MRT3 Gets MOT Approval, Completion Set for 2026

The MRT3 Circle Line has officially received the go ahead from the Ministry of Transport, marking a key milestone in the Klang Valley’s rail line development. The 51.6 KM route, designed to complete the city’s rail loop, is now on track for full completion by the end of 2026.
MRT Corp made the announcement recently, confirming that Transport Minister YB Anthony Loke Siew Fook had formally signed off on the Final Railway Scheme following a public inspection exercise conducted from Sept to Dec 2024.
-full_normal.jpg)
The company celebrated the announcement on Facebook, thanking the 45,000 Malaysians who provided feedback during the public review where a remarkable 93.3% showed strong support for the project.
MRT Corp also revealed that the route has been fine-tuned in response to public input. The number of affected land lots has been reduced from 1,012 to 690, while adjustments have been made to station and viaduct locations to minimise disruption to communities.
Land acquisition will begin immediately and MRT Corp will continue to engage impacted residents and businesses, offering updates on changes specific to each location.
-full_normal.jpg)
CEO Zarif Hashim extended his gratitude to MPs, Selangor state assemblymen, local councils and business groups for their cooperation and input throughout the consultation period, which helped shape the final alignment.
The Circle Line will include 10 interchange stations and connect with the existing MRT, LRT, KTM and Monorail networks, making it a critical link in the city’s broader transit ecosystem.
Once operational, the line will be able to carry up to 25,000 passengers per hour per direction where a full journey across the network is expected to take 73 minutes.
Source: MalayMail
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQP4873
SELANGOR
BSN1593
JOHOR
JYS7541
PULAU PINANG
PSA3971
PERAK
APF7602
PAHANG
CFF6454
KEDAH
KGE6740
NEGERI SEMBILAN
NEJ7136
KOTA KINABALU
SJQ6764
KUCHING
QAB3860N
Last updated 11 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
MRT3 Public Inspection & Feedback Starts Sept 2, Virtual Tour Also Available
MRT Corp is inviting the public to review and provide feedback on the MRT3 from Sept 2 to Dec 2, 2024.
03-09-2024
LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity
Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025
05-07-2023
"Too early to assess Putrajaya MRT route on peak-hour congestion" - Loke
It is still too early to assess the effectiveness of Putrajaya's MRT service in reducing traffic congestion, says Loke.
07-04-2023
Ahmad Maslan: Gov. Mulling Further Cost-Reduction For MRT3
Deputy Finance Minister Ahmad Bin Maslan says that the government is mulling further cost-cutting measures in the MRT3 project.
31-03-2023
Budget 2023: Only Rail, Bus & Flight Subsidies Announced Under Transportation
The Malaysian government recognizes the importance of transportation infrastructure and services, particularly for urban communities who rely on rail and bus services to commute to work.
24-02-2023
MRT3 Public Inspection & Feedback Starts Sept 2, Virtual Tour Also Available
MRT Corp is inviting the public to review and provide feedback on the MRT3 from Sept 2 to Dec 2, 2024.
03-09-2024
Loke: No Rush on Dashcam Mandate for E-Hailing
Loke says mandating dashcams with audio in e-hailing vehicles requires deeper consultation.
09-02-2026
MTSB Bill in the Works to Streamline Transport Safety
The MTSB Bill is being drafted to integrate agencies like MIROS and AAIB, ensuring efficient transport safety management.
05-02-2026
Latest News
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Show More
trending_flat