Pan Borneo highway status in Sabah and Sarawak
Jesica Sendai
6-12-2022
Image credits to BERNAMA
The transportation industry has made remarkable progress toward recovery after being severely impacted by the pandemic. In Sabah and Sarawak, the federal government has approved the construction of Phase 2 of the Sarawak-Sabah Link Road (SSLR) project and the Trans Borneo Highway (LTB) project in August of this year, which will begin early next year.
Recently, Public Works Minister Datuk Seri Alexander Nanta Linggi has told Bernama that there will be more focus on the completion of the Pan Borneo Highway project, as a measure to ensure the development of facilities for residents in the rural areas of Sabah and Sarawak.
Nanta said that matter was one of his main focuses after being appointed to lead the Ministry of Public Works (KKR), in addition to ensuring that problematic projects across the country could be completed as soon as possible.
"It is certain that my focus is on the Sarawak Pan Borneo Highway project to be implemented and completed in the best possible way, in addition to the project in Sabah as well because it is understood that the achievements in Sabah have not been satisfactory," he said after scanning the time recorder card as a symbol of starting his official duties at the KKR headquarters in Kuala Lumpur yesterday.
Whereas the first phase of the project, which began in 2016, was expected to be completed this year, it is now more than 60% complete in Sabah, and Phase one of the Pan Borneo Highway project, which covers 786 kilometres from Telok Melano to Miri and costs RM16.117 billion, has reached 88% completion as of October 2022.
As for the SSLR and LTB projects, which connect Miri to Limbang and Lawas, are currently in their last stages of construction and are projected to take three to five years to complete.
Beside that, Sarawak also saw the opening the Pujut Section of the Sarawak portion of the Pan Borneo Highway took place on Aug 7, 2022, involving a total cost of RM10.62 billion that enable communities and residents in Miri, Limbang and Lawas to enjoy a better, safer, and more comfortable road network.
The 15.9 km stretch of the Pujut Section of the Pan Borneo Highway that connects the Miri Airport intersection and the Pujut Link Road was built at an estimated cost of RM470 million.
Source: BERNAMA
Written By
Jesica Sendai
from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.
JPJ Running Numbers
KUALA LUMPUR
VPC6243
SELANGOR
BSE5792
JOHOR
JXW8334
PULAU PINANG
PRQ4735
PERAK
ANV5057
PAHANG
CFB7130
KEDAH
KGA4853
NEGERI SEMBILAN
NEF7928
KOTA KINABALU
SJK8316
KUCHING
QAB3347L
Last updated 10 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.10
-0.08
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.80
-0.08
EURO 5 B7
RM 3.00
-0.08
Last updated 08 May, 2025
Related News
New Peugeot 3S Outlet In Kuching Officially Opens
Peugeot Malaysia (Stellantis Malaysia) sees East Malaysia network strengthened newly opened Peugeot 3S outlet in Kuching, Sarawak.
28-02-2025
Four New Proton e.MAS Dealerships In East Malaysia Announced
Proton e.MAS EV brand network grows further with four new East Malaysia dealerships announced.
10-02-2025
SDAC Ford Beefs Up East Malaysia Network, Includes Upgraded Sibu Outlet
SDAC Ford beefs up its network across East Malaysia led by upgraded dealership outlet in Sibu, Sarawak.
04-02-2025
Sarawak Customs Foil Bid To Smuggle Japanese Luxury Sportscars
Customs in Sarawak thwart attempt to smuggle two Japanese luxury sportscars sans legit declarations valued at over RM350,000.
20-12-2024
2025 Proton X70 Launched In East Malaysia – From RM100,800 Onwards
Proton officially launches 2025 Proton X70 SUV in East Malaysia priced from RM100,800 onwards.
28-08-2024
New Toyota 3S Centre Opens In Kota Samarahan, Sarawak
UMW Toyota Motor sees its East Malaysia network grow further with opening of new Toyota 3S centre in Kota Samarahan, Sarawak.
19-08-2024
Relocated EAM Mitsubishi 3S Centre Now Open in Kuching, Sarawak
MMM announces official opening of relocated EAM Mitsubishi 3S Centre in Kuching, Sarawak.
01-03-2024
GWM Malaysia Opens First 4S Centre In Kuching
GWM Malaysia opens first flagship 4S centre in East Malaysia located in Kuching, Sarawak.
12-12-2023
Latest News
MAS 2025: Special Deals, Exciting Activities At Proton’s Booth
Proton touts special offers plus interactive activities at its booth for MAS 2025 show-goers.
09-05-2025
MAS 2025: Record EV Line-Up and Over 500 Vehicles
Over 200 exhibitors, test tracks, and next-gen models headline the country’s biggest auto event, the Malaysia Autoshow 2025.
09-05-2025
MAS 2025: Special Mercedes-Benz Certified Pre-Owned Deals By MBM
Mercedes-Benz Malaysia (MBM) brings special showcases and deals for its Certified Pre-Owned Vehicles at MAS 2025.
09-05-2025
MAS 2025: Exclusive 20th Anniversary Offers And Deals By Mitsubishi
MAS 2025 sees MMM offer visitors and show-goers with exclusive 20th anniversary promotions on its vehicle line-up and more.
08-05-2025
Heavy Traffic Expected At Singapore-Malaysia Checkpoints During Wesak Day
Singapore-Malaysia travellers should expect heavy traffic at Woodlands and Tuas checkpoints from May 8 to 13.
08-05-2025
KTMB Offers Special Train Service To East Coast For Aidiladha
KTMB will offer a special train service to the East Coast for travellers returning home for the upcoming Aidiladha.
08-05-2025
Car Company Wins RM54k For Water Damage Claim
A car company is compensated RM54k for the damage to their Porsche caused by water-contaminated petrol.
08-05-2025
UMW Toyota Closes April 2025 By Shifting 7,932 Vehicles
UMW Toyota Motor closes April 2025 by shifting 7,932 vehicles, YTD total now up to 27,876 units.
07-05-2025
Show More
trending_flat