Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

Anis

Share via

Sabah-Pan-Borneo-Highway-BONGAWAN-to-PAPAR-750x500.jpg

The construction of Phase 1A of the Pan Borneo Highway (LPB) in Sabah is taking longer than anticipated, as stated by Deputy Works Minister, Datuk Seri Ahmad Maslan. Difficult land acquisition circumstances and the drawn-out utility relocation process are to blame for these delays.

He emphasized that the landowners' resistance to cooperate has caused delays and the need for an extension of time, with some even going so far as to file a lawsuit, according to Bernama.

As of August 2024, 79.48% of the 15 work packages in Phase 1A had been completed. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 km,” said Ahmad Maslan.

pan-borneo-highway.jpeg
“In addition, I hope the construction team can complete this project by meeting the quality, cost, and time standards set forth, in line with the MY Jalan KK programme’s goal of delivering comfortable and safe infrastructure for all Malaysia Madani people,” he added.



Tagged:

Pan Borneo Highway
Sarawak Pan Borneo Highway (LPB)
Sabah Pan Borneo Highway
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.

26-06-2024
Auto News
Pan Borneo highway status in Sabah and Sarawak

Pan Borneo highway status in Sabah and Sarawak

The condition of the Pan Borneo Highway in Sabah and Sarawak

06-12-2022
Auto News
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.

04-12-2025
Auto News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News
Pan Borneo Highway Project Will Be Completed This Year - Nanta

Pan Borneo Highway Project Will Be Completed This Year - Nanta

98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.

13-02-2024
Auto News
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target

Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.

26-06-2024

Latest News

Auto News
MAA: Nov 2025 Vehicle Sales Dip 4.6% from Oct, BEV Rush Keeps Market Strong

MAA: Nov 2025 Vehicle Sales Dip 4.6% from Oct, BEV Rush Keeps Market Strong

MAA reported solid vehicle sales in Nov 2025, with 72,509 units sold, slightly lower than Oct’s 75,992 units.

19-12-2025
Auto News
Perodua QV-E Sales Outlets Now Expanded to 34 Locations

Perodua QV-E Sales Outlets Now Expanded to 34 Locations

Perodua has expanded the number of sales outlets for its QV-E EV to 34 locations from the original 9 outlets.

19-12-2025
Auto News
E-Hailing Drivers Must Hit 2,000KM To Unlock BUDI95 Extra Quota

E-Hailing Drivers Must Hit 2,000KM To Unlock BUDI95 Extra Quota

E-hailing drivers must now clock at least 2,000km a month to qualify for higher BUDI95 petrol quotas.

19-12-2025
Auto News
Honda Malaysia’s 25th Anniversary Campaign – November Winners Announced

Honda Malaysia’s 25th Anniversary Campaign – November Winners Announced

Honda Malaysia has announced the November winners of its 25th anniversary “Because of You” campaign.

19-12-2025
Auto News
Cable Theft Paralyzes Rail Services, Prasarana Urges Action From Govt

Cable Theft Paralyzes Rail Services, Prasarana Urges Action From Govt

Prasarana urges urgent nationwide measures to tackle rampant cable theft as RM20.6 million of lost has been reported.

19-12-2025
Auto News
Govt Announces 50% Christmas Toll Discount On Dec 23-24

Govt Announces 50% Christmas Toll Discount On Dec 23-24

Private car users will enjoy a 50% toll discount nationwide on Dec 23, 24 as the government rolls out festive travel relief for Christmas.

19-12-2025
Auto News
No Toll Hikes in 2026 As Govt Commits To Absorb Costs

No Toll Hikes in 2026 As Govt Commits To Absorb Costs

No toll hikes in 2026 as the government steps in and commits to absorb costs for which.

Auto News
O&J Highlights J7 PHEV Capabilities Through Customer Drive

O&J Highlights J7 PHEV Capabilities Through Customer Drive

O&J's nationwide drive brings customers together showcasing the J7 PHEV's efficiency in everyday conditions.