Loke: RTS Link 83% Complete & On Schedule For 2027 Operation

Kumeran Sagathevan

Share via

RTS-Link-Alignment-Map-August-2023-EN-1536x891.png


The Rapid Transit System (RTS) Link connecting Johor Bahru, Malaysia, and Singapore is at 83% completion stage and is on schedule to begin operations on Jan 1, 2027, says Minister of Transport, YB Anthony Loke.

Loke also confirmed that system installation by RTS Operations Systems Sdn Bhd (RTSO) is expected to commence by the end of this year.

According to him further, "The completion of the rail infrastructure will pave the way for RTSO to start installing critical system components, including trackwork, rolling stock, signalling systems, and power supply and distribution."


RTS-(3).jpeg


The announcement was made during a signing ceremony for the parking space sale and purchase agreement between Malaysia Rapid Transit System Sdn Bhd (MRTS) and Coronade Properties Sdn Bhd.

Furthermore, Loke also stated that the Customs, Immigration and Quarantine (CIQ) complex building at Bukit Chagar is at the superstructure building stage after which agencies should be able to start installing systems and equipment at the CIQ complex from Aug 2025.

On the matter of mitigating traffic congestion, Loke announced that the Ministry of Transport (MPT) is developing a traffic distribution plan for the Iskandar Malaysia region in collaboration with local authorities.


Screenshot-2024-08-22-082754.jpg


All the initiative aims to complement the ongoing infrastructure development in Johor Bahru and improve the overall traffic situation in the city and surrounding areas.

Loke also added that the access to the CIQ complex for vehicles would be through Jalan Tun Abdul Razak, Jalan Tebrau, Jalan Jim Quee, and Jalan Tunku Azizah therefore to address traffic issues, the government is prioritising an investment of over RM200 million in public transport infrastructure around Bukit Chagar.


Komuter-RTS-Link-(3).jpg


It is expected that the investment on public transportation at the area is to cover current and future needs taking into account the potential growing number of daily RTS Link passengers.

Additionally, public support facilities, particularly parking spaces, are also being looked at with the construction of a new multi-storey Park 'N Ride facility at Bukit Chagar, offering 1,500 parking lots for RTS Link users on top of 781 extra parking spaces provided at Coronation Square.



Source: BERNAMA 

Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VQD4314

SELANGOR

BSK7926

JOHOR

JYM7016

PULAU PINANG

PRW5192

PERAK

APD3302

PAHANG

CFE4386

KEDAH

KGD4127

NEGERI SEMBILAN

NEH8729

KOTA KINABALU

SJP2679

KUCHING

QAB7369M

Last updated 13 Dec, 2025

Fuel Price

Petrol

RON 95

RM 2.64

-0.02

RON 97

RM 3.27

-0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.06

-0.02

EURO 5 B7

RM 3.26

-0.02

Last updated 11 Dec, 2025

Related News

Auto News
Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

The second RTS train set is heading to Johor Bahru for on-site testing, keeping the rail project on track for 2027 launch.

17-09-2025
Auto News
Malaysia–Singapore Ink Additional Agreement for RTS Link

Malaysia–Singapore Ink Additional Agreement for RTS Link

Malaysia–Singapore reaffirm RTS Link with an Additional Agreement to enable single-point immigration clearance.

Auto News
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke

Johor’s Elevated ART Moving Forward, RFP Under Review - Loke

Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.

24-11-2025
Auto News
Johor Questions Delay as Penang LRT Gets Federal Nod

Johor Questions Delay as Penang LRT Gets Federal Nod

Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.

Auto News
RTS Link: First Train Arrives In Johor, Testing Kicks Off At Wadi Hana Depot

RTS Link: First Train Arrives In Johor, Testing Kicks Off At Wadi Hana Depot

Train Set 02 has arrived at Wadi Hana Depot, marking the start of critical testing and commissioning.

17-11-2025
Auto News
Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch

Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch

Tunku Mahkota Ismail flags potential congestion around Bukit Chagar as the JB–SG RTS Link nears completion.

13-11-2025
Auto News
RTS Link 65% Complete, First Train Arriving This Month

RTS Link 65% Complete, First Train Arriving This Month

RTS Link connecting JB and SG is officially 65% complete, with the first train set expected to arrive this month.

03-11-2025
Auto News
Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

The second RTS train set is heading to Johor Bahru for on-site testing, keeping the rail project on track for 2027 launch.

17-09-2025

Latest News

Auto News
Govt Rules Out Tiered RON95 Pricing After 300 litres

Govt Rules Out Tiered RON95 Pricing After 300 litres

Government rules out tiered RON95 prices under BUDI95, keeps RM1.99 for first 300 litres

12-12-2025
Auto News
Hyundai Partners EON, Expands Local Network

Hyundai Partners EON, Expands Local Network

Hyundai and EON have signed a LOI to open two new dealerships in Klang Valley and Penang.

Auto News
Perodua Traz/Nexis D66B Set to Debut on December 17

Perodua Traz/Nexis D66B Set to Debut on December 17

The long-awaited Perodua Traz/Nexis D66B SUV is set to make its official debut later on December 17, 2025.

12-12-2025
Auto News
Gemas-JB Electrified Train Cuts KL-Johor Travel To 4 Hours

Gemas-JB Electrified Train Cuts KL-Johor Travel To 4 Hours

The new electrified Gemas-Johor Bahru train line slashes travel time from KL to Johor to just 4 hours 20 minutes.

12-12-2025
Auto News
PLUS and KEC Ink MoU to Advance Smart Mobility

PLUS and KEC Ink MoU to Advance Smart Mobility

PLUS and KEC Smart Mobility signs agreement to develop smarter, greener and more connected expressway operations.

Auto News
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025
Auto News
CKD GWM WEY G9 Rolls Out at New EPMB Plant

CKD GWM WEY G9 Rolls Out at New EPMB Plant

CKD GWM WEY G9 rolls out from EPMB’s new Phase 2 plant, strengthening Malaysia’s NEV localisation ecosystem.

Auto News
Proton Shifts 13,451 Units Throughout Nov 2025

Proton Shifts 13,451 Units Throughout Nov 2025

Proton closes Nov 2025 by shifting 13,451 units, touts to be “on target” for record exports growth too.

11-12-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.