LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
![]()
The Light Rapid Transit 3 (LRT3) project, which covers about 37 KM from Bandar Utama, Petaling Jaya, to Klang, will now cost RM21.93 billion. Said costs includes the reinstatement of five key stations: Tropicana, Raja Muda, Temasya, Bukit Raja, and Botanic City.
Deputy Transport Minister Datuk Hasbi Habibollah noted that the project was originally approved in 2015 at a cost of RM31.65 billion. However, in 2018, it was delayed due to cost-cutting measures, even though nearly 90% of the work was completed.
-full_normal.jpg)
“The revised project cost, after reducing its scope, stood at RM16.63 billion, with an additional RM5.3 billion needed to reinstate the five stations. This is a potential saving of RM9.72 billion compared to the initial amount approved in 2015,” said Hasbi in response to Azahari Hasan (Pakatan Nasional-Padang Rengas) in Dewan Rakyat.
He however also added that the reinstatement of these stations is pending approval and funding from the Finance Ministry and the Economic Ministry.
-full_normal.jpg)
Currently, Prasarana Malaysia Bhd is working on finalising the technical aspects, including the design of the stations and a new financial agreement. The design phase is expected to be completed by early next year, and construction is targeted to begin by the end of 2025.
“Construction of the five stations is expected to wrap up by the fourth quarter of 2027, with operations set to commence by the second quarter of 2028,” Hasbi added.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQD7825
SELANGOR
BSK8756
JOHOR
JYM8964
PULAU PINANG
PRW6011
PERAK
APD4031
PAHANG
CFE4685
KEDAH
KGD4501
NEGERI SEMBILAN
NEH9159
KOTA KINABALU
SJP3024
KUCHING
QAB7469M
Last updated 17 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
LRT3 Hits 99% Completion - Loke
LRT3, which will connect Bandar Utama to Johan Setia, is 99% complete and on track for launch, says Transport Minister.
30-07-2025
Federal Highway Lane Closure For LRT 3 Project Construction Works
Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.
24-07-2024
Five LRT3 Stations Set To Be Operational In 2027
Five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027, says Loke.
11-01-2024
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
RM110 Million Collected from Special Plate Sales Since 2023 – MoT
A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.
04-08-2025
652 Heavy Vehicle Accidents Recorded, Weigh-in Motion System Coming Soon
Q1 2024 saw 652 accidents involving heavy vehicles resulting in 287 fatalities due to various reasons including speeding and overloading.
24-06-2024
Prasarana Set To Roll Out 1,045 Electric Buses By 2030
Prasarana is set to roll out more than 1,045 electric buses across Kuala Lumpur and Penang by 2030.
08-12-2025
Klang Valley Trains Improving, Prasarana to Report Performance - Loke
Despite commuter complaints, rail services are running smoother than a few years ago, with fewer disruptions and new trains on the way.
08-12-2025
Latest News
No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1
Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.
16-12-2025
OMODA & JAECOO Wrap Up 2025 With Season of Rewards
OMODA & JAECOO 2025 Season of Rewards offers extended service packages and practical ownership benefits.
16-12-2025
Overloaded Trucks Crackdown Showing Results, Transport Rates Remain Stable
Strict enforcement against overloaded trucks is paying off, improving road safety and transport efficiency without hiking rates.
16-12-2025
Gemas-JB ETS Needs Better Access To Curb City Traffic - Expert
Experts urge improved first-mile access, feeder buses, and park-and-ride options for the Gemas- JB ETS.
16-12-2025
SCS Adopts Advanced European Testing Systems
SCS raises the bar for vehicle inspections with advanced European testing technology.
16-12-2025
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
Bollards Are There for Your Safety, Not Decoration - DBKL
DBKL is reminding the public that bollards play a crucial role in keeping pedestrians safe.
15-12-2025
Show More
trending_flat