Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

Kumeran Sagathevan

Share via

355458718_695232475747388_801546394303280726_n.jpg


As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.

Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.

To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.


thumb-(3).jpg


Nanta also provided updates on the various packages of the project:

  • Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
  • Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
  • Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
  • Package 4: Kampung Relong to Raub, is 63.69% complete.
  • Package 5: Raub to Bentong has been opened to users.
  • Package 6: Bentong to LPT Junction, is 30.07% complete.


LTU.jpg


He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030). 

Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.

Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.

Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.



Source: BERNAMA

Tagged:

Lingkaran Tengah Utama Project (LTU).
Central Spine Road (CSR)
Works Minister Datuk Seri Alexander Nanta Linggi
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

KKR Seeking RM20 Million To Build R&R Along LTU Highway

Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.

Auto News

Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway

Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.

Auto News

LTU Section 5A: Raub Bypass Opens On Friday

The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01

08-03-2024
Auto News

Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project

The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).

31-03-2023
Auto News

Two Million Road Users Set To Enjoy Toll-Free LTU

A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.

27-01-2023
Auto News

East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta

The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.

16-09-2025
Auto News

Nanta: MYJalan Will Become National Road Database

MYJalan app set to evolve from complaint channel to key tool in managing Malaysia’s road network.

Auto News

NPE Extension Deal Inked, RM1.4b+ Project Starts Q4 2025

NPE extension project costing over RM1.4b promises to cut travel time by up to 25 minutes and integrate with KL’s Traffic Master Plan 2040.

Latest News

Auto News

Amir Hamzah: No Daily Refuel Limits Under Budi95 For Now

Amir Hamzah: No limit on daily refuels, data analytics to monitor RM1.99 subsidy use to detect abuse.

Auto News

New RM22.7M JPJ Kajang Office Set for 2027

The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.

23-09-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

Amir Hamzah: No Back-to-Back Pumping of RM1.99 RON95 A Day

Amir Hamzah: Govt. won't allow multiple subsidised refuels in a day as BUDI95 takes effect Sept 30.

Auto News

Petron Lubricants Gains SIRIM Certification & Label

Petron Malaysia acquires SIRIM genuine product licence certification and label for engine lubricant product line-up.

23-09-2025
Auto News

Govt Will Allow Commercial RV Rentals from 2026 - Loke

Starting January 2026, RVs can be licensed for commercial use, making self-drive RV holidays safer and regulated.

23-09-2025
Auto News

BUDI95: RON95 Ban on Foreign Cars Still On, RM1.99 for Malaysians

BUDI95 keeps foreign-registered cars out of subsidised RON95, only Malaysians with local vehicles can pump at RM1.99 per litre.

Auto News

Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security

Rapid Rail will introduce a live tracker showing coach crowd levels so commuters can board with less stress.

23-09-2025