First RTS Link Train Set Delivered Ahead of 2026 Launch
The first train set for the Johor Bahru-Singapore RTS Link was unveiled today and will begin testing soon.Photo credit: Lee Ting Han (Facebook)
The first train set for the Johor Bahru-Singapore Rapid Transit System (RTS) Link was unveiled today ahead of its official launch in 2026. As reported by Malay Mail, this new four-car train will begin testing soon at the new Singapore Rail Test Centre (SRTC) located in Tuas.
Photo credit: Onn Hafiz Ghazi (Facebook)
Among the dignitaries present during the train set unveiling ceremony were Malaysia’s Transport Minister (MOT) Anthony Loke, Singapore’s Acting Transport Minister Jeffrey Siow, Johor Menteri Besar Datuk Onn Hafiz Ghazi, and Datuk Khairil Anwar Ahmad, chairman of RTS Operations (RTSO).
Photo credit: Lee Ting Han (Facebook)
The new train, spanning 76.5 metres long, was one of the eight train sets to be used for the RTS Link, with more trains set to be delivered for testing as we get closer to its 2026 official commencement date. All eight trains are being built by China’s CRRC Zhuzhou Locomotive, and each train can carry an optimal load of 607 passengers or a maximum of 1,087.
Each train car is equipped with 32 seats, including four foldable ones to accommodate wheelchairs, prams, or luggage. The trains are also fitted with a hearing induction loop system that transmits public announcements directly to hearing aids—a first for both countries’ rail systems.
According to RTSO, the overall installation of systems for the RTS Link is 56% complete, including the laying of tracks and the installation of the power system that will run the trains. Meanwhile, track installation works are expected to be finished by the end of July this year.
Following the test at the SRTC Tuas site, the train will undergo service simulation trials between Woodlands North in Singapore and Bukit Chagar in Johor until Q3 2026. Four more trains are now being assembled at CRRC’s facility in Batu Gajah, Perak, while the remaining three will follow later. Once ready, the seven remaining trains will be delivered directly to Johor Bahru’s Wadi Hana depot for further testing before the RTS Link opens.
Source: MalayMail
Gallery





Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VPH9224
SELANGOR
BSF8416
JOHOR
JYC4076
PULAU PINANG
PRS134
PERAK
ANX2423
PAHANG
CFC3890
KEDAH
KGB2041
NEGERI SEMBILAN
NEG3623
KOTA KINABALU
SJL5036
KUCHING
QAB6015L
Last updated 30 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.07
EURO 5 B7
RM 3.08
+0.07
Last updated 26 Jun, 2025
Related News
JB-SG RTS Link Fares Will Consider Currency Exchange
RTS Link ticket fares will be finalized by January 2027, considering factors like Malaysia-Singapore exchange rates.
27-02-2025
RTS Link 95% Complete, Service Operation Dec 2026
The Johor Bahru-Singapore RTS is 95% complete as of last November.
13-12-2024
Johor-Singapore RTS Link On Track For Completion In 2026 - Loke
The Johor Baru-Singapore Rapid Transit System (RTS) Link will be completed by the end of 2026, says Loke.
29-03-2023
KTM Shuttle Tebrau Ends 2027, Replaced By RTS Link
KTM Berhad’s Shuttle Tebrau service ends in 2027 and will be replaced by the RTS link.
25-06-2025
RTS Link: Key Road Closure in JB Until End of 2026
Jalan Johor Bahru–Endau closed for 18 months starting June 3 as RTS construction ramps up.
03-06-2025
Gov't Considering LRT Or Tram-Bus For RTS Link To Ease Congestion In JB
Putrajaya is considering either a LRT or a tram-bus system in JB to alleviate congestion once the RTS system is completed.
05-02-2025
JB Motorists Face Increased Congestion Due To RTS Link Construction
Johor Bahru mayor warns motorists of increased congestion as RTS Link construction ramps up.
31-01-2024
Johor-Singapore RTS Link On Track For Completion In 2026 - Loke
The Johor Baru-Singapore Rapid Transit System (RTS) Link will be completed by the end of 2026, says Loke.
29-03-2023
Latest News
Super GT Malaysia 2025 Rocks SIC After Decade-Plus Hiatus
Super GT Malaysia 2025 race weekend and festival thrills fans at SIC after decade-plus hiatus.
30-06-2025
VEP Enforcement Starts July 1 – Compound up to RM300
Starting July 1, vehicles without a valid VEP will be fined on the spot and may be stopped from leaving Malaysia.
30-06-2025
KKR Only Gets Half of RM4B Needed for Road Repairs – Ahmad Maslan
The Public Works Ministry only received half of the RM 4 billion required to repair the damaged roads in Malaysia.
30-06-2025
JPJ: Settle Summonses by July 8 or Face Crackdown
JPJ is ramping up enforcement after issuing a 14-day deadline for commercial and express bus operators to clear their summonses.
30-06-2025
First RTS Link Train Set Delivered Ahead of 2026 Launch
The first train set for the Johor Bahru-Singapore RTS Link was unveiled today and will begin testing soon.
30-06-2025
Zeekr Group Establishes National Sales Company in Malaysia
Zeekr Group has established its national sales company in Malaysia, known as Zeekr Intelligent Technology (Malaysia) Sdn Bhd.
30-06-2025
JPJ: Most Commercial Vehicle Operators Fail Safety Audit
JPJ reveals 64% of commercial vehicle operators failed safety audit under Ops Khas JISA, cites major compliance issues.
30-06-2025
JPJ: Bus Seatbelt Law Enforcement Starts July 1 - RM300 Fine
JPJ set to enforce bus seatbelt rule from July 1, includes RM300 fine for drivers and passengers.
30-06-2025
Show More
trending_flat