Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024

Kumeran Sagathevan

Share via

AmpangSri-Petaling-LRT-Line-Caricarz-(2).jpg

Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.

The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.

AmpangSri-Petaling-LRT-Line-Caricarz-(1).jpeg

After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.

These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.

AmpangSri-Petaling-LRT-Line-Caricarz-(1).jpg

Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.

Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.


Tagged:

Ampang/Sri Petaling LRT
LRT Ampang line
Bandaraya LRT Station
apid Rail Sdn Bhd (Rapid Rail)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News
Sri Petaling LRT Line Will Resume Operations On 29 February

Sri Petaling LRT Line Will Resume Operations On 29 February

Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.

07-01-2024
Auto News
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Ampang/Sri Petaling LRT repair work would take up to seven months to complete.

Auto News
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31

LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31

RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.

24-12-2024
Auto News
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes

Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes

LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.

01-02-2024
Auto News
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment

Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment

RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.

04-04-2023
Auto News
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke

Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke

Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.

02-02-2023
Auto News
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Ampang/Sri Petaling LRT repair work would take up to seven months to complete.

Latest News

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025
Auto News
1,489 Summonses Issued in VEP Enforcement Operation – JPJ

1,489 Summonses Issued in VEP Enforcement Operation – JPJ

JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.

04-08-2025
Auto News
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.

04-08-2025
Auto News
RM110 Million Collected from Special Plate Sales Since 2023 – MoT

RM110 Million Collected from Special Plate Sales Since 2023 – MoT

A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.

04-08-2025
Auto News
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.

Auto News
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News
ETS to JB Sentral ‘On Track’, But Not Quite There Yet

ETS to JB Sentral ‘On Track’, But Not Quite There Yet

KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.