KL-Karak Highway Widening Project Will Begin End-Feb
-full_normal.jpg)
According to State Infrastructure and Agriculture Exco Datuk Izham Hashim, construction of the KL-Karak Highway (KLK) will commence at the end of this month and is expected to be completed in four years.
Izham responded to questions from Muhammad Hilman Idham (PN-Gombak Setia) about the implementation of the KLK development at the Selangor State Assembly. He confirmed that the federal government has approved the KLK widening project, which began preparatory construction last month and is slated to be finished by 2029. "The implementation of this project will provide great benefits to highway users, especially in overcoming traffic congestion issues and improving safety features," he stated.
-full_normal.jpg)
According to Izham, the project will span 45.3 kilometres (km) and include lane additions in both directions, beginning at the Gombak Toll Plaza and ending in Bentong, Pahang. Additionally, he stated that the KLK widening would be carried out inside the current highway alignment or corridor, avoiding the need for additional property acquisition.
The RM2.1 billion project, which will be completely funded by concessionaire AFA Prime Berhad, comes after the federal government approved the widening project in early 2024 as a long-term solution to relieve traffic congestion in the area.
Upon completion in 2029, the road will have four lanes running in each direction from Gombak to Genting Sempah, and three lanes in each direction from Genting Sempah to Bentong. While the existing tunnel will remain unchanged, a new tunnel will be constructed 30 meters to its left, resulting in a total of three tunnels.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRC7298
SELANGOR
BSQ8606
JOHOR
JYY8209
PULAU PINANG
PSD1520
PERAK
APJ2690
PAHANG
CFG7951
KEDAH
KGG5423
NEGERI SEMBILAN
NEK6708
KOTA KINABALU
SJS4392
KUCHING
QAB152P
Last updated 22 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Review Underway For 12 Loss-Making Highways - Nanta
Works Ministry will conduct a detailed review of the issue involving 12 highway concessions that recorded losses last year.
28-11-2025
Deepavali 2025: AFA Issues TTA For KL-Karak Highway & LPT 1
AFA issues KLK and LPT1 Deepavali 2025 TTA as traffic is projected to rise by 59%.
16-10-2025
AFA PRIME Bhd Issues TTA for KLK & LPT 1
AFA PRIME Bhd enhances traffic measures to ensure a smooth and safe Hari Raya Aidilfitri travel experience.
25-03-2025
West Ipoh Span Expressway (WISE) Construction Set to Commence This Year
The WISE highway construction is expected to begin this year pending concession agreement signing.
23-07-2024
ANIH Berhad Issues TTA For KLK & LPT1 Highways - 1 Million Vehicles Expected
Kuala Lumpur - Karak Highway (KLK) and the East Coast Expressway Phase 1 (LPT1), has issued a Travel Time Advisory (TTA) covering the period from November 10 to 13, 2023 - 1 Million users expected
10-11-2023
RM2.1 Billion KL-Karak Widening Project Starts End-Feb
KL-Karak Highway widening begins this Feb, aiming for 2029 completion.
14-02-2025
AFA Allocates RM2.1b For KL-Karak Highway Widening Project; Scheduled To Begin Jan 2025
AFA allocates RM2.1 billion for the KL-Karak highway widening project which is set to begin in Jan 2025.
29-11-2024
KL-Karak Highway Will Be Widened With Additional Lanes This Year
A portion of the Lumpur-Karak highway will be widened and additional lanes added this year.
19-05-2023
Latest News
42 Clauses Are Changing: M'sia Is Facing Its Biggest Road Law Overhaul Since 2020, And Yes, It Affects Your Saman
Malaysia is introducing 42 new clauses to the Road Transport Act in its biggest traffic law overhaul since 2020. Here is how it affects your fines and roadblocks.
19-06-2026
Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped
Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.
18-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech
At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.
18-06-2026
It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up
Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.
17-06-2026
Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers
Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.
12-06-2026
15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage
Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.
10-06-2026
Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30
Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.
09-06-2026
Show More
trending_flat