Over 1,300 hours Of Train Delays This Year Due To Cable Theft - Loke
Cable theft along KTMB’s rail network has caused massive disruptions this year, with more than 1,300 hours lost, Transport Minister Anthony Loke revealed.
The thefts have repeatedly hit critical signalling systems, affecting train movements and leaving thousands of commuters stranded.
KTM Komuter services were the hardest hit, logging 741 hours of delays, while the Electric Train Service (ETS) saw 562 hours of disruption. Intercity services, however, remained unaffected.

“Among the immediate actions are conducting special operations and 24-hour patrols by KTM auxiliary police personnel in hotspot areas, especially in the Klang Valley area, as well as having intelligence and surveillance in high-risk locations,” Loke said.
Between Jan and Aug, 104 incidents were reported nationwide. Perak and Selangor topped the list with 38 and 37 cases, followed by Kedah, Negeri Sembilan, Penang, Kuala Lumpur, and Pahang.
No incidents were reported in Perlis, Melaka, Johor, or Kelantan. Last year saw 150 cases.
KTMB has taken several steps to curb the problem, including installing 193 cemented cable manhole covers in the northern sector, repairing damaged fences, and reviewing plans to deploy CCTV cameras and drones at vulnerable spots.

Joint patrols with the Royal Malaysia Police have been strengthened, and intelligence-sharing with enforcement agencies is ongoing.
“APAD and PDRM are enforcing existing laws against cable thieves, while information-sharing with PDRM and AADK has been intensified,” the minister added.
KTMB’s chief operating officer, Zain Mat Taha, warned that cable theft is more than a nuisance.

“It amounts to sabotage of railway infrastructure and could threaten the safety of hundreds of passengers while also crippling public transportation,” he said.
Looking ahead, KTMB plans to upgrade its signalling network at an estimated cost of RM12.8 million annually over the next three years, targeting high-risk areas to prevent future disruptions.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQA9446
SELANGOR
BSK3468
JOHOR
JYL4800
PULAU PINANG
PRV9314
PERAK
APC6940
PAHANG
CFE2378
KEDAH
KGD1449
NEGERI SEMBILAN
NEH6603
KOTA KINABALU
SJN7915
KUCHING
QAB5570M
Last updated 21 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
RON 97
RM 3.28
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.10
+0.03
EURO 5 B7
RM 3.30
+0.03
Last updated 20 Nov, 2025
Related News
KTMB Adds Extra ETS Trains For Christmas, School Holiday Rush
KTMB is rolling out additional ETS services to handle holiday demand and ease congestion on its northern routes.
21-11-2025
Over 82,000 KTMB Tickets Sold In One Day
KTMB saw a huge rush for 2026 train tickets, selling more than 82,000 in just one day for travel between Jan 1 and April 30.
19-11-2025
KTMB Expands Open Mode Gates In Selected Stations
Keretapi Tanah Melayu Berhad (KTMB) is rolling out its Open Mode gate system at more stations.
15-10-2025
KTMB and SRT Trials MySawasdee Cross-Border Tourist Train
KTMB and SRT complete Padang Besar-Surat Thani rail trials, paving way for expanded MySawasdee service.
06-10-2025
KTMB Adds Extra ETS Trips For Deepavali Travel Rush
KTMB will operate additional ETS services between Padang Besar and KL Sentral from Oct 17 to 22.
06-10-2025
KTMB Adds Weekend ETS Trips Between Kluang, KL Sentral
Starting Oct 10, KTMB will offer new weekend ETS services from Kluang to KL Sentral.
03-10-2025
Honda Malaysia Provides e:N1 EVs for the 45th ASEAN Railways CEOs’ Conference
Honda Malaysia has partnered with KTMB to provide 25 units of the e:N1 for the 45th ASEAN Railways CEOs’ Conference.
09-09-2025
KTMB Targets Bangkok Route Revival, Rail Links To China
KTMB’s acting CEO sets sights on reviving the Bangkok route and expanding Malaysia’s rail links to China and beyond.
02-09-2025
Latest News
Over 1,300 hours Of Train Delays This Year Due To Cable Theft - Loke
Cable theft has caused major disruptions to KTM Komuter and ETS services this year, resulting in over 1,300 hours of delays.
21-11-2025
Gemas-JB Rail Project Set To Start Full Service This Month
The Gemas-Johor Baru rail line nears completion with full train services expected this month.
21-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
Proton, MARii Inks Collaboration Agreement To Establish NATC
Proton and MARii jointly ink agreements towards jointly establishing ‘National Automotive Test Centre’ (NATC).
21-11-2025
KTMB Adds Extra ETS Trains For Christmas, School Holiday Rush
KTMB is rolling out additional ETS services to handle holiday demand and ease congestion on its northern routes.
21-11-2025
Johor Questions Delay as Penang LRT Gets Federal Nod
Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.
21-11-2025
Govt Mulls Putting Streetlight Upkeep Under Concessionaires
Government may soon place highway streetlight upkeep under concessionaires for quicker, more organised repairs.
21-11-2025
Rapid Rail Breakdowns Drop Sharply This Year - Loke
Proactive maintenance and real-time monitoring have cut train disruptions significantly this year.
20-11-2025
Show More
trending_flat