Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

The construction of Phase 1A of the Pan Borneo Highway (LPB) in Sabah is taking longer than anticipated, as stated by Deputy Works Minister, Datuk Seri Ahmad Maslan. Difficult land acquisition circumstances and the drawn-out utility relocation process are to blame for these delays.
He emphasized that the landowners' resistance to cooperate has caused delays and the need for an extension of time, with some even going so far as to file a lawsuit, according to Bernama.
As of August 2024, 79.48% of the 15 work packages in Phase 1A had been completed. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 km,” said Ahmad Maslan.

“In addition, I hope the construction team can complete this project by meeting the quality, cost, and time standards set forth, in line with the MY Jalan KK programme’s goal of delivering comfortable and safe infrastructure for all Malaysia Madani people,” he added.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQN6329
SELANGOR
BSM8273
JOHOR
JYS3382
PULAU PINANG
PSA1697
PERAK
APF5734
PAHANG
CFF5301
KEDAH
KGE5401
NEGERI SEMBILAN
NEJ6419
KOTA KINABALU
SJQ5620
KUCHING
QAB3518N
Last updated 01 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Latest News
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Updated Fuel Prices From 26 February To 4 March
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 26 February to 4 March, 2026, the rates are as such.
25-02-2026
APAD to Investigate Kelana Jaya LRT Breakdowns, Prasarana Ordered to Explain
Transport Minister has directed APAD to probe recent Kelana Jaya LRT disruptions and warned action may be taken against Prasarana.
25-02-2026
Chery TIGGO CROSS HEV Grand Prize Winner Announced
Joan Gan became the grand prize winner of a Chery TIGGO CROSS HEV, chosen from over 1,300 participants in Chery Malaysia’s year-end PHEV lucky draw.
24-02-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
Johor–Singapore RTS Link Fare Expected at RM15 to RM22 Per Trip
Transport Minister Anthony Loke says the RTS Link could cost between RM15 and RM22 per journey, with fares to be announced in 2H2026.
23-02-2026
Show More
trending_flat