ECRL: Phase 1 Testing & Certification Will Begin in June 2026

Mukhlis Azman

Share via

thumb-ECRL-Testing.jpg

The testing and certification phase for the ECRL Phase 1 from Kota Bharu to Gombak will begin in June 2026.

The testing and certification phase for the East Coast Rail Link (ECRL) Phase 1 project from Kota Bharu, Kelantan, to Gombak, Selangor, will begin in June 2026, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.

Speaking to Bernama, the CEO explained that the testing process will be conducted to ensure the system is fully operational before the official launch date of the Phase 1 ECRL, which is set to take place in Jan 2027. Adding to that, Datuk Seri Darwis also said that the first set of 11 six-carriage Electric Multiple Unit (EMU) trains for passenger service is expected to arrive by year-end, along with the first 12 electric locomotives for freight service.

476250072_1163854502410103_838206193011837866_n.jpg

MRL CEO Datuk Seri Darwis Abdul Razak & Second Finance Minister YB Senator Datuk Seri Amir Hamzah Azizan

“The first EMU trains and locomotives are expected by November or December, with the remaining units arriving in stages next year,” he said after the launch of the Sustainable Development Goals (SDG) Sukuk Impact Report for the ECRL project, which was officiated by the Second Finance Minister Datuk Seri Amir Hamzah Azizan yesterday.

ECRL-KotaBharu-Tunjong-(1).jpgECRL-KotaBharu-Tunjong-(2).jpg

Darwis also revealed that all track installation works for the ECRL in Kelantan, Terengganu, and Pahang are set for completion by the end of the year. Meanwhile, an estimated 14.3 KM of excavation for the Genting Tunnel has been completed, with full tunnel penetration expected by May this year.

“The 400 KM track from Maran, Pahang, to Kota Bharu was completed on Jan 15. Installation works for the 100 KM stretch from Maran to Bentong will begin in April and be completed in three months,” the CEO added.

Finally, Datuk Seri Darwis has also confirmed that the overall progress of the ECRL project covering Kelantan, Terengganu, Pahang, and Selangor has reached 78.5% as of last month.

Source: Bernama


Gallery

Tagged:

East Coast Rail Link (ECRL)
Second Finance Minister Datuk Seri Amir Hamzah Azizan
Malaysia Rail Link Sdn Bhd (MRL)
ECRL Phase 1
ECRL Kota Bharu-Gombak
Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

Related News

Auto News
ECRL: KotaSAS Station System Installation Completed

ECRL: KotaSAS Station System Installation Completed

KotaSAS Station becomes first along ECRL route to complete installation of critical systems.

30-05-2025
Auto News
MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail

MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail

MiTRANS: Extending the ECRL to Sungai Golok would complete a key missing link in the ASEAN rail network.

22-05-2025
Auto News
Thai Ambassador Proposes ECRL Extension To Sungai Golok

Thai Ambassador Proposes ECRL Extension To Sungai Golok

Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.

16-05-2025
Auto News
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.

06-05-2025
Auto News
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.

29-04-2025
Auto News
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.

18-04-2025
Auto News
ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

MRL announces the completion of excavation work for 38 tunnels along the ECRL rail line.

09-04-2025
Auto News
ECRL 80% Complete, Shifting To Above-Ground Work

ECRL 80% Complete, Shifting To Above-Ground Work

The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.

27-03-2025

Latest News

Auto News
Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax

Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax

RON95 petrol subsidies to be rationalised ahead of 2026 carbon tax rollout, comes as part of Malaysia’s energy transition.

17-06-2025
Auto News
Malaysian Single-Mom Truckers Make Local Headlines

Malaysian Single-Mom Truckers Make Local Headlines

In a male-dominated industry, 39-year-old Irzunika Idris and 40-year-old Marlia Ramli became truck drivers to support their kids.

17-06-2025
Auto News
Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included

Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included

The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.

17-06-2025
Auto News
PRO-NET Opens Three New Proton e.MAS & smart Dealerships

PRO-NET Opens Three New Proton e.MAS & smart Dealerships

PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.

17-06-2025
Auto News
FT Dept, JPJ Told To Deal With Abandoned Vehicles

FT Dept, JPJ Told To Deal With Abandoned Vehicles

FT Dept and JPJ ordered to review and improve laws on abandoned vehicle disposal in KL and Putrajaya.

17-06-2025
Auto News
Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised

Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised

JPJ suspends Gerik crash bus driver’s PSV licence as investigations rule out technical failure.

17-06-2025
Auto News
PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza

PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza

PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).

16-06-2025
Auto News
RON95 Petrol Subsidy Rationalisation Will Proceed – PMX

RON95 Petrol Subsidy Rationalisation Will Proceed – PMX

The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.

16-06-2025