Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

The construction of Phase 1A of the Pan Borneo Highway (LPB) in Sabah is taking longer than anticipated, as stated by Deputy Works Minister, Datuk Seri Ahmad Maslan. Difficult land acquisition circumstances and the drawn-out utility relocation process are to blame for these delays.
He emphasized that the landowners' resistance to cooperate has caused delays and the need for an extension of time, with some even going so far as to file a lawsuit, according to Bernama.
As of August 2024, 79.48% of the 15 work packages in Phase 1A had been completed. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 km,” said Ahmad Maslan.

“In addition, I hope the construction team can complete this project by meeting the quality, cost, and time standards set forth, in line with the MY Jalan KK programme’s goal of delivering comfortable and safe infrastructure for all Malaysia Madani people,” he added.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQT9370
SELANGOR
BSP2438
JOHOR
JYU7857
PULAU PINANG
PSB4246
PERAK
APG6447
PAHANG
CFG2184
KEDAH
KGF3280
NEGERI SEMBILAN
NEK1353
KOTA KINABALU
SJR3802
KUCHING
QAB5481N
Last updated 19 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Latest News
Journalists Say New 200L Petrol Cap Is 'Not Enough' To Do Their Jobs. Should They Get More?
Is 200L enough? 14 media clubs are pleading with the Gov to restore the 300L BUDI95 quota.
17-04-2026
From 300 to 8,000 Customers: The 15-Year Evolution of Auto Bavaria Kuala Lumpur
Auto Bavaria Kuala Lumpur celebrates 15 years! Discover how they grew from 300 to 8,000 customers and become Malaysia’s first EV-certified BMW dealer.
16-04-2026
Siti Nurhaliza Injured in 4-Vehicle Collision on MEX Highway
Datuk Seri Siti Nurhaliza involved in a multi-car accident at KM14.2 of the MEX Highway. Management confirms minor injuries and stable condition.
16-04-2026
Chery Battery Caught Fire for 80 Seconds: Here’s Why It Didn't Explode
Can a battery survive 1,000°C? Here's a technical deep dive into TIGGO 7 & 8 PHEV safety.
16-04-2026
B10 to B15: What the Biodiesel Shift Means for Your 4x4 Maintenance
Malaysia shifts to a B15 biodiesel mandate. Learn what this means for your 4x4 engine, maintenance costs, and why the government is making the move.
15-04-2026
Proton Makes History: Malaysia’s First Passenger Car Maker to Secure ISO 50001 Certification
PROTON makes history as Malaysia's first passenger car manufacturer to achieve ISO 50001: 2018 certification. Learn how energy efficiency is powering PROTON's future.
15-04-2026
15,370 Units & Counting: How Toyota is Outrunning the 'New Brand' Invasion in 2026
UMW Toyota Motor hits 15,370 units in Q1 2026. Discover how the 'Extra Mile' strategy and new hybrid Harrier are helping Toyota outrun new market rivals.
14-04-2026
Stable for Now, Critical by June: A Survival Guide to Malaysia's Mid-Year Energy Uncertainty
Malaysia’s fuel supply is "stable for now," but June is critical. Learn how the new diesel purchase limits in Sabah & Sarawak affect your travel and why T20 drivers should watch for RON 95 targeted subsidy announcements this year.
14-04-2026
Show More
trending_flat