LRT3 Will Begin Operations On Sept 30 - Loke

Transport Minister Anthony Loke announced in a parliamentary reply on Wednesday that the Light Rail Transit 3 (LRT3) is scheduled to start operating on September 30 this year.
The 37.8km line connecting Bandar Utama, Petaling Jaya to Johan Setia, Klang, is currently 98.63% complete and expected to be fully completed and handed over to Prasarana Malaysia Bhd by the turnkey contractor by July 31.
In response to Azli Yusof's (Pakatan Harapan-Shah Alam) inquiry about the LRT3 project's current status, including the trial run and expected full operation date, Loke stated that the trial run without passengers will be conducted in two phases to ensure the safety of the LRT3 service.

According to the minister, the first phase, which will be carried out by the principal contractor, Setia Utama LRT3 Sdn Bhd, will include 75 days of trial run (TR) and fault free run (FFR) from mid-April to late-June 2025. During this period, the Land Public Transport Agency (APAD) will assess the system's safety, compliance, and reliability.
Loke also noted that Rapid Rail Sdn Bhd will conduct a 60-day trial operation under the second phase with technical support from the main contractor. The trial operation, which will run from July to August 2025, will begin after the completion and approval of TR and FFR by APAD.

The LRT3 project, initially planned with 26 stations and a budget of RM9 billion, saw its cost escalate to RM31.7 billion. In 2018, the Pakatan Harapan administration deferred five stations and cancelled one, reducing the cost to RM16.63 billion. However, in 2024, Prime Minister Anwar Ibrahim announced the reinstatement of the five shelved stations at an additional cost of RM4.7 billion.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQD7946
SELANGOR
BSK8796
JOHOR
JYM9079
PULAU PINANG
PRW6032
PERAK
APD4038
PAHANG
CFE4689
KEDAH
KGD4503
NEGERI SEMBILAN
NEH9170
KOTA KINABALU
SJP3046
KUCHING
QAB7484M
Last updated 17 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
Latest News
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
Test Drive Any Chery PHEVs and Stand a Chance to Win Up to RM200K in Prizes
Test drive any of Chery’s new PHEVs from now until Jan 6 and stand a chance to win prizes worth up to RM200,000.
17-12-2025
Rapid KL Travel Pass Prices Increase from Jan 1, 2026
Rapid KL travel pass prices to rise in 2026; My50 and concession passes unchanged
17-12-2025
KTMB Expands ETS, East Coast Rail Services From Jan 1
KTMB expands train services nationwide with new ETS and East Coast routes starting Jan 1.
17-12-2025
KLIA Aerotrain Begins Trial Runs, Nightly Shutdown Remains
Malaysia Airports will start trial operations for the KLIA Aerotrain as part of a month-long plan to fix reliability issues.
17-12-2025
No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1
Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.
16-12-2025
OMODA & JAECOO Wrap Up 2025 With Season of Rewards
OMODA & JAECOO 2025 Season of Rewards offers extended service packages and practical ownership benefits.
16-12-2025
Overloaded Trucks Crackdown Showing Results, Transport Rates Remain Stable
Strict enforcement against overloaded trucks is paying off, improving road safety and transport efficiency without hiking rates.
16-12-2025
Show More
trending_flat