ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete
The East Coast Rail Link (ECRL) project, spanning 665 kilometers from Kota Bharu, Kelantan to Selangor, has achieved over 81% completion. Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak confirmed the project's progress, stating it remains on track for its December 2026 completion date.
According to Darwis, the 81% completion figure follows a recent inspection of the Pasir Puteh ECRL Station site.
“The work progress of the 43-kilometre alignment in Kelantan has reached 88.86 per cent, contributing significantly to the overall advancement of the project,” he said, adding that testing and commissioning activities are expected to begin in June 2026.
The CEO of MRL stated that construction on the two ECRL stations in Pasir Puteh and Tunjong, Kelantan, are 69 and 68 percent complete, respectively. Both stations should be finished by May 2025.
Furthermore, Darwis said that the 400-kilometer section connecting Kelantan, Terengganu, and portions of Pahang is doing well, with 90 percent of the work completed in Terengganu and 86 percent in Pahang.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPR4859
SELANGOR
BSH6049
JOHOR
JYG3608
PULAU PINANG
PRT8003
PERAK
APB342
PAHANG
CFD4152
KEDAH
KGC1781
NEGERI SEMBILAN
NEG9654
KOTA KINABALU
SJM4969
KUCHING
QAB1273M
Last updated 06 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.16
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
EURO 5 B7
RM 3.08
Last updated 04 Sep, 2025
Latest News
MITI: Car Prices in Malaysia Driven by Market, Not Government
MITI says vehicle prices are set by the market, with government support focused on incentives and tax breaks.
06-09-2025
PMX: Proton’s International Success a Model for Malaysia
PM Datuk Seri Anwar Ibrahim says Proton’s success abroad in Egypt proves the brand is ready to expand into more markets.
04-09-2025
New Proton Saga ‘Teased’ During EV Factory Launch – ADAS Confirmed
Upcoming next-gen Proton Saga ‘teased’ during new EV factory launch, basic ADAS confirmed, along with other bits.
04-09-2025
Proton Launches New EV Plant in Tanjung Malim – e.MAS 7 CKD Begins
Proton has launched its first EV plant in Tanjung Malim, with the local assembly of the e.MAS 7 EV already started.
04-09-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
KPDN Tightens RON95 Subsidy Control with MyKad Verification via eCOSS
Malaysians will soon need to verify their MyKad through the eCOSS system to purchase subsidised RON95 petrol.
04-09-2025
Selangor Eyes DRT Comeback By Year-End
State govt fine-tuning plans to relaunch Selangor Mobility’s on-demand transit service after pilot phase ended last year.
04-09-2025
KLIA Aerotrain Breaks Down Hours After Back-in-Schedule Announcement
Fresh off nearly two weeks of “fine-tuning” maintenance to boost reliability, KLIA’s aerotrain stalled at 1.36PM, service only resumed at 5.38PM.
04-09-2025
Show More
trending_flat