The Light Rail Transit 3 (LRT3) project, which will connect Bandar Utama to Johan Setia in Klang, is almost ready for launch. As of July 10, the line was 99.21 percent complete, according to Transport Minister Anthony Loke.

In a written reply to Parliament, Loke reaffirmed the government’s commitment to delivering the project safely and on schedule. The line is expected to begin operations on September 30.

Responding to a question from Permatang Pauh MP Muhammad Fawwaz Mohamad Jan on delays and rising costs, Loke explained that progress had been significantly impacted by the COVID-19 pandemic. 

“Construction was halted during the Movement Control Order between March 2020 and October 2021, which caused major disruptions to timelines, supply chains, and material availability.

“Labour shortages that followed further slowed the pace of work,” the minister said. Intro-42-1.jpg Initially approved in 2015 with a price tag of RM31.65 billion, the project’s cost was reduced to RM16.63 billion in 2018 after a major restructuring exercise. That revision saved the government over RM15 billion by scaling back certain components.

However, in 2024, the government decided to restore parts of the original scope to meet future demand.

“The reinstated elements included five additional stations, seven more train sets, an expanded depot in Johan Setia, the purchase of 150 electric feeder buses, and the construction of three new bus depots,” Loke said, adding that these additions brought the total cost to RM21.93 billion.

LRT3-Line-integration-map.jpg
Despite the higher cost, the enhancements are aimed at improving service coverage and long-term reliability.

Once fully operational, the LRT3 will serve key areas such as Bandar Utama, Shah Alam, and Klang. It’s designed to carry up to 18,630 passengers per hour in each direction and benefit roughly two million residents living along the route.



Tagged:

LRT 3
Setia Utama LRT 3 Sdn Bhd
public transportation sector
Minister of Transport YB Anthony Loke
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.

Auto News

Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.

Auto News

Five LRT3 Stations Set To Be Operational In 2027

Five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027, says Loke.

11-01-2024
Auto News

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News

Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.

Auto News

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News

A Single Public Transport Trip Eliminates 300 Cars From Traffic - Loke

A single public transport journey can reduce traffic congestion in densely populated areas by removing 300 vehicles from the road.

05-06-2025
Auto News

Public Transport Usage Rates In Malaysia Are Worryingly Low - Ahmad Zahid

Malaysia's public transport usage lags behind several modern nations like Singapore, Seoul and Tokyo, says DPM Ahmad Zahid.

15-05-2025

Latest News

Auto News

JPJ: RM3 Million Rolls-Royce Among 53 Vehicles Seized

JPJ Ops Luxury 2.0 sees 53 high-end vehicles, including a Rolls-Royce Cullinan and Lamborghini Huracan, seized over expired road tax and insurance.

Auto News

Malaysian-Bound Toyota Yaris Cross Receives 5-Star ASEAN NCAP Score

The DNGA-based Toyota Yaris Cross just received a five-star score for the ASEAN NCAP crash test. Coming to Malaysia soon?

02-08-2025
Auto News

Chery’s Lepas Brand Entering Malaysia Soon? ‘Official’ IG Page Sighted

New ‘official’ IG page we sighted by chance indicates Chery’s new Lepas sub-brand is set to enter Malaysia very soon.

01-08-2025
Auto News

Govt Looking To Revive MEX II Highway With New Completion Plan

The government is working with bondholders to restart the long-delayed MEX II Highway.

01-08-2025
Auto News

2025 Proton X50 Facelift Sees 999 Units Shifted In 5 Days

2025 Proton X50 Facelift sees 999 units delivered in just five days, production hits 2,000 units mark as of end of July too.

01-08-2025
Auto News

Bridgestone Turanza 6 Tyres Launched in Malaysia – 14 to 21 Inches, EV-Ready

Bridgestone Malaysia has introduced the new Turanza 6 tyres in Malaysia, with sizes ranging from 14 to 21 inches.

01-08-2025
Auto News

Johor Proposes RTS2 Link Between Iskandar Puteri and Tuas

With Bukit Chagar terminal nearing completion, Johor eyes new RTS2 link to Tuas to further ease cross-border travel.

Auto News

PAC to KKR: Avoid Costly Missteps in Delayed MLFF Rollout

PAC wants KKR to ensure no hidden costs to government or road users in the upcoming MLFF toll system rollout.