LRT3 Will Begin Operations On Sept 30 - Loke

Anis

Share via

230705-LRT3-MRT-LRT-map.jpg


Transport Minister Anthony Loke announced in a parliamentary reply on Wednesday that the Light Rail Transit 3 (LRT3) is scheduled to start operating on September 30 this year.

The 37.8km line connecting Bandar Utama, Petaling Jaya to Johan Setia, Klang, is currently 98.63% complete and expected to be fully completed and handed over to Prasarana Malaysia Bhd by the turnkey contractor by July 31.

In response to Azli Yusof's (Pakatan Harapan-Shah Alam) inquiry about the LRT3 project's current status, including the trial run and expected full operation date, Loke stated that the trial run without passengers will be conducted in two phases to ensure the safety of the LRT3 service.
lrt-3-train-5-e1624335707437.jpg


According to the minister, the first phase, which will be carried out by the principal contractor, Setia Utama LRT3 Sdn Bhd, will include 75 days of trial run (TR) and fault free run (FFR) from mid-April to late-June 2025. During this period, the Land Public Transport Agency (APAD) will assess the system's safety, compliance, and reliability.

Loke also noted that Rapid Rail Sdn Bhd will conduct a 60-day trial operation under the second phase with technical support from the main contractor. The trial operation, which will run from July to August 2025, will begin after the completion and approval of TR and FFR by APAD.
3002622.jpg


The LRT3 project, initially planned with 26 stations and a budget of RM9 billion, saw its cost escalate to RM31.7 billion. In 2018, the Pakatan Harapan administration deferred five stations and cancelled one, reducing the cost to RM16.63 billion. However, in 2024, Prime Minister Anwar Ibrahim announced the reinstatement of the five shelved stations at an additional cost of RM4.7 billion.

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY4627

SELANGOR

BSK173

JOHOR

JYK7418

PULAU PINANG

PRV5289

PERAK

APC3978

PAHANG

CFE856

KEDAH

KGC9101

NEGERI SEMBILAN

NEH5637

KOTA KINABALU

SJN5907

KUCHING

QAB4931M

Last updated 10 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.20

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.02

+0.07

EURO 5 B7

RM 3.22

+0.07

Last updated 06 Nov, 2025

Related News

Auto News
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3

Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3

Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.

Auto News
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.

Auto News
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

Auto News
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works

Auto News
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News
LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025

Auto News
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

Latest News

Auto News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just  20 Minutes

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.