LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
The LRT3 Shah Alam line is due to be opened later on Sept 30, 2025, but the new metro line could miss its much-anticipated planned debut, The Star reports.
This comes after the governing body for the LRT3 line announced on its Facebook page that it is currently conducting 24-hour train testing and commissioning activities along the LRT3 line from Bandar Utama station to its depot in Johan Setia.
As of now, the body did not state how long these testing and commissioning activities will take, although an earlier version of said Facebook post suggested that these processes will go on until Oct 31, 2025, which is about a month past the original planned launch date on Sept 30.
Malaysian Minister of Transport YB Anthony Loke
By end-July 2025, the LRT3 project was already at 99% completion, with Transport Minister (MoT) Anthony Loke revealing that the cost of the whole project now stands at RM21.93 billion, which is RM9.72 billion less than the originally approved budget back in 2015.
Once completed, the new LRT3 Shah Alam line will feature 25 stations, running from Bandar Utama to Johan Setia in Klang, with several interchange stations, including Bandar Utama for the MRT Kajang line and Glenmarie for the LRT Kelana Jaya line.
Source: The Star
Gallery






Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VPM5539
SELANGOR
BSG7726
JOHOR
JYE4987
PULAU PINANG
PRT1064
PERAK
ANY7209
PAHANG
CFD677
KEDAH
KGB6433
NEGERI SEMBILAN
NEG6396
KOTA KINABALU
SJL9999*
KUCHING
QAB8457L
Last updated 04 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
Latest News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor
KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.
04-08-2025
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5
Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.
04-08-2025
1,489 Summonses Issued in VEP Enforcement Operation – JPJ
JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.
04-08-2025
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.
Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.
04-08-2025
RM110 Million Collected from Special Plate Sales Since 2023 – MoT
A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.
04-08-2025
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short
With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.
04-08-2025
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
04-08-2025
ETS to JB Sentral ‘On Track’, But Not Quite There Yet
KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.
04-08-2025
Show More
trending_flat