ECRL Is More Than 60% Complete - Malaysia Rail
-full_normal.jpg)
Photo: Bernama.
Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak, stated that the East Coast Rail Link (ECRL) has made 62.4% progress. According to Bernama, the project's Kelantan phase is currently 75.8% complete.
“The 43km ECRL alignment in Kelantan involves the construction of two stations, Kota Bharu for passengers only and Pasir Puteh Station for passengers and cargo.
The alignment from Kota Bharu to the integrated transport terminal in Gombak, Selangor, is expected to be completed on time in December 2026, with services beginning in January 2027. Meanwhile, the ECRL alignment from Gombak to Port Klang is scheduled to be completed by December 2027, Darwis added.
To recap, the ECRL project is a 665-kilometer, RM50.3 billion rail network that connects the east and west coasts, specifically Kota Bharu in Kelantan and Gombak (Selangor). The travel time between these points is expected to be reduced to four hours from the current seven-hour road journey, or more than 12 hours during the holiday season.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRQ1287
SELANGOR
BST6904
JOHOR
JE2548J
PULAU PINANG
PSF5430
PERAK
APL4639
PAHANG
CFH7319
KEDAH
KGJ1104
NEGERI SEMBILAN
NEL8402
KOTA KINABALU
SJU1246
KUCHING
QAB5624P
Last updated 17 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?
Puspakom now has rivals for M.V.15 ownership transfer inspections, but fees won't get cheaper. Here's why JPJ is keeping rates standardised.
15-09-2026
If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out
Suzuki has opened a new RM1 million dealership in Juru, Penang, expanding its Malaysian network to 14 sales outlets and 13 service centres.
14-09-2026
Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?
Proton and Perodua account for nearly 63% of Malaysia's new car registrations in 2026. Here's why national brands still dominate despite growing competition.
14-09-2026
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out
JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.
11-09-2026
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Would You Trust Malaysia's MLFF System To Charge The Right Car, Every Time?
Malaysia's MLFF is moving forward, but how will barrier-free tolls identify and charge the right car? Here's how RFID, ANPR and the system could work.
09-09-2026
Is "Adjusting" Used-Car Mileage Really Normal In Malaysia?
A Bro Wong-SCRUT dispute has put used-car mileage adjustment back in focus. How common is odometer tampering in Malaysia, and are buyers protected?
09-09-2026
Show More
trending_flat