ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
-full_normal.jpg)
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.

MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices. 
The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
-full_normal.jpg)
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQC7183
SELANGOR
BSK6631
JOHOR
JYM4142
PULAU PINANG
PRW4018
PERAK
APD1829
PAHANG
CFE3853
KEDAH
KGD3403
NEGERI SEMBILAN
NEH8103
KOTA KINABALU
SJP1920
KUCHING
QAB7062M
Last updated 06 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.66
+0.03
RON 97
RM 3.29
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.08
EURO 5 B7
RM 3.28
Last updated 04 Dec, 2025
Related News
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
Latest News
RON95 Subsidy Could Save Govt RM4B Without Raising Debt - MOF
RON95 subsidy rationalisation could save the government up to RM4 billion a year while keeping national debt stable.
05-12-2025
Malaysia-Singapore Cross-Border Taxis Quota Rises To 500
Licensed cross-border taxis between Malaysia and Singapore will increase from 200 to 500 per country, with drop-offs allowed anywhere.
05-12-2025
Maxim Cleared To Resume E-Hailing Operations Nationwide
Maxim Malaysia has officially received approval from APAD to continue its e-hailing services.
05-12-2025
Malaysia–Singapore Ink Additional Agreement for RTS Link
Malaysia–Singapore reaffirm RTS Link with an Additional Agreement to enable single-point immigration clearance.
05-12-2025
US Embracing Compact Cars: Opportunities for Malaysian Automakers?
As the US embraces compact cars, new opportunities are emerging for automakers worldwide.
05-12-2025
Honda Malaysia Rewards 25th Anniversary Campaign Winners
First two lucky winners in Honda Malaysia 25th Anniversary Campaign effort take delivery of their grand prize cars.
04-12-2025
UMW Toyota Motor Hits 8,574 Sales In November
UMWT sold 8,574 vehicles in Nov, bringing its year-to-date total to 88,133.
04-12-2025
Proton 2030 Roadmap: 330K Sales, 30% NEVs in Sight
Proton outlines 2030 sales targets of 330,000 units, and it seeks to have 30% of it stemming from NEVs.
04-12-2025
Show More
trending_flat