Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.
According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.

Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.

It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.
The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.
Source: NewStraitsTimes & FB Warga Prasarana
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQD7946
SELANGOR
BSK8796
JOHOR
JYM9079
PULAU PINANG
PRW6032
PERAK
APD4038
PAHANG
CFE4689
KEDAH
KGD4503
NEGERI SEMBILAN
NEH9170
KOTA KINABALU
SJP3046
KUCHING
QAB7484M
Last updated 17 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
Latest News
Updated Fuel Prices From 18 To 24 December
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 18 to 24 December, 2025, the rates are as such.
17-12-2025
Perodua Traz Secures 5-Star ASEAN NCAP Crash Test Score
The newly-launched Perodua Traz has secured a full five-star rating for the ASEAN NCAP crash test.
17-12-2025
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
Test Drive Any Chery PHEVs and Stand a Chance to Win Up to RM200K in Prizes
Test drive any of Chery’s new PHEVs from now until Jan 6 and stand a chance to win prizes worth up to RM200,000.
17-12-2025
Rapid KL Travel Pass Prices Increase from Jan 1, 2026
Rapid KL travel pass prices to rise in 2026; My50 and concession passes unchanged
17-12-2025
KTMB Expands ETS, East Coast Rail Services From Jan 1
KTMB expands train services nationwide with new ETS and East Coast routes starting Jan 1.
17-12-2025
KLIA Aerotrain Begins Trial Runs, Nightly Shutdown Remains
Malaysia Airports will start trial operations for the KLIA Aerotrain as part of a month-long plan to fix reliability issues.
17-12-2025
No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1
Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.
16-12-2025
Show More
trending_flat