Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

Kumeran Sagathevan

Share via

355458718_695232475747388_801546394303280726_n.jpg


As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.

Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.

To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.


thumb-(3).jpg


Nanta also provided updates on the various packages of the project:

  • Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
  • Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
  • Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
  • Package 4: Kampung Relong to Raub, is 63.69% complete.
  • Package 5: Raub to Bentong has been opened to users.
  • Package 6: Bentong to LPT Junction, is 30.07% complete.


LTU.jpg


He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030). 

Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.

Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.

Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.



Source: BERNAMA

Tagged:

Lingkaran Tengah Utama Project (LTU).
Central Spine Road (CSR)
Works Minister Datuk Seri Alexander Nanta Linggi
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

KKR Seeking RM20 Million To Build R&R Along LTU Highway

Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.

Auto News

Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway

Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.

Auto News

LTU Section 5A: Raub Bypass Opens On Friday

The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01

08-03-2024
Auto News

Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project

The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).

31-03-2023
Auto News

Two Million Road Users Set To Enjoy Toll-Free LTU

A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.

27-01-2023
Auto News

50% Toll Discount Nationwide for CNY 2026

50% toll discount on selected highways from Feb 14–15 to ease CNY travel.

Auto News

Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.

Auto News

MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta

Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.

03-12-2025

Latest News

Auto News

Updated Fuel Prices From 12 To 18 February

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 12 to 18 February, 2026, the rates are as such.

11-02-2026
Auto News

PLUS Expects 2.2 Million Vehicles Daily During CNY Peak Travel

PLUS is preparing for up to 2.2 million vehicles per day during the CNY, a 16% increase from normal traffic levels.

11-02-2026
Auto News

GWM Wey G9 Receives 800 Bookings Within First Week of Launch

The new GWM Wey G9 MPV has received over 800 bookings within the first week of its Malaysian debut.

11-02-2026
Auto News

Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.

11-02-2026
Auto News

Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%

New vehicle registrations fell to 67,995 units in Jan, a seasonal pullback from Dec’s delivery-driven surge.

Auto News

Honda Malaysia Eyes 60,000 Sales, Confirms Six New Models For 2026 Too

Honda Malaysia lays out target to shift up to 60,000 units, buoyed by the introduction of six new models too.

10-02-2026
Auto News

KPDN Plans Tighter Controls on RON95 Misuse

KPDN is reviewing legislative changes to prevent fraud and ensure subsidised RON95 benefits only eligible Malaysians.

Auto News

Putrajaya Pulls Plug on ART Plans Due to High Costs

Putrajaya has dropped plans for a trackless ART tram after the RM212 million project was found to be too costly.