ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.
MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.
The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPV9537
SELANGOR
BSJ5248
JOHOR
JYJ5182
PULAU PINANG
PRU9256
PERAK
APB8324
PAHANG
CFD7831
KEDAH
KGC6511
NEGERI SEMBILAN
NEH4002
KOTA KINABALU
SJN2048
KUCHING
QAB3657M
Last updated 21 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.18
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.93
EURO 5 B7
RM 3.13
Last updated 16 Oct, 2025
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared
Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.
22-09-2025
ECRL Cites Potential Delay From Escalated Cable and Wire Theft
ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.
11-09-2025
Govt Studying ECRL Extension to Thai Border Town Rantau Panjang
Anwar says the ECRL extension to Rantau Panjang could open new growth at the Malaysia–Thailand border.
03-09-2025
Zafrul: ECRL Will Spur Jobs, Investments Along the East Coast
Tengku Zafrul says the ECRL will not only improve connectivity but also drive growth across the East Coast.
03-09-2025
ECRL Extension To Thailand Faces Track, Flood Challenges – Loke
Transport Minister says extending the ECRL to Thailand faces challenges like track differences and flood risks.
20-08-2025
Latest News
MAHB Calls In Independent Assessor After Latest KLIA Aerotrain Glitch
MAHB will appoint an independent assessor to review the KLIA aerotrain’s power system after another breakdown on Wed.
21-10-2025
Budi95: 300-Litre Quota Sufficient for Most Malaysians
Government data shows 95% of Malaysians use less than 180 litres of RON95 monthly.
20-10-2025
Chery Malaysia Initiates Chery Certified Sales Professional Programme
Chery Malaysia reinforces commitment to excellence through Chery Certified Sales Professional (CCSP) Programme.
18-10-2025
Omoda | Jaecoo Chart Record Exports and NEV Growth
Omoda | Jaecoo ends Sept 2025 with record global sales, driven by strong demand for its hybrid and new energy models.
17-10-2025
ASEAN 2025: Rapid Rail Steps Up With More Trains, Safety Upgrades
Rapid Rail will boost train frequency and safety measures during the ASEAN Summit to ease travel disruptions.
17-10-2025
MBPJ Standardises Reserved Bays into 24-Hour Parking
MBPJ converting 1,054 reserved and blue-lined bays into 24-hour spaces rented at RM400 monthly.
17-10-2025
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Chery Super Hybrid Showcased In 20,000 KM Global Endurance Drive
Chery’s latest global endurance drive put its Super Hybrid lineup and tech to the ultimate test.
17-10-2025
Show More
trending_flat