A surge in cable and equipment thefts has jeopardised the timely completion of the East Coast Rail Link (ECRL), Malaysia’s key infrastructure project linking the Klang Valley to the East Coast.

According to Malaysia Rail Link (MRL) Sdn Bhd, 81 outdoor transformer units and over 1,200 metres of signalling cables have been stolen along the route, as reported by The Star yesterday.
ECRL-KotaBharu-Tunjong-(2)-full.jpg

The theft of these custom-made components, some of which could take up to six months to replace, has raised serious concerns about potential delays.

“The thefts may delay the project delivery. We were very much looking forward to the testing and commissioning phase in June next year,” said MRL Chief Executive Officer Datuk Seri Darwis Abdul Razak.
Untitled-design---2025-06-23T105157.544.png

Slated for completion by 2027, this 665-kilometre rail line, now 82.45% complete, is designed for both passenger and freight transport, with trains capable of reaching speeds of 160 km/h for passengers and 80 km/h for cargo.

However, since the installation of Communications, Information, and Signalling (CIS) systems began at KotaSAS Station in Pahang in March, theft incidents have been reported at no fewer than seven locations across Pahang, Terengganu, and Kelantan.

Untitled-design---2025-06-23T105257.543.png

According to Darwis, as the project is still under the contractor’s responsibility, any losses from the thefts will be borne by China Communications Construction Company (CCCC-ECRL).


“That said, we as the project owner will also do our part to curb this problem. The ECRL project team is working closely with police to engage those in the scrap collection or recycling business,” he said, adding that MRL will meet police and ministers to boost ECRL security with patrols, CCTV, and fencing at ground level.

Untitled-design---2025-06-23T105222.500.png

In other developments,  Darwis stated that all land acquisition for the main ECRL alignment from Kota Bharu, Kelantan, to Port Klang, Selangor, has been completed with the support of the respective state governments.

He also announced that 38 tunnels have been bored along the route. The last two, the Genting Twin Tunnel and Serendah Tunnel 2, are expected to be completed by the end of this month and early next month, respectively.





















Tagged:

East Coast Rail Link (ECRL)
ECRL contruction progress
ECRL cable thefts
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL: KotaSAS Station System Installation Completed

ECRL: KotaSAS Station System Installation Completed

KotaSAS Station becomes first along ECRL route to complete installation of critical systems.

30-05-2025
Auto News
MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail

MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail

MiTRANS: Extending the ECRL to Sungai Golok would complete a key missing link in the ASEAN rail network.

22-05-2025
Auto News
Thai Ambassador Proposes ECRL Extension To Sungai Golok

Thai Ambassador Proposes ECRL Extension To Sungai Golok

Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.

16-05-2025
Auto News
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.

06-05-2025
Auto News
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.

29-04-2025
Auto News
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.

18-04-2025
Auto News
ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

MRL announces the completion of excavation work for 38 tunnels along the ECRL rail line.

09-04-2025
Auto News
ECRL 80% Complete, Shifting To Above-Ground Work

ECRL 80% Complete, Shifting To Above-Ground Work

The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.

27-03-2025

Latest News

Auto News
Customised Proton X90 Delivered to Tengku Laksamana Selangor

Customised Proton X90 Delivered to Tengku Laksamana Selangor

A customised, two-toned Proton X90 was delivered to the Tengku Laksamana of Selangor, YAM Tengku Sulaiman Shah.

23-06-2025
Auto News
Raise Heavy Vehicle Taxes To Fund Road Repairs - Expert

Raise Heavy Vehicle Taxes To Fund Road Repairs - Expert

Expert proposes higher taxes on heavy vehicles to address their impact on road damage.

23-06-2025
Auto News
Setel Pump-and-Pay Integrated Into TNG eWallet

Setel Pump-and-Pay Integrated Into TNG eWallet

Setel and TNG Digital will offer simplified fuel payments, and integrate rewards into one app experience.

23-06-2025
Auto News
JPJ Will Audit 500 High-Risk Bus, Lorry Operators

JPJ Will Audit 500 High-Risk Bus, Lorry Operators

Starting June 23, JPJ will launch safety checks on 500 high-risk goods and passenger transport operators under the JISA Op.

23-06-2025
Auto News
Cable Thefts Put ECRL Timeline At Risk - MRL Chief

Cable Thefts Put ECRL Timeline At Risk - MRL Chief

Spike in cable and equipment thefts threatens ECRL completion timeline, says MRL CEO

23-06-2025
Auto News
JRTB Gets RM55M for Repairs, Staged Rollout Planned

JRTB Gets RM55M for Repairs, Staged Rollout Planned

JKR to begin phased repairs on Gerik–Jeli stretch with RM55 million allocation.

23-06-2025
Auto News
KLIA Aerotrain Set To Resume Service On July 1

KLIA Aerotrain Set To Resume Service On July 1

KLIA Aerotrain is set to resume operations on July 1, following successful trials after years of suspension.

21-06-2025
Auto News
Michelin 24H Series Heads to Malaysia for 2025/2026 Season

Michelin 24H Series Heads to Malaysia for 2025/2026 Season

The Michelin 24H Series is heading to Malaysia next season, with the 12H Malaysia round set to be the season opener.

21-06-2025