ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
Anis
9-4-2025
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.
MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.
The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPC873
SELANGOR
BSE4402
JOHOR
JXW4803
PULAU PINANG
PRQ3417
PERAK
ANV3402
PAHANG
CFB6571
KEDAH
KGA4221
NEGERI SEMBILAN
NEF7075
KOTA KINABALU
SJK7319
KUCHING
QAB3039L
Last updated 01 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
EURO 5 B7
RM 3.08
Last updated 01 May, 2025
Related News
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties
The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.
29-04-2025
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete
ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.
18-04-2025
ECRL 80% Complete, Shifting To Above-Ground Work
The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.
27-03-2025
MOT Developing Policy To Encourage Cargo Companies To Use ECRL
MOT will implement a policy to incentivize the industry to use the ECRL service.
06-03-2025
ECRL: Port Klang Stretch Will Be Upgraded to Double-Track System
The 25-KM stretch of the ECRL at Port Klang will be upgraded to a double-track system with no extra cost, MOT says.
18-02-2025
ECRL: Phase 1 Testing & Certification Will Begin in June 2026
The testing and certification phase for the ECRL Phase 1 from Kota Bharu to Gombak will begin in June 2026.
05-02-2025
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion
ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.
16-01-2025
New ECRL Train & Logo Launched - Malaysia-China 50:50 Partnership
YB Loke launches new ECRL train design and logo, also details the 50:50 partnership terms.
19-12-2024
Latest News
Unchanged Fuel Prices From 01 To 07 May
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 01 to 07 May, 2025, the rates are as such.
30-04-2025
Jazeman Jaafar Set For Super GT Malaysia 2025 Wildcard Entry
Local racing ace Jazeman Jaafar enters upcoming Super GT Malaysia 2025 round as wildcard with co-driver Kerong Li under EBM banner.
30-04-2025
Young Drivers Shine In Vios Challege 2025 Season Opener
Young drivers shined in season-opening weekend of the Vios Challenge 2025 held last weekend at Petronas SIC.
30-04-2025
Travellers To Thailand Must Fill Out TDAC Starting May 1
Malaysians intending a quick trip to Thailand are reminded to complete their digital arrival card application starting Thursday, May 1st.
30-04-2025
Counterfeit Engine Oil Syndicate Busted
Authorities raid three premises in Ara Damansara and Kepong, uncovering a syndicate that repackages and sells counterfeit engine oil.
30-04-2025
PIAM: Motor and EV Insurance Up 6.7% in 2024
Motor insurance surged in 2024, adding RM651.1 million in premiums, EV coverage sets the tone for 2025, touts PIAM.
30-04-2025
MOT Lowers School Zone Speed Limit To 30 KM/H
The government will soon gazette new 30 KM/H speed limit in school zones.
30-04-2025
JPJ Seizes Two Lorries After Drivers, Owner Obstruct Enforcement
JPJ seized two lorries after their drivers and owner obstructed enforcement by spilling sand, causing major disruption.
29-04-2025
Show More
trending_flat