Pedas RSA Build Reaches 43% Ahead Of Rescheduled Q1 2026 Opening

Kumeran Sagathevan

Share via

PEDAS-RSA---2025-04-2.jpg


Following up on our earlier coverage, the Pedas RSA at KM 241 (Southbound) on the PLUS North-South Expressway continues to take shape as Malaysia’s first privately-operated Rest Service Area (RSA).

Developed by Levn Capital with the approval of the Malaysian Highway Authority (LLM), the project is set to deliver a new and elevated experience for southbound travellers.


project-03-copy.jpg


Located just 84 KM south of Kuala Lumpur, the RSA enjoys dual access from both the expressway and nearby local roads. It is designed to serve highway users as well as the surrounding Kampung Pedas Hilir community, including students from nearby institutions.

As of the end of March 2025, construction progress remains strong at 43% completion. Approximately 70% of the 1st-floor slab casting for the main complex has been completed, marking a major structural milestone.


image-(11)-(1).jpg


In parallel, all three drive-thru satellite buildings have successfully completed concrete roof casting. These outlets will provide quick, convenient services to meet the needs of today’s on-the-go travellers.


PEDAS-RSA---2025-04-1.jpg


To recap, the Pedas RSA will feature Malaysia’s first Electric Vehicle Charging Corridor (EVCC), offering 350 kW DC fast chargers developed in partnership with Gentari and Tesla. This positions the RSA as a key node in the nation’s emerging EV infrastructure.

The site will also house Petronas and Shell refuelling stations, creating a comprehensive hub for both electric and traditional vehicles.

With sustainability as a core design principle, the Pedas RSA is being developed as a Platinum-rated Green Building. It will include energy-efficient lighting, rainwater harvesting, and naturally lit communal areas. Travellers can also look forward to well-known F&B brands such as McDonald’s, Coffee Bean, and Tealive.


web_CariCarz_MA_Tesla-Malaysia-Gamuda-Cove-Supercharger_-16.jpgCaricarz-MINI-Electric-ResoluteEditon-Ext-4-full.jpg


Strategically positioned along the high-traffic corridor between Kuala Lumpur and Singapore, the RSA is well-placed to serve commuters, long-distance travellers, and the local community.

According to Levn Capital, the project originally slated for a Q4 2025 opening, has been rescheduled to Q1 2026 to ensure the highest standards of delivery. We will continue to provide updates as the project progresses, as this facility is set to become a vital connection point for the growing needs of long-distance highway commuters.




Tagged:

Pedas RSA
PLUS Pedas-Linggi Layby Southbound
Electric Vehicle Charging Corridor (EVCC)
Levn Capital
rest and service areas (RSAs)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

EV

Yinson GreenTech, PLUS Ink JV for Integrated EV Charging Hubs

Yinson GreenTech and PLUS join forces to develop full-service EV charging hubs along North-South Expressway.

EV

Pedas RSA: Nation's First 350 kW EV Charging Corridor Powered by Gentari & Tesla

PEDAS RSA - First privately-operated rest area with 350 kW Electric Vehicle Charging Corridor.

Auto News

Petron Malaysia Opens Milestone 800th Service Station

Petron Malaysia officially opens milestone 800th service station at PLUS Pedas-Linggi Layby Southbound.

14-01-2025
EV

Pedas RSA: Nation's First 350 kW EV Charging Corridor Powered by Gentari & Tesla

PEDAS RSA - First privately-operated rest area with 350 kW Electric Vehicle Charging Corridor.

EV

Pedas RSA: Nation's First 350 kW EV Charging Corridor Powered by Gentari & Tesla

PEDAS RSA - First privately-operated rest area with 350 kW Electric Vehicle Charging Corridor.

Auto News

Authorities Investigating Viral DASH Highway ‘Drifters’

Authorities investigating viral DASH Highway ‘Drifters’ for reckless driving acts at the Denai Alam Toll Plaza of the DASH Highway.

27-02-2023
Auto News

Temporary Closure Of PLUS Rest Areas

Rest and Service areas (RSAs) and lay-bys would be temporarily closed to the public for maintenance.

15-12-2022

Latest News

EV

Honda Super-One EV Specs Detailed – Single FWD Motor, Boost Mode

Honda has unveiled more specifications for its upcoming kei EV hot-hatch, the Honda Super-One, ahead of its Japanese debut.

13-02-2026
EV

Mazda 6e EV Debuts in the UK – Malaysia Next?

The UK becomes the next right-hand-drive market to welcome the sleek Mazda 6e EV saloon. Is Malaysia next?

12-02-2026
EV

MITI: Malaysia’s EV Strategy Enters New Phase

EV adoption surged to 44,813 units in 2025 as the country shifts focus toward local assembly and EV ecosystem.

EV

2027 Toyota Highlander EV Debuts in the US – Three-Row EV SUV with 515 km Range

The Toyota Highlander has been revived as a three-row, all-electric SUV for its next-gen iteration.

11-02-2026
EV

BYD Atto 3 Evo: 800V Architecture, 449 PS and 220 kW DC Charging

BYD’s Atto 3 Evo makes a big step forward with 800V tech, up to 449 PS and 220 kW DC fast charging.

EV

Updated 2026 Denza D9 Leaked, Has Up To 557 PS Now Too

Refreshed 2026 model year version of the Denza D9 luxury EV MPV leaks online, reportedly gains more power too – up to 557 PS touted.

10-02-2026
EV

Ferrari Luce – Brand’s First EV Name & Interior Unveiled Ahead of Debut

Ferrari’s first EV will be known as the Luce, featuring a button-laden interior penned by a former Apple designer.

10-02-2026
EV

Shell Malaysia Eyes Dynamic EV Charging Rate as Network Scales

Shell Malaysia to reviews EV charging rates competitiveness as it explores dynamic pricing and expands its nationwide network.