ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.
MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.
The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPR4415
SELANGOR
BSH5894
JOHOR
JYG3326
PULAU PINANG
PRT7834
PERAK
APA9719
PAHANG
CFD4090
KEDAH
KGC1694
NEGERI SEMBILAN
NEG9537
KOTA KINABALU
SJM4891
KUCHING
QAB1247M
Last updated 04 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.16
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
EURO 5 B7
RM 3.08
Last updated 04 Sep, 2025
Related News
Govt Studying ECRL Extension to Thai Border Town Rantau Panjang
Anwar says the ECRL extension to Rantau Panjang could open new growth at the Malaysia–Thailand border.
03-09-2025
Zafrul: ECRL Will Spur Jobs, Investments Along the East Coast
Tengku Zafrul says the ECRL will not only improve connectivity but also drive growth across the East Coast.
03-09-2025
ECRL Extension To Thailand Faces Track, Flood Challenges – Loke
Transport Minister says extending the ECRL to Thailand faces challenges like track differences and flood risks.
20-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End
ECRL is expected to receive its first two EMU trains and two E-Loco by the end of this year.
16-07-2025
ECRL Breakthrough: Genting Tunnel Becomes SEA’s Longest Rail Tunnel
The 16.39KM Genting Tunnel is now Southeast Asia’s longest rail tunnel, marking a major leap for ECRL.
14-07-2025
Latest News
PMX: Proton’s International Success a Model for Malaysia
PM Datuk Seri Anwar Ibrahim says Proton’s success abroad in Egypt proves the brand is ready to expand into more markets.
04-09-2025
New Proton Saga ‘Teased’ During EV Factory Launch – ADAS Confirmed
Upcoming next-gen Proton Saga ‘teased’ during new EV factory launch, basic ADAS confirmed, along with other bits.
04-09-2025
Proton Launches New EV Plant in Tanjung Malim – e.MAS 7 CKD Begins
Proton has launched its first EV plant in Tanjung Malim, with the local assembly of the e.MAS 7 EV already started.
04-09-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
KPDN Tightens RON95 Subsidy Control with MyKad Verification via eCOSS
Malaysians will soon need to verify their MyKad through the eCOSS system to purchase subsidised RON95 petrol.
04-09-2025
Selangor Eyes DRT Comeback By Year-End
State govt fine-tuning plans to relaunch Selangor Mobility’s on-demand transit service after pilot phase ended last year.
04-09-2025
KLIA Aerotrain Breaks Down Hours After Back-in-Schedule Announcement
Fresh off nearly two weeks of “fine-tuning” maintenance to boost reliability, KLIA’s aerotrain stalled at 1.36PM, service only resumed at 5.38PM.
04-09-2025
Pos Malaysia Expands EV Fleet with 136 New Electric Vans
Pos Malaysia has expanded its EV fleet by adding 136 new all-electric Maxus eDeliver 3 electric vans.
04-09-2025
Show More
trending_flat