KL-Karak Highway Widening Project Will Begin End-Feb
-full_normal.jpg)
According to State Infrastructure and Agriculture Exco Datuk Izham Hashim, construction of the KL-Karak Highway (KLK) will commence at the end of this month and is expected to be completed in four years.
Izham responded to questions from Muhammad Hilman Idham (PN-Gombak Setia) about the implementation of the KLK development at the Selangor State Assembly. He confirmed that the federal government has approved the KLK widening project, which began preparatory construction last month and is slated to be finished by 2029. "The implementation of this project will provide great benefits to highway users, especially in overcoming traffic congestion issues and improving safety features," he stated.
-full_normal.jpg)
According to Izham, the project will span 45.3 kilometres (km) and include lane additions in both directions, beginning at the Gombak Toll Plaza and ending in Bentong, Pahang. Additionally, he stated that the KLK widening would be carried out inside the current highway alignment or corridor, avoiding the need for additional property acquisition.
The RM2.1 billion project, which will be completely funded by concessionaire AFA Prime Berhad, comes after the federal government approved the widening project in early 2024 as a long-term solution to relieve traffic congestion in the area.
Upon completion in 2029, the road will have four lanes running in each direction from Gombak to Genting Sempah, and three lanes in each direction from Genting Sempah to Bentong. While the existing tunnel will remain unchanged, a new tunnel will be constructed 30 meters to its left, resulting in a total of three tunnels.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQQ4305
SELANGOR
BSN3768
JOHOR
JYT2497
PULAU PINANG
PSA5364
PERAK
APF9567
PAHANG
CFF7631
KEDAH
KGE7615
NEGERI SEMBILAN
NEJ7645
KOTA KINABALU
SJQ7973
KUCHING
QAB4080N
Last updated 17 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Review Underway For 12 Loss-Making Highways - Nanta
Works Ministry will conduct a detailed review of the issue involving 12 highway concessions that recorded losses last year.
28-11-2025
Deepavali 2025: AFA Issues TTA For KL-Karak Highway & LPT 1
AFA issues KLK and LPT1 Deepavali 2025 TTA as traffic is projected to rise by 59%.
16-10-2025
AFA PRIME Bhd Issues TTA for KLK & LPT 1
AFA PRIME Bhd enhances traffic measures to ensure a smooth and safe Hari Raya Aidilfitri travel experience.
25-03-2025
West Ipoh Span Expressway (WISE) Construction Set to Commence This Year
The WISE highway construction is expected to begin this year pending concession agreement signing.
23-07-2024
ANIH Berhad Issues TTA For KLK & LPT1 Highways - 1 Million Vehicles Expected
Kuala Lumpur - Karak Highway (KLK) and the East Coast Expressway Phase 1 (LPT1), has issued a Travel Time Advisory (TTA) covering the period from November 10 to 13, 2023 - 1 Million users expected
10-11-2023
RM2.1 Billion KL-Karak Widening Project Starts End-Feb
KL-Karak Highway widening begins this Feb, aiming for 2029 completion.
14-02-2025
AFA Allocates RM2.1b For KL-Karak Highway Widening Project; Scheduled To Begin Jan 2025
AFA allocates RM2.1 billion for the KL-Karak highway widening project which is set to begin in Jan 2025.
29-11-2024
KL-Karak Highway Will Be Widened With Additional Lanes This Year
A portion of the Lumpur-Karak highway will be widened and additional lanes added this year.
19-05-2023
Latest News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Show More
trending_flat