ECRL Is More Than 60% Complete - Malaysia Rail

Anis

Share via

Thailand-Grants-T.M.-6-Form-Relief-For-Malaysian-Drivers-(26).png
Photo: Bernama.
Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak, stated that the East Coast Rail Link (ECRL) has made 62.4% progress. According to Bernama, the project's Kelantan phase is currently 75.8% complete.

“The 43km ECRL alignment in Kelantan involves the construction of two stations, Kota Bharu for passengers only and Pasir Puteh Station for passengers and cargo.

The alignment from Kota Bharu to the integrated transport terminal in Gombak, Selangor, is expected to be completed on time in December 2026, with services beginning in January 2027. Meanwhile, the ECRL alignment from Gombak to Port Klang is scheduled to be completed by December 2027, Darwis added.

To recap, the ECRL project is a 665-kilometer, RM50.3 billion rail network that connects the east and west coasts, specifically Kota Bharu in Kelantan and Gombak (Selangor). The travel time between these points is expected to be reduced to four hours from the current seven-hour road journey, or more than 12 hours during the holiday season.

Tagged:

East Coast Rail Link (ECRL)
ECRL
ECRL project
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Hits 88% Milestone As Key C1B Stretch Completed

ECRL Hits 88% Milestone As Key C1B Stretch Completed

The ECRL project has hit 88% completion with the C1B Segment now successfully completed.

05-11-2025
Auto News
MOT Eyes Rail Expansion, Road Safety and Airport Improvements

MOT Eyes Rail Expansion, Road Safety and Airport Improvements

Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.

Auto News
ECRL Project On Track Despite RM2.9mil Theft Losses

ECRL Project On Track Despite RM2.9mil Theft Losses

MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.

30-10-2025
Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3

Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3

Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.

Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared

ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared

Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.

Auto News
ECRL Cites Potential Delay From Escalated Cable and Wire Theft

ECRL Cites Potential Delay From Escalated Cable and Wire Theft

ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.

Latest News

Auto News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just  20 Minutes

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025