The Light Rail Transit 3 (LRT3) project, which will connect Bandar Utama to Johan Setia in Klang, is almost ready for launch. As of July 10, the line was 99.21 percent complete, according to Transport Minister Anthony Loke.

In a written reply to Parliament, Loke reaffirmed the government’s commitment to delivering the project safely and on schedule. The line is expected to begin operations on September 30.

Responding to a question from Permatang Pauh MP Muhammad Fawwaz Mohamad Jan on delays and rising costs, Loke explained that progress had been significantly impacted by the COVID-19 pandemic. 

“Construction was halted during the Movement Control Order between March 2020 and October 2021, which caused major disruptions to timelines, supply chains, and material availability.

“Labour shortages that followed further slowed the pace of work,” the minister said. Intro-42-1.jpg Initially approved in 2015 with a price tag of RM31.65 billion, the project’s cost was reduced to RM16.63 billion in 2018 after a major restructuring exercise. That revision saved the government over RM15 billion by scaling back certain components.

However, in 2024, the government decided to restore parts of the original scope to meet future demand.

“The reinstated elements included five additional stations, seven more train sets, an expanded depot in Johan Setia, the purchase of 150 electric feeder buses, and the construction of three new bus depots,” Loke said, adding that these additions brought the total cost to RM21.93 billion.

LRT3-Line-integration-map.jpg
Despite the higher cost, the enhancements are aimed at improving service coverage and long-term reliability.

Once fully operational, the LRT3 will serve key areas such as Bandar Utama, Shah Alam, and Klang. It’s designed to carry up to 18,630 passengers per hour in each direction and benefit roughly two million residents living along the route.



Tagged:

LRT 3
Setia Utama LRT 3 Sdn Bhd
public transportation sector
Minister of Transport YB Anthony Loke
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.

Auto News
Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.

Auto News
Five LRT3 Stations Set To Be Operational In 2027

Five LRT3 Stations Set To Be Operational In 2027

Five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027, says Loke.

11-01-2024
Auto News
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News
Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.

Auto News
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News
A Single Public Transport Trip Eliminates 300 Cars From Traffic - Loke

A Single Public Transport Trip Eliminates 300 Cars From Traffic - Loke

A single public transport journey can reduce traffic congestion in densely populated areas by removing 300 vehicles from the road.

05-06-2025
Auto News
Public Transport Usage Rates In Malaysia Are Worryingly Low - Ahmad Zahid

Public Transport Usage Rates In Malaysia Are Worryingly Low - Ahmad Zahid

Malaysia's public transport usage lags behind several modern nations like Singapore, Seoul and Tokyo, says DPM Ahmad Zahid.

15-05-2025

Latest News

Auto News
Petrol Cards And Civil Servant Perks On Offer By Jetour Malaysia This Month

Petrol Cards And Civil Servant Perks On Offer By Jetour Malaysia This Month

Up to RM1 million worth of free petrol cards plus special perks for civil servants on offer from Jetour Malaysia this month.

20-09-2025
Auto News
TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.

19-09-2025
Auto News
MyKad Checks Urged Ahead of Fuel Price Drop

MyKad Checks Urged Ahead of Fuel Price Drop

Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.

19-09-2025
Auto News
GAC Emkoo Awarded 5-star ASEAN NCAP Rating

GAC Emkoo Awarded 5-star ASEAN NCAP Rating

Upcoming GAC Emkoo C-SUV earns coveted 5-star rating form ASEAN NCAP crash-testing regime.

19-09-2025
Auto News
KLCC Roads Closed Saturday For Sarong Music Run

KLCC Roads Closed Saturday For Sarong Music Run

Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.

19-09-2025
Auto News
Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.

19-09-2025
Auto News
Customs Seizes 32 Imported Cars Worth RM8.45 Million

Customs Seizes 32 Imported Cars Worth RM8.45 Million

Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.

19-09-2025
Auto News
MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

Latest MAA Aug 2025 sales figures see PVs contribute 67,302 units, with CVs taking the remaining 5,739.