LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity
-full_normal.jpg)
Yesterday, Transport Minister YB Anthony Loke delivered an update on the Light Rail Transit 3 (LRT3) project's development. Loke reported that construction is progressing quickly, with completion at 86%, including the installation of the signalling system.
Currently, 22 sets of three-coach trains are being tested thoroughly. LRT3 operations are expected to begin on March 1, 2025, which is approximately 18 to 19 months from now. Loke expressed confidence in the project's successful implementation, emphasising the significance of collaboration among all stakeholders to fulfil the target deadline.
-full_normal.jpg)
-full_normal.jpg)
The LRT3 is intended to assist nearly two million Klang Valley people, notably those living between Petaling Jaya and Klang. As a densely populated and developed region, tens of thousands of passengers are expected to utilise the LRT3.
With a capacity to accommodate 18,630 passengers per hour per direction, the project will include two interchange stations. Bandar Utama will connect the MRT Kajang Line to LRT3, while Glenmarie will connect the Kelana Jaya Line to LRT3. A flyover will connect these two stations, improving the system's overall connection.
-full_normal.jpg)
Loke emphasised that the 22 train sets are all brand new, luxurious, and outfitted with environmentally friendly "green technology." They are currently in the last stages of testing to ensure their readiness for the approaching opening.
During a site visit to the depot and LRT3 operation control center, Loke personally conducted a test drive on the trial route using one of the trains. He emphasised that the LRT3 is an important addition to public transportation in the Klang Valley, with the goal of encouraging more people to use public transportation in the area.
-full_normal.jpg)
Once completed, the LRT3 line would be approximately 37 kilometres long, with 2 km running underground. Over 2000 parking spots would be offered in 6 stations to assist travellers who choose to Park & Ride. The route would also service 67,000 people every day, with a 6-minute average wait time.
Source: MalayMail
Gallery
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQG3789
SELANGOR
BSL4062
JOHOR
JYP1319
PULAU PINANG
PRX2761
PERAK
APD7892
PAHANG
CFE6347
KEDAH
KGD6562
NEGERI SEMBILAN
NEJ1753
KOTA KINABALU
SJP5704
KUCHING
QAB9427M
Last updated 31 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.56
RON 97
RM 3.16
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
EURO 5 B7
RM 3.14
Last updated 01 Jan, 2026
Related News
Automatic Speed Limit Device Compliance Now at 48.37% – Loke
The compliance rate for the use of automatic speed limit devices has risen to 48.37%, says Transport Minister Anthony Loke.
03-12-2025
Singapore Tour Buses Allowed, But Express Services Remain Off-Limits - Loke
Singaporean buses can bring tourists into Malaysia, but running express routes with scheduled ticket sales is not permitted.
03-12-2025
Truck Operators Give 48-Hour Ultimatum, Loke Stands Firm On Load Limits
Truck operators give Anthony Loke 48 hours to respond to their 26-point memorandum on overloaded lorry limits.
20-11-2025
Loke Stands Firm On Lorry Load Limits Despite Pressure From Industry, MPs
Govt refuses to relax overloaded lorry rules even as transport groups and MPs push for a softer approach.
19-11-2025
MOT: Kejara System Rebuilt for Real Enforcement by 2026
Revamped Kejara in 2026 will blacklist defaulters, unify summons rates, and enforce traffic rules consistently.
18-11-2025
MTSB Memorandum Set to Be Presented to Cabinet Soon – Loke
The memorandum for the Malaysian Transport Safety Board will be presented to the Cabinet soon, says Transport Minister Anthony Loke.
17-11-2025
Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End
Transport Minister Anthony Loke says over 5.5 million JPJ summonses remain unpaid, urges motorists to settle them before year-end too.
07-11-2025
BAS.MY Pass Now At RM30 Monthly for Unlimited Bus Rides
BAS.MY services now cost just RM1 a day as the government reduces the 30-day Unlimited Travel Pass from RM50 to RM30.
04-11-2025
Latest News
Updated Fuel Prices From 1 To 7 January
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 1 to 7 January, 2026, the rates are as such.
31-12-2025
Selangor Police Collect RM19.5 Million During Summons Discount Period
More than 258,000 traffic summonses were settled in Selangor during the two-month 70% discount programme, collecting RM19.5 million.
31-12-2025
Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?
The traffic summons discount is over, millions of fines remain unpaid, and stricter penalties kick in next year
31-12-2025
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
KLIA T1 Moves Customs Checks — Here’s What You Need To Know
Customs checks at KLIA T1 will move to the departure gates from Jan 1, promising smoother departures.
31-12-2025
China Set to Overtake Japan as World’s Top Auto Seller in 2025
China set to become world’s top auto seller in 2025, overtaking Japan as domestic and overseas sales growth surges.
30-12-2025
KTMB Southern Express Ends Service As ETS Takes Over
KTMB will end the Southern Express on the Gemas–JB Sentral route from Jan 1 to make way for eight daily ETS trips.
30-12-2025
Can Instalment-Based Payment Scheme Help Solve Unpaid Summonses?
Road safety expert suggests instalment-based payment scheme could help resolve unpaid summonses. Do you agree?
30-12-2025
Show More
trending_flat