Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

Kumeran Sagathevan

Share via

355458718_695232475747388_801546394303280726_n.jpg


As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.

Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.

To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.


thumb-(3).jpg


Nanta also provided updates on the various packages of the project:

  • Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
  • Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
  • Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
  • Package 4: Kampung Relong to Raub, is 63.69% complete.
  • Package 5: Raub to Bentong has been opened to users.
  • Package 6: Bentong to LPT Junction, is 30.07% complete.


LTU.jpg


He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030). 

Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.

Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.

Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.



Source: BERNAMA

Tagged:

Lingkaran Tengah Utama Project (LTU).
Central Spine Road (CSR)
Works Minister Datuk Seri Alexander Nanta Linggi
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

KKR Seeking RM20 Million To Build R&R Along LTU Highway

Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.

Auto News

Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway

Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.

Auto News

LTU Section 5A: Raub Bypass Opens On Friday

The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01

08-03-2024
Auto News

Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project

The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).

31-03-2023
Auto News

Two Million Road Users Set To Enjoy Toll-Free LTU

A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.

27-01-2023
Auto News

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News

New Audit Move To Keep Highway Concessionaires In Check

Works Ministry will introduce independent audits for highway concessionaires in early 2026.

04-11-2025
Auto News

East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta

The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.

16-09-2025

Latest News

Auto News

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025