Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Image: Bernama
Earlier this week, Dewan Rakyat was informed that 15 out of 19 work packages for Phase 1B of the Pan Borneo Highway Project in Sabah are in the final stages of an open tender evaluation.
Datuk Seri Alexander Nanta Linggi announced that Letters of Acceptance (LOA) for these packages are anticipated to be issued to selected contractors in the third quarter (Q3) of this year. Four contractors have already been appointed to undertake construction work on four of the project’s packages, covering a total distance of 366.8 kilometers.
The project, with an estimated development cost of RM13.99 billion, is being funded through a hybrid financing method. This includes allocations from the Development Expenditure Budget and sukuk or bond issuances by DanaInfra Nasional Berhad.
Nanta stated that RM400 million has been allocated for preliminary works in 2024, based on current financial projections. He provided this information in response to a query from Isnaraissah Munirah Majlis (Warisan-Kota Belud) regarding the latest procurement types and funding sources for the project.
Datuk Seri Alexander Nanta Linggi (second from right).
Addressing the status of Work Package 9, which covers the route from Serusop to Pituru and has experienced delays, Nanta explained that the delays were to ensure that qualified and capable contractors are selected.
The final evaluation for this work package is ongoing, with the LOA expected to be issued in Q3 of this year. The project is slated for completion within three years following the issuance of the LOA.
Nanta emphasised the significance of the Sabah Pan Borneo Highway project, describing it as a high-impact initiative and a priority for the Works Ministry. The ministry is committed to ensuring the project's timely implementation to enhance Sabah’s federal road infrastructure network.
In response to a supplementary question from Datuk Seri Dr. Ronald Kiandee (PN-Beluran) about why the Pan Borneo Highway project in Sarawak is progressing faster than in Sabah, Nanta attributed the delays to several factors, including land acquisition issues, utility relocation, and contractor selection challenges. KR
Source: Bernama
Written By
Thoriq Azmi
Former DJ turned driver, rider and story-teller. I drive, I ride, and I string words together about it all. [#FuelledByThoriq] IG: https://www.instagram.com/fuelledbythoriq/
JPJ Running Numbers
KUALA LUMPUR
VPM6438
SELANGOR
BSG8065
JOHOR
JYE5498
PULAU PINANG
PRT1340
PERAK
ANY7602
PAHANG
CFD1022
KEDAH
KGB6557
NEGERI SEMBILAN
NEG6471
KOTA KINABALU
SJL9999*
KUCHING
QAB8584L
Last updated 06 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
Four New Proton e.MAS Dealerships In East Malaysia Announced
Proton e.MAS EV brand network grows further with four new East Malaysia dealerships announced.
10-02-2025
SDAC Ford Beefs Up East Malaysia Network, Includes Upgraded Sibu Outlet
SDAC Ford beefs up its network across East Malaysia led by upgraded dealership outlet in Sibu, Sarawak.
04-02-2025
2025 Proton X70 Launched In East Malaysia – From RM100,800 Onwards
Proton officially launches 2025 Proton X70 SUV in East Malaysia priced from RM100,800 onwards.
28-08-2024
Lexus Kota Kinabalu Officially Opens As Brand’s First Centre In Sabah
Lexus Malaysia sees network expand in East Malaysia as it marks the official opening of Lexus Kota Kinabalu.
05-12-2023
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
New Ford Ranger heads to East Malaysia this Sept and Oct
New generation Ford Ranger pick-up truck set for preview tour in East Malaysia ahead of its showroom launches there.
30-08-2022
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Latest News
Report: Malaysia Takes Lead in Southeast Asia’s Auto Market
Malaysia for the first time has surpassed Indonesia in quarterly car sales driven by strong local demand.
06-08-2025
Zero Tolerance Ahead For Untaxed Luxury Cars - Experts
Road safety experts are urging tougher penalties for luxury car owners who skip road tax and insurance.
06-08-2025
KTMB Train Schedule Upgrades Hit Speed Bumps
KTMB's schedule upgrades delayed by train shortages, limited track access, and speed restrictions.
06-08-2025
JPJeID Registration Now Available at Driving Institutes
JPJeID registration is now available at all driving institutes, streamlining access to MySIKAP and MyJPJ services.
05-08-2025
Couple Killed In Ford Mustang Crash Near Segamat
A married couple died after their Ford Mustang crashed into an electric pole along Jalan Segamat-Kuantan.
05-08-2025
Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?
The upcoming Proton e.MAS 5 is going on a ‘MISI 5’ national tour from August to October, 2025. Launch imminent?
05-08-2025
Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ
JPJ flags over 1,000 luxury cars, including Ferraris and Lambos, for missing road tax and insurance.
05-08-2025
MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept
MoF is finalising the targeted fuel subsidy system, with full rollout details expected by end-Sept.
05-08-2025
Show More
trending_flat