Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.
According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.

Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.

It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.
The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.
Source: NewStraitsTimes & FB Warga Prasarana
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQK8158
SELANGOR
BSM2680
JOHOR
JYQ8814
PULAU PINANG
PRY3746
PERAK
APE8753
PAHANG
CFF1443
KEDAH
KGE1886
NEGERI SEMBILAN
NEJ4465
KOTA KINABALU
SJQ1553
KUCHING
QAB1868N
Last updated 01 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
Latest News
Chery Malaysia Outlines 2026 Plans, Four New SUVs Confirmed
Chery Malaysia outlines 2026 plans, with four new SUVs confirmed as the brand shifts focus toward premium and lifestyle models.
31-01-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
Summons Discounts for Foreign Vehicles Will Be Reviewed – MOT
The Transport Ministry will review traffic summons discounts offered to foreign vehicles, says minister Anthony Loke.
30-01-2026
Hyundai Expands Dealer Network and Insurance Partnerships
Hyundai Motor Malaysia partners with HZN and top insurers to enhance customer access and vehicle protection.
30-01-2026
JPJ Rolls Out Flexible Road Tax Renewal For E-Hailing Vehicles
E-hailing drivers can now renew their road tax from one to 12 months, making compliance easier and more cost-effective.
30-01-2026
Scrap Your Old Car, Get Up To RM4,000 For A New Proton
Scrap your old car and get up to RM4,000 towards a new Proton with trade-in incentives and a government grant.
30-01-2026
Traffic Diversions at 12 KL Intersections for 2026 Thaipusam
Traffic diversions at 12 KL intersections will be carried out in stages 2026 Thaipusam.
30-01-2026
Is GWM Seeking To Build Its Own Plant in Malaysia?
MITI raises prospects of a standalone GWM factory as newly launched Wey G9 begins production with 40% local content.
29-01-2026
Show More
trending_flat