KLIA Aerotrain Finally Returns, Earns PM’s Nod Too
“Good… faster than before,” was how Prime Minister Datuk Seri Anwar Ibrahim described his ride on the newly upgraded KLIA Aerotrain during a visit to Terminal 1 of the Kuala Lumpur International Airport (KLIA1) earlier today.
Anwar arrived at the terminal at 1PM, accompanied by Transport Minister YB Anthony Loke Siew Fook, Malaysia Airports Holdings Bhd (MAHB) managing director Datuk Mohd Izani Ghani and senior MAHB officials.
He tested the enhanced Aerotrain service first-hand, travelling from the Contact Pier to the Satellite Building before receiving a briefing on the upgrades.
The Aerotrain, a long-standing icon of KLIA since its opening in 1998, recently underwent a RM456 million overhaul as part of MAHB’s RM742 million Airport Regeneration Plan. The project involved replacing and modernising the ageing fleet and related infrastructure.
The upgraded Aerotrain now operates using Alstom Innovia APM 300R three-car driverless trainsets, each capable of carrying up to 270 passengers at speeds of 56 KM/H. The journey between the main terminal and the satellite terminal now takes less than three minutes.
Transport Minister Loke had signed off on the system for operation just yesterday following six months of testing and commissioning carried out by the Land Public Transport Agency (APAD). It included comprehensive safety and technical assessments conducted from Jan to June this year.
According to MAHB, the new trains are equipped with advanced condition monitoring systems designed to reduce service disruptions, improve operational reliability and enhance overall passenger comfort.
KLIA Terminal 1 currently records over 100,000 passenger movements daily. The Aerotrain remains a crucial connection for international transit passengers, particularly as the Satellite Building houses most of the airport’s long-haul carriers.
With operations now fully restored, MAHB says the upgraded Aerotrain will strengthen KLIA’s readiness for growing traffic in the lead-up to Visit Malaysia Year 2026 and help support the airport’s return to pre-pandemic levels.
Source: Bernama
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPJ2058
SELANGOR
BSF9055
JOHOR
JYC4828
PULAU PINANG
PRS1081
PERAK
ANX3089
PAHANG
CFC4151
KEDAH
KGB2297
NEGERI SEMBILAN
NEG3798
KOTA KINABALU
SJL5401
KUCHING
QAB6176L
Last updated 02 Jul, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.07
EURO 5 B7
RM 3.08
+0.07
Last updated 26 Jun, 2025
Related News
KLIA Aerotrain Set To Resume Service On July 1
KLIA Aerotrain is set to resume operations on July 1, following successful trials after years of suspension.
21-06-2025
KLIA Aerotrain Delay Resulted From Leadership, Govt Changes - MAHB Chairman
The delay in the KLIA aerotrain project is due to several leadership and governmental transitions, says MAHB chairman.
25-04-2025
PAC To Summon Loke Over Aerotrain Delay and More
PAC will probe EPF’s RM500 million loss in MAHB shares and other key issues, summoning figures like Transport Minister Anthony Loke.
03-02-2025
KLIA Aerotrain Will Return In Q2 2025, MAHB Confirms
KLIA aerotrain service is anticipated to start operating again by the second quarter of this year.
24-01-2025
KLIA Aerotrain Delayed, MAHB Project Management & Efficiency Questioned
KLIA Aerotrain faces indefinite delays, and this has sparked public frustration and questions over MAHB's management.
16-01-2025
KLIA's New Aerotrain Set To Be Operational in Q1 2025
KLIA’s new Aerotrain service is expected to be completed in January 2025.
17-07-2024
KLIA Aerotrains Is 90% Completed - Anthony Loke
The first set of Aerotrains is almost 90% done with several new features, says Loke.
23-10-2023
KLIA Aerotrain Services Suspended Due To Mechanical & Electronic Failure
KLIA Aerotrain is already 25 years old making issues like parts supply a major concern
03-03-2023
Latest News
Vios Challenge 2025 Sees Milestone Set With Endurance Race
TGR Malaysia Vios Challenge 2025 Round 2 charts new milestone wirth endurance race format during Super GT weekend.
01-07-2025
KLIA Aerotrain Finally Returns, Earns PM’s Nod Too
PM Anwar rides the upgraded KLIA Aerotrain, inter-terminal travel time now takes less than three minutes.
01-07-2025
Ferrari Loses Trademark Battle Over Local Drink’s Horse Logo
Ferrari lost a trademark dispute against Sunrise-Mark over the Wee Power energy drink logo, which features two horses and a "W."
01-07-2025
Crackdown Urged On Dummy GPS Use In Commercial Vehicles
Experts urge tough action on fake GPS use in commercial vehicles to improve road safety.
01-07-2025
Persona Energy Signs MOU For New TTAP Bosch Xcelerator Program
Persona Energy Sdn Bhd inks MOU with Bosch Engineering Japan for new TTAP Bosch Xcelerator program.
01-07-2025
Delayed - Overnight Closure At Sg Besi Toll For Gantry Works Canceled
KL–Seremban Highway near Sg Besi toll to close overnight (July 2–3) for gantry works delayed.
01-07-2025
Mortar Bomb Near Menora Tunnel Triggers Traffic Chaos, Safely Detonated
An 81mm mortar bomb found near KM265 of the North-South Expressway has been confirmed as an UXO.
01-07-2025
New Caltex Havoline Fully Synthetic Hybrid SAE 0W-20 Launched
New Caltex Havoline Fully Synthetic Hybrid SAE 0W-20 launched for Malaysia, promises smoother engine operation.
01-07-2025
Show More
trending_flat