LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity
-full_normal.jpg)
Yesterday, Transport Minister YB Anthony Loke delivered an update on the Light Rail Transit 3 (LRT3) project's development. Loke reported that construction is progressing quickly, with completion at 86%, including the installation of the signalling system.
Currently, 22 sets of three-coach trains are being tested thoroughly. LRT3 operations are expected to begin on March 1, 2025, which is approximately 18 to 19 months from now. Loke expressed confidence in the project's successful implementation, emphasising the significance of collaboration among all stakeholders to fulfil the target deadline.
-full_normal.jpg)
-full_normal.jpg)
The LRT3 is intended to assist nearly two million Klang Valley people, notably those living between Petaling Jaya and Klang. As a densely populated and developed region, tens of thousands of passengers are expected to utilise the LRT3.
With a capacity to accommodate 18,630 passengers per hour per direction, the project will include two interchange stations. Bandar Utama will connect the MRT Kajang Line to LRT3, while Glenmarie will connect the Kelana Jaya Line to LRT3. A flyover will connect these two stations, improving the system's overall connection.
-full_normal.jpg)
Loke emphasised that the 22 train sets are all brand new, luxurious, and outfitted with environmentally friendly "green technology." They are currently in the last stages of testing to ensure their readiness for the approaching opening.
During a site visit to the depot and LRT3 operation control center, Loke personally conducted a test drive on the trial route using one of the trains. He emphasised that the LRT3 is an important addition to public transportation in the Klang Valley, with the goal of encouraging more people to use public transportation in the area.
-full_normal.jpg)
Once completed, the LRT3 line would be approximately 37 kilometres long, with 2 km running underground. Over 2000 parking spots would be offered in 6 stations to assist travellers who choose to Park & Ride. The route would also service 67,000 people every day, with a 6-minute average wait time.
Source: MalayMail
Gallery
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPY7918
SELANGOR
BSK1383
JOHOR
JYK9434
PULAU PINANG
PRV6170
PERAK
APC4637
PAHANG
CFE1418
KEDAH
KGC9560
NEGERI SEMBILAN
NEH5860
KOTA KINABALU
SJN6348
KUCHING
QAB5029M
Last updated 13 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
+0.05
RON 97
RM 3.25
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.07
+0.05
EURO 5 B7
RM 3.27
+0.05
Last updated 13 Nov, 2025
Related News
Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End
Transport Minister Anthony Loke says over 5.5 million JPJ summonses remain unpaid, urges motorists to settle them before year-end too.
07-11-2025
BAS.MY Pass Now At RM30 Monthly for Unlimited Bus Rides
BAS.MY services now cost just RM1 a day as the government reduces the 30-day Unlimited Travel Pass from RM50 to RM30.
04-11-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
JPJ Issued Over 4,000 Notices for Heavy Vehicle Speed Limiter Compliance
JPJ has issued over 4,000 notices to ensure heavy vehicles install speed limiter devices for safer roads.
23-10-2025
JPJ: Zero Tolerance Towards Overloading Includes Body Cam & Firearms Adoption
JPJ deploys body cam and small arms (pistols) as part of a nationwide crackdown on overloaded commercial vehicles.
14-10-2025
Govt Still Weighing Options For KL–Singapore HSR Project - Loke
Malaysia is still reviewing options for the KL–Singapore HSR, with a final model yet to be determined.
08-10-2025
Over 7,000 Commercial Vehicle Safety Audits Completed - Loke
Loke told Parliament that JPJ has audited more than 7,000 commercial vehicle operators, with a new digital system set by 2027.
07-10-2025
New RM22.7M JPJ Kajang Office Set for 2027
The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.
23-09-2025
Latest News
Updated Fuel Prices From 13 To 19 November
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 13 to 19 November, 2025, the rates are as such.
12-11-2025
RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta
The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.
12-11-2025
BYD Shark PHEV Pick-Up Truck Teased by BYD Cars Malaysia – Coming Soon?
BYD Cars Malaysia has dropped a teaser for the BYD Shark PHEV pick-up truck. Coming to Malaysia soon?
12-11-2025
Malaysia Scraps Rule of 78, Car Loan Savings Ahead - Analysts
Malaysia ends the Rule of 78, letting car loan borrowers save more with fairer interest.
12-11-2025
Govt Not Forcing Aeroline To TBS, Corus KLCC Stop Unsuitable
Express bus operators aren’t forced to use TBS or TBG but must run from safe, licensed terminals.
12-11-2025
Oct 2025 Vehicle Sales Up 30%, xEV Share at 8.7%
Malaysia’s car market surged in Oct 2025 with 81,413 new registrations, up 30% from Sept’s 62,598 units.
12-11-2025
LATAR Interchange Opens, Direct Access To Eco Grandeur
The Eco Grandeur Interchange and Toll Plaza has officially opened, offering direct access through Exit 2502 to Eco Grandeur.
11-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Show More
trending_flat