Loke: RTS Link 83% Complete & On Schedule For 2027 Operation

The Rapid Transit System (RTS) Link connecting Johor Bahru, Malaysia, and Singapore is at 83% completion stage and is on schedule to begin operations on Jan 1, 2027, says Minister of Transport, YB Anthony Loke.
Loke also confirmed that system installation by RTS Operations Systems Sdn Bhd (RTSO) is expected to commence by the end of this year.
According to him further, "The completion of the rail infrastructure will pave the way for RTSO to start installing critical system components, including trackwork, rolling stock, signalling systems, and power supply and distribution."
-full_normal.webp)
The announcement was made during a signing ceremony for the parking space sale and purchase agreement between Malaysia Rapid Transit System Sdn Bhd (MRTS) and Coronade Properties Sdn Bhd.
Furthermore, Loke also stated that the Customs, Immigration and Quarantine (CIQ) complex building at Bukit Chagar is at the superstructure building stage after which agencies should be able to start installing systems and equipment at the CIQ complex from Aug 2025.
On the matter of mitigating traffic congestion, Loke announced that the Ministry of Transport (MPT) is developing a traffic distribution plan for the Iskandar Malaysia region in collaboration with local authorities.

All the initiative aims to complement the ongoing infrastructure development in Johor Bahru and improve the overall traffic situation in the city and surrounding areas.
Loke also added that the access to the CIQ complex for vehicles would be through Jalan Tun Abdul Razak, Jalan Tebrau, Jalan Jim Quee, and Jalan Tunku Azizah therefore to address traffic issues, the government is prioritising an investment of over RM200 million in public transport infrastructure around Bukit Chagar.
-full_normal.webp)
It is expected that the investment on public transportation at the area is to cover current and future needs taking into account the potential growing number of daily RTS Link passengers.
Additionally, public support facilities, particularly parking spaces, are also being looked at with the construction of a new multi-storey Park 'N Ride facility at Bukit Chagar, offering 1,500 parking lots for RTS Link users on top of 781 extra parking spaces provided at Coronation Square.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQG7239
SELANGOR
BSL4553
JOHOR
JYP3080
PULAU PINANG
PRX3634
PERAK
APD8650
PAHANG
CFE6705
KEDAH
KGD6933
NEGERI SEMBILAN
NEJ2064
KOTA KINABALU
SJP6361
KUCHING
QAB9640M
Last updated 04 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.56
RON 97
RM 3.16
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
EURO 5 B7
RM 3.14
Last updated 01 Jan, 2026
Related News
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Second RTS Link Train To Arrive At Wadi Hana Depot By End-September
The second RTS train set is heading to Johor Bahru for on-site testing, keeping the rail project on track for 2027 launch.
17-09-2025
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Malaysia–Singapore Ink Additional Agreement for RTS Link
Malaysia–Singapore reaffirm RTS Link with an Additional Agreement to enable single-point immigration clearance.
05-12-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Johor Questions Delay as Penang LRT Gets Federal Nod
Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.
21-11-2025
RTS Link: First Train Arrives In Johor, Testing Kicks Off At Wadi Hana Depot
Train Set 02 has arrived at Wadi Hana Depot, marking the start of critical testing and commissioning.
17-11-2025
Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch
Tunku Mahkota Ismail flags potential congestion around Bukit Chagar as the JB–SG RTS Link nears completion.
13-11-2025
Latest News
BESRAYA KM9.5 U-Turn Closed for Six Months
BESRAYA has closed the KM9.5 U-turn in both directions for six months to ease congestion and improve traffic flow.
05-01-2026
Proton Shifted 157,976 Units In 2025, Charts 3.3% Growth & New Export Record
Proton closes 2025 on a high by shifting 157,976 units, logging a 3.3% growth plus a new export record.
02-01-2026
KSM Lowers Kia Spare Parts Price By 15%, Brings New Incentives Too
New prices aside, Kia Sales Malaysia (KSM) also lower Kia spare parts prices by 15%, announces a slew of new incentives too.
02-01-2026
Prasarana Moved 1.54 Million People on New Year’s Eve
Prasarana moved 1.54 million people on New Year’s Eve, marking its highest single-day ridership.
02-01-2026
Updated Fuel Prices From 1 To 7 January
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 1 to 7 January, 2026, the rates are as such.
31-12-2025
Selangor Police Collect RM19.5 Million During Summons Discount Period
More than 258,000 traffic summonses were settled in Selangor during the two-month 70% discount programme, collecting RM19.5 million.
31-12-2025
Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?
The traffic summons discount is over, millions of fines remain unpaid, and stricter penalties kick in next year
31-12-2025
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
Show More
trending_flat