ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
The East Coast Rail Link (ECRL) project is on track to achieve its target of 41 tunnel breakthroughs by Q3 2025, as Malaysia Rail Link Sdn Bhd (MRL) announces the completion of excavation work for 38 tunnels along the rail line.
The Serendah 1 Tunnel, spanning 3.50 kilometers, reached a significant milestone with its breakthrough on April 7th, two months ahead of schedule. This accomplishment follows two other notable breakthroughs in Selangor earlier in the week, bringing the total number of completed tunnel excavations to 38. The day before, on April 6th, the 189-meter Rawang-Bestari Jaya Tunnel marked the 37th breakthrough in the project.
MRL announced that only three tunnels remain under excavation following the breakthrough of two tunnels: the 9.85km Serendah 2 Tunnel and the 16.39km twin-bore Genting Tunnel. The Serendah 2 Tunnel is expected to be completed by the third quarter of 2025. The Genting Tunnel, which is being excavated using two advanced tunnel boring machines (TBMs), is expected to be completed by mid-2025.
Datuk Seri Darwis Abdul Razak, CEO of MRL, attributed the successful excavation of the Serendah 1 and Rawang-Bestari Jaya tunnels to the ECRL project team's exceptional work, advanced tunneling techniques, and safe construction practices.
The seamless excavation of the 3.50 km Serendah 1 Tunnel marks a significant achievement for the company, crucial to the ECRL alignment connecting Gombak to Port Klang in Selangor, he says.
"Some 512,582 cubic metres of soil and rock were safely removed with minimal ground movement and minor inconvenience to the road users throughout the excavation period using the drill-and-blast method," he said.
China Communications Construction (ECRL) Sdn Bhd managing director Deng Bo affirmed the company's dedication to maintaining momentum and ensuring punctual delivery as the ECRL construction progresses into the new phase of system installations.
The first phase of the ECRL, connecting Kota Bharu, Kelantan to the Gombak Integrated Terminal, Selangor, is scheduled for completion in December 2026, with operations commencing in January 2027. The second phase, linking Gombak and Port Klang, is projected to be finalized by December 2027, and fully operational by January 2028.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPR2524
SELANGOR
BSH5324
JOHOR
JYG2393
PULAU PINANG
PRT7359
PERAK
APA8665
PAHANG
CFD3872
KEDAH
KGC1465
NEGERI SEMBILAN
NEG9344
KOTA KINABALU
SJM4611
KUCHING
QAB1045M
Last updated 02 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.16
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.03
EURO 5 B7
RM 3.08
+0.03
Last updated 28 Aug, 2025
Related News
ECRL Extension To Thailand Faces Track, Flood Challenges – Loke
Transport Minister says extending the ECRL to Thailand faces challenges like track differences and flood risks.
20-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End
ECRL is expected to receive its first two EMU trains and two E-Loco by the end of this year.
16-07-2025
ECRL Breakthrough: Genting Tunnel Becomes SEA’s Longest Rail Tunnel
The 16.39KM Genting Tunnel is now Southeast Asia’s longest rail tunnel, marking a major leap for ECRL.
14-07-2025
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31
Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.
10-07-2025
ECRL Project 85% Completed
The ECRL is 85% complete and on track to start operations by early 2027, says Chief Secretary.
09-07-2025
Latest News
Own Damage Knock for Knock Brings Faster Repair Settlements
Drivers not at fault in accidents can now claim Own Damage Knock for Knock repair from insurers, with NCDs left untouched.
30-08-2025
Delayed EKVE Phase One Finally Opened With 30-Day Toll-Free Span
Phase one of EKVE finally opens six years behind schedule, concessionaires offer 30-day toll-free run.
29-08-2025
New Isuzu 3S Outlet Opens in Kuantan, Pahang
Isuzu Malaysia sees local network strengthened with newly opened 3S centre in Kuantan, Pahang.
29-08-2025
Road Closures In Seremban Ahead Of Merdeka
Several major roads in Seremban will close this week for National Day rehearsals and celebrations.
29-08-2025
Malaysians Told To Ignore False Claims Of RON95 Rationing
The Finance Ministry has denied viral claims of RON95 rationing and urged Malaysians to beware of suspicious messages and links.
29-08-2025
Johor Speeds Up Road Repairs with Pothole Pro JCB
Johor lead Asia-Pacific region by adopting Pothole Pro JCB for faster, longer-lasting road repairs.
29-08-2025
Loke: KLIA Taxi Touting Betrays Nation’s Image
KLIA taxi touts overcharging tourists by up to RM400 are tarnishing Malaysia’s reputation.
29-08-2025
PLUS Expects 2.2 Million Vehicles This Merdeka Weekend
PLUS is bracing for 2.2 million vehicles daily over the Merdeka weekend and is urging drivers to plan ahead using its updated app.
29-08-2025
Show More
trending_flat