Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

KS

Share via

453218537_1007686224479436_6295259034249152090_n.jpg


The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.

According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


453382648_1007686204479438_2704506612600314558_n.jpg453252451_1007686131146112_7532968729376801684_n.jpg


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.


453495284_1007686081146117_6793017307642832688_n.jpg


Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.


453219303_1007686217812770_6307662427527364152_n.jpg


It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


453083082_1007686077812784_7157571752057684711_n.jpg453183840_1007686161146109_8992891956263002173_n.jpg


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.

The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.



Source: NewStraitsTimes & FB Warga Prasarana 

Share This Article

Written By

KS

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/

Share via

JPJ Running Numbers

KUALA LUMPUR

VPG2486

SELANGOR

BSF4611

JOHOR

JYA4079

PULAU PINANG

PRR4578

PERAK

ANW6126

PAHANG

CFC1078

KEDAH

KGA9157

NEGERI SEMBILAN

NEG2183

KOTA KINABALU

SJL2710

KUCHING

QAB5039L

Last updated 16 Jun, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.07

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.74

EURO 5 B7

RM 2.94

Last updated 12 Jun, 2025

Related News

Auto News
LRT3 Will Begin Operations On Sept 30 - Loke

LRT3 Will Begin Operations On Sept 30 - Loke

LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.

27-02-2025
Auto News
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

27-06-2024
Auto News
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works

12-09-2023
Auto News
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

24-08-2023
Auto News
LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025

05-07-2023
Auto News
Loke: KEJARA System A Failure, Major Revamp Coming

Loke: KEJARA System A Failure, Major Revamp Coming

KEJARA system has failed to penalise traffic offenders who ignore their summonses, admits Loke.

13-06-2025
Auto News
New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

Speed Limitation Device (SLD) will be compulsory for commercial vehicles starting Oct 2025 to meet national road safety targets.

13-06-2025
Auto News
Govt Will Address East-West Highway Safety At Cabinet Meeting  - Loke

Govt Will Address East-West Highway Safety At Cabinet Meeting - Loke

Transport Minister announced that the safety issue of the JRTB will be discussed at the Cabinet meeting today.

11-06-2025

Latest News

Auto News
Gerik Crash: No signs Of Brake, Steering Failure

Gerik Crash: No signs Of Brake, Steering Failure

Preliminary investigations into the fatal June 9 bus crash in Gerik, have not revealed any technical malfunctions.

15-06-2025
Auto News
Gerik Crash: Motac Urges Return Of Authority Over Tourism Vehicles

Gerik Crash: Motac Urges Return Of Authority Over Tourism Vehicles

In response to the fatal bus crash involving UPSI students, Motac aimed to regain control over tourism transport for safety reasons.

13-06-2025
Auto News
Loke: KEJARA System A Failure, Major Revamp Coming

Loke: KEJARA System A Failure, Major Revamp Coming

KEJARA system has failed to penalise traffic offenders who ignore their summonses, admits Loke.

13-06-2025
Auto News
New MD & Co-MD Announced At VPCM and PHSAM

New MD & Co-MD Announced At VPCM and PHSAM

Volkswagen Passenger Cars Malaysia (VPCM) and PHS Automotive Malaysia (PHSAM) announces new MD and co-MD.

13-06-2025
Auto News
New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

Speed Limitation Device (SLD) will be compulsory for commercial vehicles starting Oct 2025 to meet national road safety targets.

13-06-2025
Auto News
FRU Crash: Lorry Exceeds Weight Limit By 70%

FRU Crash: Lorry Exceeds Weight Limit By 70%

Investigation into the fatal Teluk Intan road accident that killed nine FRU personnel last month found the tipper lorry was overloaded.

13-06-2025
Auto News
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.

13-06-2025
Auto News
Maxim Malaysia Files Final Appeal To APAD

Maxim Malaysia Files Final Appeal To APAD

Maxim Malaysia has made an appeal to APAD, requesting permission to maintain its operations within the Malaysian market.

12-06-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.