ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
-full_normal.jpg)
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.

MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.

The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
-full_normal.jpg)
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat