KLIA Aerotrain Set To Resume Service On July 1
Transport Minister Anthony Loke announced that the long-awaited KLIA Aerotrain is set to resume operations as early as July 1, following successful trials after years of suspension.
He confirmed that the project has been completed and will soon undergo additional testing, including the Emergency Response Plan assessment, in coordination with the relevant authorities.
“If everything goes well, it will begin operations at 10am on July 1," he says, adding that the Aerotrain will boost KLIA’s service and image, with shuttle buses running alongside to ease passenger flow.
KLIA’s iconic Aerotrain, which has served as the airport’s main internal transport system since 1998, is set to return with three train sets—two in active service and one on standby.
To allow for maintenance, according to Loke, only one train will run during off-peak hours (12am to 5am). Each Aerotrain features three carriages and can accommodate up to 270 passengers, ensuring smoother and more efficient movement between terminals.
“We also want to ensure the trains are well maintained in terms of safety, and that is something very important.
“That’s why we have taken time to carry out various tests, including those monitored by the Land Public Transport Agency,” he stated
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPK4921
SELANGOR
BSG3576
JOHOR
JYD3902
PULAU PINANG
PRS4507
PERAK
ANX8093
PAHANG
CFC6396
KEDAH
KGB4116
NEGERI SEMBILAN
NEG4760
KOTA KINABALU
SJL7383
KUCHING
QAB6928L
Last updated 18 Jul, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
+0.03
EURO 5 B7
RM 3.11
+0.03
Last updated 17 Jul, 2025
Related News
KLIA Aerotrain Finally Returns, Earns PM’s Nod Too
PM Anwar rides the upgraded KLIA Aerotrain, inter-terminal travel time now takes less than three minutes.
01-07-2025
KLIA Aerotrain Delay Resulted From Leadership, Govt Changes - MAHB Chairman
The delay in the KLIA aerotrain project is due to several leadership and governmental transitions, says MAHB chairman.
25-04-2025
PAC To Summon Loke Over Aerotrain Delay and More
PAC will probe EPF’s RM500 million loss in MAHB shares and other key issues, summoning figures like Transport Minister Anthony Loke.
03-02-2025
KLIA Aerotrain Will Return In Q2 2025, MAHB Confirms
KLIA aerotrain service is anticipated to start operating again by the second quarter of this year.
24-01-2025
KLIA Aerotrain Delayed, MAHB Project Management & Efficiency Questioned
KLIA Aerotrain faces indefinite delays, and this has sparked public frustration and questions over MAHB's management.
16-01-2025
KLIA's New Aerotrain Set To Be Operational in Q1 2025
KLIA’s new Aerotrain service is expected to be completed in January 2025.
17-07-2024
KLIA Aerotrains Is 90% Completed - Anthony Loke
The first set of Aerotrains is almost 90% done with several new features, says Loke.
23-10-2023
KLIA Aerotrain Services Suspended Due To Mechanical & Electronic Failure
KLIA Aerotrain is already 25 years old making issues like parts supply a major concern
03-03-2023
Latest News
2025 Proton X50 Garners 5,000 Bookings, Test-Drives Open This Weekend
Face-lifted 2025 Proton X50 garners 5,000 bookings in 10 days, test-drives also opened at 3S & 4S showrooms this weekend.
18-07-2025
Suspended PSV, GDL Drivers To Undergo Mandatory Rehab Starting Nov
JPJ will launch a rehab course in November for suspended PSV, GDL drivers to regain licences.
18-07-2025
Singapore’s Driverless Bus Cleared To Run Without Safety Officer
Singapore approves WeRide’s driverless Robobus to run in Sentosa without a safety officer onboard.
18-07-2025
Rapid KL Expands On-Demand Van Service To 12 New Areas In Selangor
Rapid KL’s on-demand van service is expanding to 12 more areas in Shah Alam and Klang starting Friday.
18-07-2025
MRT3 Gets MOT Approval, Completion Set for 2026
The 51.6 KM MRT Circle Line is officially approved, full rollout expected by end of 2026.
18-07-2025
JPJ Plans Major Reform For Kejara System
JPJ is wrapping up its review of long-awaited improvements for the Kejara system.
18-07-2025
4-Vehicle Pile-Up On Besraya Partly Caused By Deployed Airbag
Deployed airbag partly to blame for viral four-vehicle pile-up on Besraya earlier this week.
17-07-2025
No SST-Linked Price Hike for Honda Models in 2025
Honda Malaysia commits to shielding customers from SST-related cost increases.
17-07-2025
Show More
trending_flat