Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

Kumeran Sagathevan

Share via

355458718_695232475747388_801546394303280726_n.jpg


As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.

Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.

To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.


thumb-(3).jpg


Nanta also provided updates on the various packages of the project:

  • Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
  • Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
  • Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
  • Package 4: Kampung Relong to Raub, is 63.69% complete.
  • Package 5: Raub to Bentong has been opened to users.
  • Package 6: Bentong to LPT Junction, is 30.07% complete.


LTU.jpg


He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030). 

Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.

Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.

Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.



Source: BERNAMA

Tagged:

Lingkaran Tengah Utama Project (LTU).
Central Spine Road (CSR)
Works Minister Datuk Seri Alexander Nanta Linggi
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

KKR Seeking RM20 Million To Build R&R Along LTU Highway

Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.

Auto News

Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway

Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.

Auto News

LTU Section 5A: Raub Bypass Opens On Friday

The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01

08-03-2024
Auto News

Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project

The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).

31-03-2023
Auto News

Two Million Road Users Set To Enjoy Toll-Free LTU

A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.

27-01-2023
Auto News

50% Toll Discount Nationwide for CNY 2026

50% toll discount on selected highways from Feb 14–15 to ease CNY travel.

Auto News

Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.

Auto News

MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta

Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.

03-12-2025

Latest News

Auto News

Phew! Anthony Loke Confirms T20s Won’t Be Cut From Fuel Subsidies... For Now

Transport Minister Anthony Loke confirms T20 group will not be cut from RON95 fuel subsidies for now. Learn why the government is sticking to the "simple" Budi95 MyKad system.

14-05-2026
Auto News

First 300L, Now 200L... Is 150L Inevitable? A Look At The Future Of Budi Madani

Is the 150L petrol quota coming? We break down the "taken out of context" Budi95 news and why Malaysia's RM7 billion subsidy bill makes a future cut a real possibility.

13-05-2026
Auto News

5 Shocking Numbers That Explain Why Proton Is Exiting Its Distribution Deal In South Africa

Proton's South African distributor, CMH Group, confirms the termination of its agreement. From selling only 7 cars in April to the rise of Geely, here are 5 numbers you need to see.

13-05-2026
Auto News

It’s Not Just About Income'—Economy Ministry Responds To Concerns That T20 Are Being 'Unfairly' Cut Off

Is the T20 being unfairly cut off from RON95 subsidies? Economy Ministry clarifies how PADU will use household needs, not just income, for targeted fuel subsidies in Malaysia.

12-05-2026
Auto News

Bankrupt Or Safe? Take This Quiz To See Your New Motor Insurance Fate

Will your driving habits save you money or break the bank? Take our quiz to see how Malaysia’s new 'risk-based' motor insurance rules from PIAM could affect your premiums.

12-05-2026
Auto News

Cheap Petrol For T20? Its Days Are Numbered. PM Anwar Drops New Update

PM Anwar confirms the T20 fuel subsidy cut is in its final stages. Find out how the T20, B40 and M40 groups are affected by the new RON95 rationalisation.

11-05-2026
Auto News

Why You Might Be Rejected (And Why You Won't): Decoding JPJ’s New License Conversion Categories

Returning to Malaysia? Starting June 1, 2026, you can convert your foreign driving license to a JPJ license without retaking the test. We decode the new SOPs, eligibility rules, and common reasons for rejection.

08-05-2026
Auto News

"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Why is the Pan Borneo Highway taking so long? Chief Minister Hajiji Noor reveals 4 main constraints slowing down Phase 1B from Sandakan to Lahad Datu.

07-05-2026