LRT3 Will Begin Operations On Sept 30 - Loke

Transport Minister Anthony Loke announced in a parliamentary reply on Wednesday that the Light Rail Transit 3 (LRT3) is scheduled to start operating on September 30 this year.
The 37.8km line connecting Bandar Utama, Petaling Jaya to Johan Setia, Klang, is currently 98.63% complete and expected to be fully completed and handed over to Prasarana Malaysia Bhd by the turnkey contractor by July 31.
In response to Azli Yusof's (Pakatan Harapan-Shah Alam) inquiry about the LRT3 project's current status, including the trial run and expected full operation date, Loke stated that the trial run without passengers will be conducted in two phases to ensure the safety of the LRT3 service.

According to the minister, the first phase, which will be carried out by the principal contractor, Setia Utama LRT3 Sdn Bhd, will include 75 days of trial run (TR) and fault free run (FFR) from mid-April to late-June 2025. During this period, the Land Public Transport Agency (APAD) will assess the system's safety, compliance, and reliability.
Loke also noted that Rapid Rail Sdn Bhd will conduct a 60-day trial operation under the second phase with technical support from the main contractor. The trial operation, which will run from July to August 2025, will begin after the completion and approval of TR and FFR by APAD.

The LRT3 project, initially planned with 26 stations and a budget of RM9 billion, saw its cost escalate to RM31.7 billion. In 2018, the Pakatan Harapan administration deferred five stations and cancelled one, reducing the cost to RM16.63 billion. However, in 2024, Prime Minister Anwar Ibrahim announced the reinstatement of the five shelved stations at an additional cost of RM4.7 billion.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQQ9412
SELANGOR
BSN4462
JOHOR
JYT4110
PULAU PINANG
PSA6240
PERAK
APG946
PAHANG
CFF8325
KEDAH
KGE8152
NEGERI SEMBILAN
NEJ8027
KOTA KINABALU
SJQ8453
KUCHING
QAB4198N
Last updated 18 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
Latest News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Show More
trending_flat