Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Image: Bernama
Earlier this week, Dewan Rakyat was informed that 15 out of 19 work packages for Phase 1B of the Pan Borneo Highway Project in Sabah are in the final stages of an open tender evaluation.
Datuk Seri Alexander Nanta Linggi announced that Letters of Acceptance (LOA) for these packages are anticipated to be issued to selected contractors in the third quarter (Q3) of this year. Four contractors have already been appointed to undertake construction work on four of the project’s packages, covering a total distance of 366.8 kilometers.
The project, with an estimated development cost of RM13.99 billion, is being funded through a hybrid financing method. This includes allocations from the Development Expenditure Budget and sukuk or bond issuances by DanaInfra Nasional Berhad.
Nanta stated that RM400 million has been allocated for preliminary works in 2024, based on current financial projections. He provided this information in response to a query from Isnaraissah Munirah Majlis (Warisan-Kota Belud) regarding the latest procurement types and funding sources for the project.
-full_normal.jpg)
Datuk Seri Alexander Nanta Linggi (second from right).
Addressing the status of Work Package 9, which covers the route from Serusop to Pituru and has experienced delays, Nanta explained that the delays were to ensure that qualified and capable contractors are selected.
The final evaluation for this work package is ongoing, with the LOA expected to be issued in Q3 of this year. The project is slated for completion within three years following the issuance of the LOA.
Nanta emphasised the significance of the Sabah Pan Borneo Highway project, describing it as a high-impact initiative and a priority for the Works Ministry. The ministry is committed to ensuring the project's timely implementation to enhance Sabah’s federal road infrastructure network.
In response to a supplementary question from Datuk Seri Dr. Ronald Kiandee (PN-Beluran) about why the Pan Borneo Highway project in Sarawak is progressing faster than in Sabah, Nanta attributed the delays to several factors, including land acquisition issues, utility relocation, and contractor selection challenges. KR
Source: Bernama
Written By
Thoriq Azmi
Former DJ turned driver, rider and story-teller. I drive, I ride, and I string words together about it all. [#FuelledByThoriq] IG: https://www.instagram.com/fuelledbythoriq/
JPJ Running Numbers
KUALA LUMPUR
VQB3862
SELANGOR
BSK4081
JOHOR
JYL6541
PULAU PINANG
PRW985
PERAK
APC7938
PAHANG
CFE2693
KEDAH
KGD1929
NEGERI SEMBILAN
NEH6934
KOTA KINABALU
SJN8792
KUCHING
QAB5844M
Last updated 26 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
RON 97
RM 3.28
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.10
+0.03
EURO 5 B7
RM 3.30
+0.03
Last updated 20 Nov, 2025
Related News
Proton: Sabah X50 Customers Have Nothing To Worry
Proton reaffirms after-sales for X50 model customers in Sabah through Regional Parts Centre established in Kota Kinabalu.
24-10-2025
Four New Proton e.MAS Dealerships In East Malaysia Announced
Proton e.MAS EV brand network grows further with four new East Malaysia dealerships announced.
10-02-2025
SDAC Ford Beefs Up East Malaysia Network, Includes Upgraded Sibu Outlet
SDAC Ford beefs up its network across East Malaysia led by upgraded dealership outlet in Sibu, Sarawak.
04-02-2025
2025 Proton X70 Launched In East Malaysia – From RM100,800 Onwards
Proton officially launches 2025 Proton X70 SUV in East Malaysia priced from RM100,800 onwards.
28-08-2024
Lexus Kota Kinabalu Officially Opens As Brand’s First Centre In Sabah
Lexus Malaysia sees network expand in East Malaysia as it marks the official opening of Lexus Kota Kinabalu.
05-12-2023
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
New Ford Ranger heads to East Malaysia this Sept and Oct
New generation Ford Ranger pick-up truck set for preview tour in East Malaysia ahead of its showroom launches there.
30-08-2022
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Latest News
SPYSHOT: Proton e.MAS 7 PHEV Sighted! – Launching Next Year?
Proton e.MAS 7 PHEV sighted undergoing road tests in camouflage. Will PRO-NET launch it next year?
25-11-2025
Nationwide Checks Find No Shortchanging of RON95
Authorities confirm petrol stations are dispensing RON95 fuel accurately across the country.
25-11-2025
Man Killed After 100KG Detached Metal Shaft Strikes Car
A 63-year-old man lost his life when a heavy metal shaft fell from a truck and pierced his vehicle’s windshield.
25-11-2025
PLUS Activates Contra Lane On Elite Until Nov 27
A nightly contra lane will run between Bandar Saujana Putra and Putrajaya with lane diversions in place.
25-11-2025
KTMB Diverts Passengers From Arau Station As Floods Worsen In Perlis
Flooded roads have forced KTMB to temporarily shift ETS boarding and alighting from Arau to Kodiang Station.
25-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Isuzu Malaysia Opens New 4S Centre in Balakong
Isuzu Malaysia has opened its new 4S centre in Balakong, operated by SV Prestige Auto.
24-11-2025
Show More
trending_flat