Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Kumeran Sagathevan

Share via


Minister of Transport, YB Anthony Loke earlier today announced that the investigation on the structural damage of the viaduct and the cracked pier near the Bandaraya LRT station is complete. This service interruption between the Masjid Jamek LRT station and the Bandaraya LRT station happened on 27 Jan 27 2023.

The investigation shows that damages to the three viaduct structures and the pier was caused by "ground movement" believed to be from works at the adjacent construction site. According to the Land Public Transport Agency (APAD), the construction works were performed without any consultation with APAD under the Railway (Railway Protection Zone) Regulations 1998 [P.U. (A) 367].


Prasarana, the concession holder for Rapid KL is now in the process of appointing a contractor to carry out the repair work which is expected to start in early March and would take up to seven months to complete.

These seven months would include two months for strengthening of the structure and five months for comprehensive repair works. Prasarana would be looking into legal action against the developer for the damages incurred.


Once the Putrajaya Line MRT service is operational this coming March, users of the Ampang/Sri Petaling Line will have an alternative route to the city centre via interchange stations such as Chan Sow Lin, Titiwangsa and Sg Besi.

While the repair works are being carried out, Rapid KL would continue the feeder bus service which has been ongoing since 27 Jan. 


Gallery

Tagged:

Ampang LRT Line
Ampang/Sri Petaling LRT
Agensi Pengangkutan Awam Darat (APAD)
Land Public Transport Agency (APAD)
Bandaraya LRT Station
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Sri Petaling LRT Line Will Resume Operations On 29 February

Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.

07-01-2024
Auto News

Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024

Ampang/Sri Petaling LRT Line, reopening delayed till February 29, 2024

Auto News

Govt Won’t Suspend KLIA Aerotrain, MAHB Facing Action - Loke

Loke says the government won’t halt the KLIA Aerotrain, but MAHB is facing action.

30-10-2025
Auto News

Youths Encroach “Women Only Coach”; KTMB & APAD discuss legislation

A recent incident of harassment in “Women Only Coach”, brings up the call for legislation.

Auto News

APAD To Regulate P-Hailing Riders’ Income, Says MOT

The Ministry Of Transport has agreed to allow the Land Public Transport Agency (APAD) in regulating p-hailing service providers.

12-04-2023
Auto News

APAD Extends Taxi & e-Hailing Vehicles Age Limit to 15 Years

The Malaysian Land Public Transport Agency has increased the age limit for taxi & e-hailing vehicles to 15 years.

03-04-2023
Auto News

Gerik - Jeli Incident, Transportation Company's License Revoked - APAD

Hence the APAD’s Cancellation and Revocation department concluded to revoke the operator, Mun Fei Enterprise (IM0103026-M) operation license with immediate effect.

Auto News

JPJ Targets Firms Hiring Unlicensed Foreign Drivers

JPJ will launch operations nationwide to take action against companies employing foreigners without valid driving licences.

07-11-2025

Latest News

Auto News

BYD Sees 2025 YTD Sales Total Reach 11,097 Units – 70% YoY Up From 2024

BYD Cars Malaysia discloses its 2025 YTD toral sales have reached 11,097 units, marking a 70% YoY increase from 2024.

14-11-2025
Auto News

KLIA Aerotrain To Stop Nightly From Nov 15 For Reliability Upgrades

KLIA’s Aerotrain will be suspended nightly from 9PM to 7AM starting Nov 15 for reliability upgrades.

14-11-2025
Auto News

Kelana Jaya LRT Weekend Disruptions For Upgrades

Rapid KL will upgrade the Kelana Jaya Line signalling system on Nov 15–16 and 29–30.

14-11-2025
Auto News

GWM Malaysia Accelerates Localisation Drive To Strengthen Supply Chain

GWM Malaysia strengthens local partnerships and production to support the nation’s new-energy mobility ambitions.

Auto News

Upgraded Mitsubishi Eon Auto Mart 3S Centre Reopens in Melaka

Mitsubishi Motors Malaysia, together with Eon Auto Mart, announces the relocation and upgrade of its outlet in Melaka.

14-11-2025
Auto News

PLUS Implements Night Contra-Flow On Elite Highway For Pipe Work

Motorists on the Elite Highway should expect a contra-flow from Nov 17–20 for pipe work.

14-11-2025
Auto News

Flat Rate, Rule of 78, Reducing Balance: How Hire-Purchase Loans Really Work

We break down a RM100,000 loan over seven years to show how reducing balance interest saves you money.

Auto News

Genting Highlands Set To Introduce Vehicle Fee to Boost Safety

Motorists heading to Genting Highlands will soon pay a fee to fund maintenance and safety on the 24 km private road.