Penang LRT Project Progressing Steadily - MRT Corp

Anis

Share via

Muhammad-Kifli-Ma-Hassan.-(61).png
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.


MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.

This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
634250378d788477a2115c11f51aa283-(1).jpg


With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.

In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that  utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.

17977720-projek-lrt-mutiara-bernama-210425.jpeg


The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung. It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.

Tagged:

Penang Mutiara Line LRT Project
Penang LRT Project
Mass Rapid Transit Corporation Sdn Bhd (MRT Corp)
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
Penang LRT Stays Within RM16 Billion Budget - MRT Corp

Penang LRT Stays Within RM16 Billion Budget - MRT Corp

Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.

30-07-2025
Auto News
Penang Still Waiting For Green Light From MOT For LRT project

Penang Still Waiting For Green Light From MOT For LRT project

Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.

02-07-2025
Auto News
Mutiara LRT Issues Resolved , Earthworks Commencing Soon

Mutiara LRT Issues Resolved , Earthworks Commencing Soon

Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.

11-06-2025
Auto News
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.

Auto News
Penang Mutiara LRT Project Poised To Commence In 2025

Penang Mutiara LRT Project Poised To Commence In 2025

Loke announces phase 1 of Penang Mutiara LRT project will commence early next year.

Auto News
Penang Confirms LRT Work Construction To Begin In December

Penang Confirms LRT Work Construction To Begin In December

December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.

09-10-2024
Auto News
Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B

Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B

The Juru-Sungai Dua Elevated Highway is set to cost RM1.8B, project will be undertaken by PLUS on a Public-Private Partnership basis.

Auto News
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT

Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT

Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.

Latest News

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025
Auto News
1,489 Summonses Issued in VEP Enforcement Operation – JPJ

1,489 Summonses Issued in VEP Enforcement Operation – JPJ

JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.

04-08-2025
Auto News
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.

04-08-2025
Auto News
RM110 Million Collected from Special Plate Sales Since 2023 – MoT

RM110 Million Collected from Special Plate Sales Since 2023 – MoT

A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.

04-08-2025
Auto News
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.

Auto News
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News
ETS to JB Sentral ‘On Track’, But Not Quite There Yet

ETS to JB Sentral ‘On Track’, But Not Quite There Yet

KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.