Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Kumeran Sagathevan

Share via

Federal-Highway-(2).jpg


Despite worsening congestion, the FT2 Federal Highway will not be widened or upgraded, the Dewan Negara heard today.

Works Minister Datuk Seri Alexander Nanta Linggi said the 34.59 KM route linking Kuala Lumpur and Port Klang no longer justifies an upgrade, as land and asset acquisition costs have become prohibitively high. He added that the social impact of such works would also outweigh the benefits.

Traffic figures from 2024 show the FT2 operating at Level of Service F at Census Station BR101, reflecting extremely heavy traffic conditions. This puts it in the same category as parts of the Middle Ring Road 2 (FT28), which is facing similar congestion levels.


Federal-Highway-(1).jpg


Nanta was responding to Senator Tiew Way Keng’s question on the progress of highway and federal road improvements across Selangor.

Rather than expanding FT2, the government is looking at other ways to manage traffic demand, including the possibility of a new highway. Greater reliance on public transport is also expected once the LRT3 line between Shah Alam and Kuala Lumpur begins service on Dec 31.

For the 37.58 KM FT28 MRR2 corridor from Kepong to Sri Petaling, Nanta said congestion relief has been addressed through the Sungai Besi–Ulu Kelang Expressway (SUKE). Upgrading MRR2 itself is no longer seen as viable for the same cost and social reasons.


Federal-Highway-(1).jpeg


He noted that FT5 Jalan Klang–Sabak Bernam is currently operating well within capacity, with 2024 data showing a Level of Service A at Census Station BR104, meaning no upgrade is required for now.

Nanta also pointed to the West Coast Expressway, due for full completion in 2026, as a potential alternative route that could help divert traffic away from FT5.

He reiterated that any new road or upgrade proposal must originate from the state government and be channelled through the State Economic Planning Unit (UPEN) and relevant technical agencies, before the ministry can consider it, subject to available funding.


Source: MalayMail

Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VQD7946

SELANGOR

BSK8796

JOHOR

JYM9079

PULAU PINANG

PRW6032

PERAK

APD4038

PAHANG

CFE4689

KEDAH

KGD4503

NEGERI SEMBILAN

NEH9170

KOTA KINABALU

SJP3046

KUCHING

QAB7484M

Last updated 17 Dec, 2025

Fuel Price

Petrol

RON 95

RM 2.64

-0.02

RON 97

RM 3.27

-0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.06

-0.02

EURO 5 B7

RM 3.26

-0.02

Last updated 11 Dec, 2025

Related News

Auto News

Govt Mulls Putting Streetlight Upkeep Under Concessionaires

Government may soon place highway streetlight upkeep under concessionaires for quicker, more organised repairs.

21-11-2025
Auto News

RM20 Million Allocated to Upgrade Federal Highway Motorcycle Lanes – KKR

A total of RM20 million will be allocated to upgrade the motorcycle lanes on the Federal Highway, the Works Ministry says.

08-08-2025
Auto News

MLFF Toll System - Too Early To Finalize Implement

Too early for multi-Lane Free Flow (MLFF) toll collection system to be finalised, government welcomes new ideas for implementation instead.

05-02-2025
Auto News

Govt Will Offer 50% Toll Discounts For All Festive Holidays

Instead of toll-free travels, the government will instead offer 50% toll discounts during major holiday festivals.

04-02-2025
Auto News

Deepavali Toll Free Travel - Oct 29 & 30

Works Ministry announces two days of toll free travel in conjunction with Deepavali celebrations on Oct 29 and 30, 2024.

28-10-2024
Auto News

Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

300 KM Central Spine Road is 63.35% complete with fourteen projects under construction.

25-07-2024
Auto News

WCE Assam Jawa Interchange Opens To Public - TOLL FREE Till 2 Jan 2024!

Assam Jawa Interchange on West Coast Expressway (WCE) Section 6 opens to the public on Tuesday, November 21, 2023 at 12:01 am

20-11-2023

Latest News

Auto News

KLIA Aerotrain Begins Trial Runs, Nightly Shutdown Remains

Malaysia Airports will start trial operations for the KLIA Aerotrain as part of a month-long plan to fix reliability issues.

17-12-2025
Auto News

No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1

Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.

16-12-2025
Auto News

OMODA & JAECOO Wrap Up 2025 With Season of Rewards

OMODA & JAECOO 2025 Season of Rewards offers extended service packages and practical ownership benefits.

Auto News

Overloaded Trucks Crackdown Showing Results, Transport Rates Remain Stable

Strict enforcement against overloaded trucks is paying off, improving road safety and transport efficiency without hiking rates.

16-12-2025
Auto News

Gemas-JB ETS Needs Better Access To Curb City Traffic - Expert

Experts urge improved first-mile access, feeder buses, and park-and-ride options for the Gemas- JB ETS.

16-12-2025
Auto News

SCS Adopts Advanced European Testing Systems

SCS raises the bar for vehicle inspections with advanced European testing technology.

Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.