RTS Link 95% Complete, Service Operation Dec 2026

Kumeran Sagathevan

Share via

thumb-(2).jpg\

The Johor Bahru-Singapore Rapid Transit System (RTS) is making significant progress, with infrastructure works now 95% complete as of last November.

Deputy Transport Minister Datuk Hasbi Habibollah reported that the installation of key system components—such as rolling stock, signaling, power supply, distribution, and telecommunications—commenced earlier this month.


468720230_989936169841953_4527929699268960262_n.jpg468939605_989936213175282_4852271510332234597_n.jpg


So far, the government has allotted RM2.5 million for civil infrastructure on the Malaysian side of the RTS project, which is part of a bigger RM5.2 billion budget set out for the overall program in Malaysia.

Hasbi further stated that the RTS Link is designed to carry up to 100,000 passengers per day, with trains running at ideal intervals of 3.6 minutes during peak hours.


Screenshot-2024-12-12-231219.jpg


He also anticipates that the service would serve between 30,000 to 40,000 people each day in its first year of operation, which will commence on December 31, 2026.


RTS-Link-Alignment-Map-August-2023-EN-1536x891.png


Hasbi further noted that Malaysia Rapid Transit System Sdn Bhd (MRTS), which serves as InfraCo Malaysia, has given RTS Operations Pte Ltd (RTSO), the authorised service operator at the Wadi Hana Depot, early access to begin trackwork installation.



Source: BERNAMA
Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY762

SELANGOR

BSJ9016

JOHOR

JYK5764

PULAU PINANG

PRV4429

PERAK

APC3163

PAHANG

CFD9712

KEDAH

KGC8509

NEGERI SEMBILAN

NEH5261

KOTA KINABALU

SJN5354

KUCHING

QAB4754M

Last updated 03 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.20

+0.06

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.95

+0.06

EURO 5 B7

RM 3.15

+0.06

Last updated 30 Oct, 2025

Related News

Auto News

01-08-2025
Auto News

30-06-2025
Auto News

13-12-2024
Auto News

30-06-2025
Auto News

26-04-2024

Latest News

Auto News

RTS Link 65% Complete, First Train Arriving This Month

RTS Link connecting JB and SG is officially 65% complete, with the first train set expected to arrive this month.

03-11-2025
Auto News

Toyota Skill Contest 2025 Winners Announced

Winners for the Toyota Skill Contest 2025 organised by UMW Toyota Motor have been announced.

03-11-2025
Auto News

Budi95: Only 0.6% Max Out Quota, Govt Flags Unusual Purchase Near Border

Only 0.6% hit the 300L limit under BUDI95 programme with most recipients using only about 98 litres in Oct.

03-11-2025
Auto News

RM600 Million Super Magnet Plant Set to Power Malaysia’s EV Ambitions

RM600 million JS Link–Lynas investment drives Malaysia’s push in downstream REE processing for EV and clean energy sectors.

Auto News

Datuk Abdul Rashid Musa Returns To Proton As Deputy CEO

Datuk Abdul Rashid Musa returns to Proton as Deputy CEO, succeeding Roslan Abdullah.

03-11-2025
Auto News

ETS3 To Johor Bahru Set To Roll Out by Mid-December

The ETS3 line is set to launch by mid-Dec, extending the Electric Train Service from Gemas to JB.

03-11-2025
Auto News

Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents

The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.

Auto News

APAD Orders Aeroline To Halt Services Over Repeated Non-Compliance

Aeroline was directed to halt trips from Nov 6 to Dec 5 after failing to relocate to approved terminals as required by APAD.

03-11-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.