ECRL: KotaSAS Station System Installation Completed
The East Coast Rail Link (ECRL) project is set to mark a significant milestone as system installation works at the KotaSAS Central Station are now complete.
It’s now the first station along the 665-KM alignment to achieve this progress. KotaSAS holds symbolic value for the project - it was the site of the groundbreaking ceremony in Aug 2017, officiated by former PM Datuk Seri Najib Razak.
The ECRL spans four states - Kelantan, Terengganu, Pahang, and Selangor - and will feature 20 stations. It is expected to reach 90% overall completion by the end of this year.
Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak said the project had recorded 82.45% overall progress as of April. Regionally, progress stands at 89% in Kelantan, 91% in Terengganu, 84% in Pahang and 67% in Selangor.
“These figures show the project is advancing steadily. With continued support from all involved states, we’re confident of hitting the 90% mark by year-end,” he said during a ceremony at the KotaSAS Station.
The event marked the successful installation of the Communication, Information and Signalling (CIS) systems at the station. These systems ensure safe, efficient and reliable train operations through automated train protection, traffic control and real-time passenger information.
Darwis further noted the completion reflects years of collaboration between MRL and project contractor China Communications Construction Company (CCCC).
The ECRL plans to begin testing and commissioning in June 2026. Two six-car Electric Multiple Unit (EMU) trains for passengers and two Electric Locomotives (E-Loco) for freight are expected to arrive in Malaysia by year-end. Full delivery of all 11 EMU sets and 12 E-Locos is scheduled by June 2026.
The ECRL will link Kota Baru to the Gombak Integrated Transport Terminal, with operations slated to begin in Jan 2027. Meanwhile the final stretch to Port Klang is expected to open by Jan 2028.
Source: NSTP
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPS2340
SELANGOR
BSH7400
JOHOR
JYG6278
PULAU PINANG
PRT9835
PERAK
APB2037
PAHANG
CFD4672
KEDAH
KGC2673
NEGERI SEMBILAN
NEH1073
KOTA KINABALU
SJM5849
KUCHING
QAB1586M
Last updated 15 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.90
+0.02
EURO 5 B7
RM 3.10
+0.02
Last updated 11 Sep, 2025
Related News
ECRL Cites Potential Delay From Escalated Cable and Wire Theft
ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.
11-09-2025
Govt Studying ECRL Extension to Thai Border Town Rantau Panjang
Anwar says the ECRL extension to Rantau Panjang could open new growth at the Malaysia–Thailand border.
03-09-2025
Zafrul: ECRL Will Spur Jobs, Investments Along the East Coast
Tengku Zafrul says the ECRL will not only improve connectivity but also drive growth across the East Coast.
03-09-2025
ECRL Extension To Thailand Faces Track, Flood Challenges – Loke
Transport Minister says extending the ECRL to Thailand faces challenges like track differences and flood risks.
20-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End
ECRL is expected to receive its first two EMU trains and two E-Loco by the end of this year.
16-07-2025
Latest News
GWM Wey 80 Teased Again, Now Renamed ‘Wey G9’ Instead
Upcoming GWM Wey 80 teased on social media, now bearing new ‘Wey G9’ nameplate too.
15-09-2025
Proton Iriz Production Ends – No Successor Planned, But Should There Be One?
Proton Iriz hatch production ends without a successor, leaving automaker without a new hatch model since 1994.
12-09-2025
West Ipoh Span Expressway Construction Will Begin After 2026
Construction of the West Ipoh Span Expressway is set to start after 2026, providing an alternative to the busy Menora Tunnel route.
12-09-2025
SSLR2 Highway Launched: RM7.6b Project Will Link Sarawak and Sabah
The 335km Sarawak–Sabah Link Road Phase 2 will connect key towns across northern Sarawak into Sabah.
12-09-2025
Proton: We Are Prepared To Serve New X50 After Sales In East Malaysia
Proton reassures it is more than capable of handling after sales coverage for face-lifted new X50 model in East Malaysia.
12-09-2025
PLUS: Up to 2.2 Million Vehicles Daily This Malaysia Day Weekend
PLUS expects traffic to hit 2.2 million vehicles per day on Sept 12, 13, 19 and 20,motorists urged to plan journeys with the MyPLUS-TTA app.
12-09-2025
Prasarana Rail Reliability Hits Record High, Disruptions Halved
Prasarana reports its best rail performance yet, with service reliability more than doubling since 2024.
12-09-2025
Caricarz Automall Sunday Car Market Returns Sept 21 After Strong Debut
Caricarz Automall Sunday Car Market returns Sept 21 to help owners beat lowball trade-ins with direct sales.
12-09-2025
Show More
trending_flat