LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
![]()
The Light Rapid Transit 3 (LRT3) project, which covers about 37 KM from Bandar Utama, Petaling Jaya, to Klang, will now cost RM21.93 billion. Said costs includes the reinstatement of five key stations: Tropicana, Raja Muda, Temasya, Bukit Raja, and Botanic City.
Deputy Transport Minister Datuk Hasbi Habibollah noted that the project was originally approved in 2015 at a cost of RM31.65 billion. However, in 2018, it was delayed due to cost-cutting measures, even though nearly 90% of the work was completed.
-full_normal.jpg)
“The revised project cost, after reducing its scope, stood at RM16.63 billion, with an additional RM5.3 billion needed to reinstate the five stations. This is a potential saving of RM9.72 billion compared to the initial amount approved in 2015,” said Hasbi in response to Azahari Hasan (Pakatan Nasional-Padang Rengas) in Dewan Rakyat.
He however also added that the reinstatement of these stations is pending approval and funding from the Finance Ministry and the Economic Ministry.
-full_normal.jpg)
Currently, Prasarana Malaysia Bhd is working on finalising the technical aspects, including the design of the stations and a new financial agreement. The design phase is expected to be completed by early next year, and construction is targeted to begin by the end of 2025.
“Construction of the five stations is expected to wrap up by the fourth quarter of 2027, with operations set to commence by the second quarter of 2028,” Hasbi added.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPX9541
SELANGOR
BSJ8736
JOHOR
JYK5467
PULAU PINANG
PRV4293
PERAK
APC3014
PAHANG
CFD9630
KEDAH
KGC8422
NEGERI SEMBILAN
NEH5206
KOTA KINABALU
SJN5238
KUCHING
QAB4725M
Last updated 02 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
LRT3 Hits 99% Completion - Loke
LRT3, which will connect Bandar Utama to Johan Setia, is 99% complete and on track for launch, says Transport Minister.
30-07-2025
Federal Highway Lane Closure For LRT 3 Project Construction Works
Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.
24-07-2024
Five LRT3 Stations Set To Be Operational In 2027
Five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027, says Loke.
11-01-2024
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
RM110 Million Collected from Special Plate Sales Since 2023 – MoT
A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.
04-08-2025
652 Heavy Vehicle Accidents Recorded, Weigh-in Motion System Coming Soon
Q1 2024 saw 652 accidents involving heavy vehicles resulting in 287 fatalities due to various reasons including speeding and overloading.
24-06-2024
MRT Putrajaya Line Repairs Ongoing After Cable Theft Disruption
Cable theft near Taman Desa cripples MRT Putrajaya Line operations, forcing manual train runs.
26-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
Latest News
VEP: No Exit Without Permit, Crackdown Begins Nov 15
Foreign vehicles, particularly from Singapore, cannot leave Malaysia without an active VEP and fines fully settled.
01-11-2025
BUDI95 Fuel Shortfall Claims Untrue - KPDN
KPDN says claims of fuel shortfalls under the BUDI95 are unfounded after inspections found all petrol pumps accurate.
31-10-2025
LPT3 Will Proceed Under Public-Private Partnership Model - Ahmad Maslan
RM9.8b East Coast Expressway 3 (LPT3) will be developed via public-private partnership at no cost to the government.
31-10-2025
Suzuki Fronx Secures 5-Star ASEAN NCAP Rating
The new Suzuki Fronx achieves full 5-star ASEAN NCAP rating, scoring 77.70 points under latest 2021–2025 protocol.
31-10-2025
Loke Orders MAHB To Keep Shuttle Bus Amid KLIA Aerotrain Woes
Transport minister says shuttle buses must stay as investigations continue into repeated aerotrain breakdowns.
31-10-2025
KPDN Busts Pig Slaughterhouse For Illegal Diesel Storage
Authorities seized 2,000L of subsidised diesel hidden inside a Perak pig slaughterhouse.
30-10-2025
Govt Won’t Suspend KLIA Aerotrain, MAHB Facing Action - Loke
Loke says the government won’t halt the KLIA Aerotrain, but MAHB is facing action.
30-10-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
Show More
trending_flat