Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

Anis

Share via

Sabah-Pan-Borneo-Highway-BONGAWAN-to-PAPAR-750x500.jpg

The construction of Phase 1A of the Pan Borneo Highway (LPB) in Sabah is taking longer than anticipated, as stated by Deputy Works Minister, Datuk Seri Ahmad Maslan. Difficult land acquisition circumstances and the drawn-out utility relocation process are to blame for these delays.

He emphasized that the landowners' resistance to cooperate has caused delays and the need for an extension of time, with some even going so far as to file a lawsuit, according to Bernama.

As of August 2024, 79.48% of the 15 work packages in Phase 1A had been completed. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 km,” said Ahmad Maslan.

pan-borneo-highway.jpeg
“In addition, I hope the construction team can complete this project by meeting the quality, cost, and time standards set forth, in line with the MY Jalan KK programme’s goal of delivering comfortable and safe infrastructure for all Malaysia Madani people,” he added.



Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQH3195

SELANGOR

BSL5834

JOHOR

JYP5605

PULAU PINANG

PRX5166

PERAK

APE1207

PAHANG

CFE7393

KEDAH

KGD7818

NEGERI SEMBILAN

NEJ2564

KOTA KINABALU

SJP7026

KUCHING

QAB156N

Last updated 13 Jan, 2026

Fuel Price

Petrol

RON 95

RM 2.54

-0.02

RON 97

RM 3.11

-0.05

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.89

-0.05

EURO 5 B7

RM 3.09

-0.05

Last updated 08 Jan, 2026

Related News

Auto News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.

26-06-2024
Auto News
Pan Borneo highway status in Sabah and Sarawak

Pan Borneo highway status in Sabah and Sarawak

The condition of the Pan Borneo Highway in Sabah and Sarawak

06-12-2022
Auto News
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.

04-12-2025
Auto News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News
Pan Borneo Highway Project Will Be Completed This Year - Nanta

Pan Borneo Highway Project Will Be Completed This Year - Nanta

98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.

13-02-2024
Auto News
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.

26-06-2024

Latest News

Auto News
Jaecoo J5 Poised To Galvanize O&J Malaysia In 2026

Jaecoo J5 Poised To Galvanize O&J Malaysia In 2026

Fresh off a breakout 2025, O&J Malaysia is turning to the J5 to sustain its rapid growth into the new year.

Auto News
Rapid KL Set To Restructure Bus Routes Starting Jan 16

Rapid KL Set To Restructure Bus Routes Starting Jan 16

Rapid KL will restructure selected bus and MRT feeder routes starting Jan 16, shifting low-demand services to on-demand vans.

12-01-2026
Auto News
PLUS Rolls Out ANPR Toll Pilot on Kedah–Penang Stretch

PLUS Rolls Out ANPR Toll Pilot on Kedah–Penang Stretch

PLUS Malaysia’s ANPR toll pilot delivers lane freedom while laying the groundwork for Multi Lane Free Flow tolling.

Auto News
Dec 2025 Vehicle Sales: Petrol Up 24.5%, xEV Hits Record 12.4%

Dec 2025 Vehicle Sales: Petrol Up 24.5%, xEV Hits Record 12.4%

Dec 2025 registrations rose 24.5%, lifting Malaysia’s auto market past 800,000 units as xEV share hit 12.4%.

Auto News
BHPetrol Unveils Refreshed BHPetromart and eNak Concept

BHPetrol Unveils Refreshed BHPetromart and eNak Concept

BHPetrol launches refreshed BHPetromart and eNak concepts, present more modern and customer-centric retail direction.

Auto News
Chery Kicks Off CNY With SUV Deals Starting RM88,800

Chery Kicks Off CNY With SUV Deals Starting RM88,800

Chery Malaysia launches Lunar New Year SUV deals, with top models discounted and extra perks for red cars.

09-01-2026
Auto News
Jetour T2 Secures 5-Star ASEAN NCAP Rating

Jetour T2 Secures 5-Star ASEAN NCAP Rating

Jetour T2 secures 5-Star ASEAN NCAP rating, setting a strong safety benchmark ahead of its expected Malaysian launch.

Auto News
MyDigital ID Becomes Mandatory Login For MyNIISe From Jan 15

MyDigital ID Becomes Mandatory Login For MyNIISe From Jan 15

From Jan 15, Malaysians must use MyDigital ID as the single login to access the MyNIISe immigration app.

09-01-2026

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.