ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
-full_normal.jpg)
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.

MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.

The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
-full_normal.jpg)
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQJ4751
SELANGOR
BSL8945
JOHOR
JYQ2710
PULAU PINANG
PRX9482
PERAK
APE4703
PAHANG
CFE8867
KEDAH
KGD9571
NEGERI SEMBILAN
NEJ3497
KOTA KINABALU
SJP8418
KUCHING
QAB760N
Last updated 23 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Latest News
UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors
Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.
23-01-2026
Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign
Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.
23-01-2026
LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch
LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.
23-01-2026
JPJ Lifts Travel Proof Rule for Physical Driving Licence
JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.
23-01-2026
KL’s Lalaport Hub Nears Approval for Singapore Express Buses
KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.
22-01-2026
Overloaded Lorry Crackdown Reduces Road Deaths
Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.
22-01-2026
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Puspakom - New Brake Inspection Rules for Heavy Vehicles
Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.
22-01-2026
Show More
trending_flat