Loke: RTS Link 83% Complete & On Schedule For 2027 Operation

The Rapid Transit System (RTS) Link connecting Johor Bahru, Malaysia, and Singapore is at 83% completion stage and is on schedule to begin operations on Jan 1, 2027, says Minister of Transport, YB Anthony Loke.
Loke also confirmed that system installation by RTS Operations Systems Sdn Bhd (RTSO) is expected to commence by the end of this year.
According to him further, "The completion of the rail infrastructure will pave the way for RTSO to start installing critical system components, including trackwork, rolling stock, signalling systems, and power supply and distribution."
-full_normal.webp)
The announcement was made during a signing ceremony for the parking space sale and purchase agreement between Malaysia Rapid Transit System Sdn Bhd (MRTS) and Coronade Properties Sdn Bhd.
Furthermore, Loke also stated that the Customs, Immigration and Quarantine (CIQ) complex building at Bukit Chagar is at the superstructure building stage after which agencies should be able to start installing systems and equipment at the CIQ complex from Aug 2025.
On the matter of mitigating traffic congestion, Loke announced that the Ministry of Transport (MPT) is developing a traffic distribution plan for the Iskandar Malaysia region in collaboration with local authorities.

All the initiative aims to complement the ongoing infrastructure development in Johor Bahru and improve the overall traffic situation in the city and surrounding areas.
Loke also added that the access to the CIQ complex for vehicles would be through Jalan Tun Abdul Razak, Jalan Tebrau, Jalan Jim Quee, and Jalan Tunku Azizah therefore to address traffic issues, the government is prioritising an investment of over RM200 million in public transport infrastructure around Bukit Chagar.
-full_normal.webp)
It is expected that the investment on public transportation at the area is to cover current and future needs taking into account the potential growing number of daily RTS Link passengers.
Additionally, public support facilities, particularly parking spaces, are also being looked at with the construction of a new multi-storey Park 'N Ride facility at Bukit Chagar, offering 1,500 parking lots for RTS Link users on top of 781 extra parking spaces provided at Coronation Square.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQH2267
SELANGOR
BSL5627
JOHOR
JYP5108
PULAU PINANG
PRX4910
PERAK
APE531
PAHANG
CFE7267
KEDAH
KGD7601
NEGERI SEMBILAN
NEJ2480
KOTA KINABALU
SJP6851
KUCHING
QAB108N
Last updated 11 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
-0.02
RON 97
RM 3.11
-0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.89
-0.05
EURO 5 B7
RM 3.09
-0.05
Last updated 08 Jan, 2026
Related News
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Second RTS Link Train To Arrive At Wadi Hana Depot By End-September
The second RTS train set is heading to Johor Bahru for on-site testing, keeping the rail project on track for 2027 launch.
17-09-2025
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Malaysia–Singapore Ink Additional Agreement for RTS Link
Malaysia–Singapore reaffirm RTS Link with an Additional Agreement to enable single-point immigration clearance.
05-12-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Johor Questions Delay as Penang LRT Gets Federal Nod
Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.
21-11-2025
RTS Link: First Train Arrives In Johor, Testing Kicks Off At Wadi Hana Depot
Train Set 02 has arrived at Wadi Hana Depot, marking the start of critical testing and commissioning.
17-11-2025
Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch
Tunku Mahkota Ismail flags potential congestion around Bukit Chagar as the JB–SG RTS Link nears completion.
13-11-2025
Latest News
Dec 2025 Vehicle Sales: Petrol Up 24.5%, xEV Hits Record 12.4%
Dec 2025 registrations rose 24.5%, lifting Malaysia’s auto market past 800,000 units as xEV share hit 12.4%.
11-01-2026
BHPetrol Unveils Refreshed BHPetromart and eNak Concept
BHPetrol launches refreshed BHPetromart and eNak concepts, present more modern and customer-centric retail direction.
10-01-2026
Chery Kicks Off CNY With SUV Deals Starting RM88,800
Chery Malaysia launches Lunar New Year SUV deals, with top models discounted and extra perks for red cars.
09-01-2026
Jetour T2 Secures 5-Star ASEAN NCAP Rating
Jetour T2 secures 5-Star ASEAN NCAP rating, setting a strong safety benchmark ahead of its expected Malaysian launch.
09-01-2026
MyDigital ID Becomes Mandatory Login For MyNIISe From Jan 15
From Jan 15, Malaysians must use MyDigital ID as the single login to access the MyNIISe immigration app.
09-01-2026
Hyundai Tucson Headlines CNY Promotions, Priced From RM125,888
Hyundai Malaysia announced festive CNY promotions, sees Hyundai Tucson tagged from RM125,888 and more.
09-01-2026
Proton B&P Fire: No Casualties, Incident Under Investigation
Proton acknowledges fire incident that occurred at its B&P facility, says investigation underway and no casualties reported.
08-01-2026
Fallen Tree Disrupts KTMB Services Again, Safety Concerns Grow
Another track obstruction has caused major delays on KTM routes, renewing concerns over tree management and rail safety.
08-01-2026
Show More
trending_flat