Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana Malaysia Bhd has postponed the opening of the Shah Alam LRT Line, emphasising that passenger safety must come first and avoiding any repeat of the 2021 Kelana Jaya LRT collision that injured over 200 passengers.
According to Wan Agyl Wan Hassan, founder and CEO of MY Mobility Vision, the construction work on the line is nearly complete, but the technology running the trains is far more complex.

"The Shah Alam LRT is fully automated (GoA4), meaning the system controls speed, braking, doors, and train spacing entirely via software. Even a minor glitch could cause a train to brake suddenly or disrupt schedules
“Each train must complete a fault-free run (FFR) as required by the Land Public Transport Agency (APAD)
“If a problem occurs, testing must start over. It may not be popular, but it’s necessary to make sure passengers are truly safe," he told The Star.
He added that many countries, including Singapore, the UK, and Australia, have delayed the launch of automated rail lines at the last minute to deal with software integration issues.
-full_normal-(1).jpg)
“In modern rail systems, postponing safety is normal. What’s unusual is opening a system that isn’t fully stable,” Wan Agyl added.
Samirul Ariff Othman, senior consultant at Global Asia Consulting, said extending the testing period is a principled decision, not an unnecessary delay.
“It prioritises system reliability and passenger safety. Rushing the launch could lead to trains stopping mid-track, brake failures, repeated delays, and a damaged public image

"Addressing all issues before operations start prevents costly repairs and long-term negative perception," he noted in the same report.
Source: The star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQK8158
SELANGOR
BSM2680
JOHOR
JYQ8814
PULAU PINANG
PRY3746
PERAK
APE8753
PAHANG
CFF1443
KEDAH
KGE1886
NEGERI SEMBILAN
NEJ4465
KOTA KINABALU
SJQ1553
KUCHING
QAB1868N
Last updated 01 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
Latest News
Chery Malaysia Outlines 2026 Plans, Four New SUVs Confirmed
Chery Malaysia outlines 2026 plans, with four new SUVs confirmed as the brand shifts focus toward premium and lifestyle models.
31-01-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
Summons Discounts for Foreign Vehicles Will Be Reviewed – MOT
The Transport Ministry will review traffic summons discounts offered to foreign vehicles, says minister Anthony Loke.
30-01-2026
Hyundai Expands Dealer Network and Insurance Partnerships
Hyundai Motor Malaysia partners with HZN and top insurers to enhance customer access and vehicle protection.
30-01-2026
JPJ Rolls Out Flexible Road Tax Renewal For E-Hailing Vehicles
E-hailing drivers can now renew their road tax from one to 12 months, making compliance easier and more cost-effective.
30-01-2026
Scrap Your Old Car, Get Up To RM4,000 For A New Proton
Scrap your old car and get up to RM4,000 towards a new Proton with trade-in incentives and a government grant.
30-01-2026
Traffic Diversions at 12 KL Intersections for 2026 Thaipusam
Traffic diversions at 12 KL intersections will be carried out in stages 2026 Thaipusam.
30-01-2026
Is GWM Seeking To Build Its Own Plant in Malaysia?
MITI raises prospects of a standalone GWM factory as newly launched Wey G9 begins production with 40% local content.
29-01-2026
Show More
trending_flat