ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

Anis

Share via


Muhammad-Kifli-Ma-Hassan.-(11).png
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.

The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.

Untitled60.jpg


MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.

Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices. terowong-baru-1.jpg


The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.

"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.

Muhammad-Kifli-Ma-Hassan.-(10).png

China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.

The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028. download-(19).jpg


Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPG2486

SELANGOR

BSF4611

JOHOR

JYA4079

PULAU PINANG

PRR4578

PERAK

ANW6126

PAHANG

CFC1078

KEDAH

KGA9157

NEGERI SEMBILAN

NEG2183

KOTA KINABALU

SJL2710

KUCHING

QAB5039L

Last updated 16 Jun, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.07

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.74

EURO 5 B7

RM 2.94

Last updated 12 Jun, 2025

Related News

Auto News
ECRL: KotaSAS Station System Installation Completed

ECRL: KotaSAS Station System Installation Completed

KotaSAS Station becomes first along ECRL route to complete installation of critical systems.

30-05-2025
Auto News
MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail

MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail

MiTRANS: Extending the ECRL to Sungai Golok would complete a key missing link in the ASEAN rail network.

22-05-2025
Auto News
Thai Ambassador Proposes ECRL Extension To Sungai Golok

Thai Ambassador Proposes ECRL Extension To Sungai Golok

Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.

16-05-2025
Auto News
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.

06-05-2025
Auto News
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.

29-04-2025
Auto News
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.

18-04-2025
Auto News
ECRL 80% Complete, Shifting To Above-Ground Work

ECRL 80% Complete, Shifting To Above-Ground Work

The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.

27-03-2025
Auto News
MOT Developing Policy To Encourage Cargo Companies To Use ECRL

MOT Developing Policy To Encourage Cargo Companies To Use ECRL

MOT will implement a policy to incentivize the industry to use the ECRL service.

06-03-2025

Latest News

Auto News
Gerik Crash: No signs Of Brake, Steering Failure

Gerik Crash: No signs Of Brake, Steering Failure

Preliminary investigations into the fatal June 9 bus crash in Gerik, have not revealed any technical malfunctions.

15-06-2025
Auto News
Gerik Crash: Motac Urges Return Of Authority Over Tourism Vehicles

Gerik Crash: Motac Urges Return Of Authority Over Tourism Vehicles

In response to the fatal bus crash involving UPSI students, Motac aimed to regain control over tourism transport for safety reasons.

13-06-2025
Auto News
Loke: KEJARA System A Failure, Major Revamp Coming

Loke: KEJARA System A Failure, Major Revamp Coming

KEJARA system has failed to penalise traffic offenders who ignore their summonses, admits Loke.

13-06-2025
Auto News
New MD & Co-MD Announced At VPCM and PHSAM

New MD & Co-MD Announced At VPCM and PHSAM

Volkswagen Passenger Cars Malaysia (VPCM) and PHS Automotive Malaysia (PHSAM) announces new MD and co-MD.

13-06-2025
Auto News
New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

Speed Limitation Device (SLD) will be compulsory for commercial vehicles starting Oct 2025 to meet national road safety targets.

13-06-2025
Auto News
FRU Crash: Lorry Exceeds Weight Limit By 70%

FRU Crash: Lorry Exceeds Weight Limit By 70%

Investigation into the fatal Teluk Intan road accident that killed nine FRU personnel last month found the tipper lorry was overloaded.

13-06-2025
Auto News
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.

13-06-2025
Auto News
Maxim Malaysia Files Final Appeal To APAD

Maxim Malaysia Files Final Appeal To APAD

Maxim Malaysia has made an appeal to APAD, requesting permission to maintain its operations within the Malaysian market.

12-06-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.