ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
-full_normal.jpg)
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.

MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.

The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
-full_normal.jpg)
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQP6209
SELANGOR
BSN2060
JOHOR
JYS8435
PULAU PINANG
PSA4240
PERAK
APF7955
PAHANG
CFF6690
KEDAH
KGE6929
NEGERI SEMBILAN
NEJ7247
KOTA KINABALU
SJQ7003
KUCHING
QAB3909N
Last updated 11 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Show More
trending_flat