Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana Malaysia Bhd has postponed the opening of the Shah Alam LRT Line, emphasising that passenger safety must come first and avoiding any repeat of the 2021 Kelana Jaya LRT collision that injured over 200 passengers.
According to Wan Agyl Wan Hassan, founder and CEO of MY Mobility Vision, the construction work on the line is nearly complete, but the technology running the trains is far more complex.

"The Shah Alam LRT is fully automated (GoA4), meaning the system controls speed, braking, doors, and train spacing entirely via software. Even a minor glitch could cause a train to brake suddenly or disrupt schedules
“Each train must complete a fault-free run (FFR) as required by the Land Public Transport Agency (APAD)
“If a problem occurs, testing must start over. It may not be popular, but it’s necessary to make sure passengers are truly safe," he told The Star.
He added that many countries, including Singapore, the UK, and Australia, have delayed the launch of automated rail lines at the last minute to deal with software integration issues.
-full_normal-(1).jpg)
“In modern rail systems, postponing safety is normal. What’s unusual is opening a system that isn’t fully stable,” Wan Agyl added.
Samirul Ariff Othman, senior consultant at Global Asia Consulting, said extending the testing period is a principled decision, not an unnecessary delay.
“It prioritises system reliability and passenger safety. Rushing the launch could lead to trains stopping mid-track, brake failures, repeated delays, and a damaged public image

"Addressing all issues before operations start prevents costly repairs and long-term negative perception," he noted in the same report.
Source: The star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQJ4856
SELANGOR
BSL9005
JOHOR
JYQ2764
PULAU PINANG
PRX9549
PERAK
APE4738
PAHANG
CFE8912
KEDAH
KGD9580
NEGERI SEMBILAN
NEJ3502
KOTA KINABALU
SJP8425
KUCHING
QAB762N
Last updated 24 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
Latest News
UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors
Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.
23-01-2026
Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign
Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.
23-01-2026
LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch
LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.
23-01-2026
JPJ Lifts Travel Proof Rule for Physical Driving Licence
JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.
23-01-2026
KL’s Lalaport Hub Nears Approval for Singapore Express Buses
KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.
22-01-2026
Overloaded Lorry Crackdown Reduces Road Deaths
Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.
22-01-2026
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Puspakom - New Brake Inspection Rules for Heavy Vehicles
Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.
22-01-2026
Show More
trending_flat