Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.
According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.

Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.

It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.
The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.
Source: NewStraitsTimes & FB Warga Prasarana
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPX9541
SELANGOR
BSJ8736
JOHOR
JYK5467
PULAU PINANG
PRV4293
PERAK
APC3014
PAHANG
CFD9630
KEDAH
KGC8422
NEGERI SEMBILAN
NEH5206
KOTA KINABALU
SJN5238
KUCHING
QAB4725M
Last updated 02 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity
Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025
05-07-2023
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
JPJ Issued Over 4,000 Notices for Heavy Vehicle Speed Limiter Compliance
JPJ has issued over 4,000 notices to ensure heavy vehicles install speed limiter devices for safer roads.
23-10-2025
Latest News
VEP: No Exit Without Permit, Crackdown Begins Nov 15
Foreign vehicles, particularly from Singapore, cannot leave Malaysia without an active VEP and fines fully settled.
01-11-2025
BUDI95 Fuel Shortfall Claims Untrue - KPDN
KPDN says claims of fuel shortfalls under the BUDI95 are unfounded after inspections found all petrol pumps accurate.
31-10-2025
LPT3 Will Proceed Under Public-Private Partnership Model - Ahmad Maslan
RM9.8b East Coast Expressway 3 (LPT3) will be developed via public-private partnership at no cost to the government.
31-10-2025
Suzuki Fronx Secures 5-Star ASEAN NCAP Rating
The new Suzuki Fronx achieves full 5-star ASEAN NCAP rating, scoring 77.70 points under latest 2021–2025 protocol.
31-10-2025
Loke Orders MAHB To Keep Shuttle Bus Amid KLIA Aerotrain Woes
Transport minister says shuttle buses must stay as investigations continue into repeated aerotrain breakdowns.
31-10-2025
KPDN Busts Pig Slaughterhouse For Illegal Diesel Storage
Authorities seized 2,000L of subsidised diesel hidden inside a Perak pig slaughterhouse.
30-10-2025
Govt Won’t Suspend KLIA Aerotrain, MAHB Facing Action - Loke
Loke says the government won’t halt the KLIA Aerotrain, but MAHB is facing action.
30-10-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
Show More
trending_flat