Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

Anis

Share via

Sabah-Pan-Borneo-Highway-BONGAWAN-to-PAPAR-750x500.jpg

The construction of Phase 1A of the Pan Borneo Highway (LPB) in Sabah is taking longer than anticipated, as stated by Deputy Works Minister, Datuk Seri Ahmad Maslan. Difficult land acquisition circumstances and the drawn-out utility relocation process are to blame for these delays.

He emphasized that the landowners' resistance to cooperate has caused delays and the need for an extension of time, with some even going so far as to file a lawsuit, according to Bernama.

As of August 2024, 79.48% of the 15 work packages in Phase 1A had been completed. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 km,” said Ahmad Maslan.

pan-borneo-highway.jpeg
“In addition, I hope the construction team can complete this project by meeting the quality, cost, and time standards set forth, in line with the MY Jalan KK programme’s goal of delivering comfortable and safe infrastructure for all Malaysia Madani people,” he added.



Tagged:

Pan Borneo Highway
Sarawak Pan Borneo Highway (LPB)
Sabah Pan Borneo Highway
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.

26-06-2024
Auto News
Pan Borneo highway status in Sabah and Sarawak

Pan Borneo highway status in Sabah and Sarawak

The condition of the Pan Borneo Highway in Sabah and Sarawak

06-12-2022
Auto News
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.

04-12-2025
Auto News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News
Pan Borneo Highway Project Will Be Completed This Year - Nanta

Pan Borneo Highway Project Will Be Completed This Year - Nanta

98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.

13-02-2024
Auto News
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.

26-06-2024

Latest News

Auto News
Zeekr 7X 2026 Pricing Updated - From RM183k, Up 1.8%

Zeekr 7X 2026 Pricing Updated - From RM183k, Up 1.8%

Zeekr Malaysia updates 7X pricing for 2026 following the end of EV tax incentives, with a modest increase of RM3,000-RM4,000 across variants.

06-02-2026
Auto News
Perodua CEO: Next-Gen Myvi In The Pipelines, Current Bezza Remains

Perodua CEO: Next-Gen Myvi In The Pipelines, Current Bezza Remains

In rare interview, Perodua CEO details plans for next-gen Myvi hatch, confirms current Bezza remains too.

06-02-2026
Auto News
UMW Toyota Records Slower January Sales, Down 12% to 4,700 Units

UMW Toyota Records Slower January Sales, Down 12% to 4,700 Units

UMW Toyota posts lower January sales as competition intensifies and electrification accelerates.

06-02-2026
Auto News
Malaysia’s Climate Plans Stop Short of Targeting Cars

Malaysia’s Climate Plans Stop Short of Targeting Cars

Private vehicles are unlikely to face direct climate targets as Malaysians remain heavily dependent on cars.

06-02-2026
Auto News
My50 Pass: Commuters Save RM100 Monthly

My50 Pass: Commuters Save RM100 Monthly

Over 50% of Klang Valley commuters are going digital with the My50 pass, saving RM100 monthly.

Auto News
LRT3 Shah Alam Line Expected To Open In June

LRT3 Shah Alam Line Expected To Open In June

After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.

05-02-2026
Auto News
First Johor Bahru–Singapore RTS Train Hits Woodlands

First Johor Bahru–Singapore RTS Train Hits Woodlands

The first Johor Bahru–Singapore RTS Link train has arrived in Singapore on Wednesday, as confirmed by LTA.

05-02-2026
Auto News
MTSB Bill in the Works to Streamline Transport Safety

MTSB Bill in the Works to Streamline Transport Safety

The MTSB Bill is being drafted to integrate agencies like MIROS and AAIB, ensuring efficient transport safety management.