New Marang Bridge 55% Done, Set to Finish By Jan 2027

Construction of the new Marang Bridge, aimed at improving travel between Kuala Terengganu and Kuantan is progressing steadily and is expected to be completed by January 2027.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the project had reached 54.7% completion as of June 30.
“This is it, no more extensions,” he said during a recent site visit. “All land acquisition issues have been resolved, and work is moving forward as planned.”
The RM338 million project, led by the Public Works Department (JKR), includes a 2.5km realignment along Federal Route 3, a 680-metre flyover to divert traffic around Marang town, a 220-metre bridge across Sungai Marang, and upgrades to 1.5km of existing roads.
Built in the 1950s, the current bridge has long been a traffic bottleneck, particularly during rush hours. It will be replaced by a modern four-lane structure designed to handle higher traffic volume and reduce congestion for east coast motorists.
But the benefits go beyond smoother traffic. With increased clearance, the new bridge will also support the local fishing community by allowing larger Zone C vessels to pass upstream, a move expected to improve accessibility and strengthen the region’s maritime and fisheries economy.

“This isn’t just about easing traffic. It’s about creating better access for fishermen, supporting local industries, and boosting Marang’s potential as a logistics hub,” Nanta affirmed. He added that the project had been prioritised under the 12th Malaysia Plan to meet rising transportation demands in the area.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPW5324
SELANGOR
BSJ6214
JOHOR
JYJ9068
PULAU PINANG
PRV1342
PERAK
APB9473
PAHANG
CFD8428
KEDAH
KGC7035
NEGERI SEMBILAN
NEH4362
KOTA KINABALU
SJN3067
KUCHING
QAB3974M
Last updated 25 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.14
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.89
-0.04
EURO 5 B7
RM 3.09
-0.04
Last updated 23 Oct, 2025
Related News
SSLR2 Highway Launched: RM7.6b Project Will Link Sarawak and Sabah
The 335km Sarawak–Sabah Link Road Phase 2 will connect key towns across northern Sarawak into Sabah.
12-09-2025
RM4b Needed, Critical Road Repairs Come First
Road repairs will be done in stages due to budget limits, with priority on the most severe sections.
19-06-2025
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
WCE Section 11 (Taiping-Beruas) Opens March 12, Toll-Free Until May 11
West Coast Expressway (WCE) officially set to open Section 11 (Taiping-Beruas) stretch from March 12, will be toll-free until May 11.
11-03-2024
Latest News
PLUS Road Diversions at Kulai–Sedenak from Oct 27–30
PLUS diverting traffic at Kulai–Sedenak to facilitate bridge beam installation from Oct 27 to 30.
25-10-2025
ASEAN 2025: KL Car-Free Morning Cancelled This Sunday
The weekly KL Car-Free Morning was cancelled this Sunday, as major road closures and tight security take over KL.
25-10-2025
Proton: Sabah X50 Customers Have Nothing To Worry
Proton reaffirms after-sales for X50 model customers in Sabah through Regional Parts Centre established in Kota Kinabalu.
24-10-2025
85 Deaths, 8,940 Crashes Recorded During Op Lancar Deepavali 2025
Road deaths fell 12% during Op Lancar Deepavali 2025, even as total crashes rose slightly to nearly 9,000 cases nationwide.
24-10-2025
Toll Collection Begins On EKVE Section 1 This Saturday
Motorists using the EKVE Section 1 will start paying tolls from Oct 25 as the free toll period comes to an end.
24-10-2025
JPJ Issued Over 4,000 Notices for Heavy Vehicle Speed Limiter Compliance
JPJ has issued over 4,000 notices to ensure heavy vehicles install speed limiter devices for safer roads.
23-10-2025
RM1.17Mil In Fines Collected From Singapore Drivers Without RFID VEP
JPJ has issued nearly 4,000 summonses to Singaporean motorists since July for failing to install RFID VEP tags.
23-10-2025
BHPetrol Refreshes CI, Shows New Look In Bandar Tun Razak Station
Fuel retailers BHPetrol announces CI refresh, ‘new look’ now applied to key Bandar Tun Razak station.
23-10-2025
Show More
trending_flat