Tagged:

LRT3 Shah Alam Line
Light Rapid Transit 3 (LRT3)
Shah Alam Line (LRT3)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025
Auto News

LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening

LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.

18-11-2025
Auto News

Shah Alam LRT Delayed Again, December Now In Sight

The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.

26-08-2025
Auto News

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News

LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening

LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.

18-11-2025
Auto News

Shah Alam LRT Delayed Again, December Now In Sight

The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.

26-08-2025
Auto News

LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.

Latest News

Auto News

Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?

The traffic summons discount is over, millions of fines remain unpaid, and stricter penalties kick in next year

31-12-2025
Auto News

LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.

Auto News

KLIA T1 Moves Customs Checks — Here’s What You Need To Know

Customs checks at KLIA T1 will move to the departure gates from Jan 1, promising smoother departures.

Auto News

China Set to Overtake Japan as World’s Top Auto Seller in 2025

China set to become world’s top auto seller in 2025, overtaking Japan as domestic and overseas sales growth surges.

Auto News

KTMB Southern Express Ends Service As ETS Takes Over

KTMB will end the Southern Express on the Gemas–JB Sentral route from Jan 1 to make way for eight daily ETS trips.

30-12-2025
Auto News

Can Instalment-Based Payment Scheme Help Solve Unpaid Summonses?

Road safety expert suggests instalment-based payment scheme could help resolve unpaid summonses. Do you agree?

30-12-2025
Auto News

Kelantan Flags 29 Federal Roads For Urgent Repairs

The Kelantan JKR has identified 29 federal roads across nine districts that need urgent repairs.

30-12-2025
Auto News

Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border

The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.

30-12-2025