ECRL: KotaSAS Station System Installation Completed

The East Coast Rail Link (ECRL) project is set to mark a significant milestone as system installation works at the KotaSAS Central Station are now complete.
It’s now the first station along the 665-KM alignment to achieve this progress. KotaSAS holds symbolic value for the project - it was the site of the groundbreaking ceremony in Aug 2017, officiated by former PM Datuk Seri Najib Razak.

The ECRL spans four states - Kelantan, Terengganu, Pahang, and Selangor - and will feature 20 stations. It is expected to reach 90% overall completion by the end of this year.

Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak said the project had recorded 82.45% overall progress as of April. Regionally, progress stands at 89% in Kelantan, 91% in Terengganu, 84% in Pahang and 67% in Selangor.
“These figures show the project is advancing steadily. With continued support from all involved states, we’re confident of hitting the 90% mark by year-end,” he said during a ceremony at the KotaSAS Station.

The event marked the successful installation of the Communication, Information and Signalling (CIS) systems at the station. These systems ensure safe, efficient and reliable train operations through automated train protection, traffic control and real-time passenger information.
Darwis further noted the completion reflects years of collaboration between MRL and project contractor China Communications Construction Company (CCCC).


The ECRL plans to begin testing and commissioning in June 2026. Two six-car Electric Multiple Unit (EMU) trains for passengers and two Electric Locomotives (E-Loco) for freight are expected to arrive in Malaysia by year-end. Full delivery of all 11 EMU sets and 12 E-Locos is scheduled by June 2026.
The ECRL will link Kota Baru to the Gombak Integrated Transport Terminal, with operations slated to begin in Jan 2027. Meanwhile the final stretch to Port Klang is expected to open by Jan 2028.
Source: NSTP
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQD7946
SELANGOR
BSK8796
JOHOR
JYM9079
PULAU PINANG
PRW6032
PERAK
APD4038
PAHANG
CFE4689
KEDAH
KGD4503
NEGERI SEMBILAN
NEH9170
KOTA KINABALU
SJP3046
KUCHING
QAB7484M
Last updated 17 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Latest News
Perodua Traz Secures 5-Star ASEAN NCAP Crash Test Score
The newly-launched Perodua Traz has secured a full five-star rating for the ASEAN NCAP crash test.
17-12-2025
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
Test Drive Any Chery PHEVs and Stand a Chance to Win Up to RM200K in Prizes
Test drive any of Chery’s new PHEVs from now until Jan 6 and stand a chance to win prizes worth up to RM200,000.
17-12-2025
Rapid KL Travel Pass Prices Increase from Jan 1, 2026
Rapid KL travel pass prices to rise in 2026; My50 and concession passes unchanged
17-12-2025
KTMB Expands ETS, East Coast Rail Services From Jan 1
KTMB expands train services nationwide with new ETS and East Coast routes starting Jan 1.
17-12-2025
KLIA Aerotrain Begins Trial Runs, Nightly Shutdown Remains
Malaysia Airports will start trial operations for the KLIA Aerotrain as part of a month-long plan to fix reliability issues.
17-12-2025
No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1
Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.
16-12-2025
OMODA & JAECOO Wrap Up 2025 With Season of Rewards
OMODA & JAECOO 2025 Season of Rewards offers extended service packages and practical ownership benefits.
16-12-2025
Show More
trending_flat