WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPF6796
SELANGOR
BSF3554
JOHOR
JYA1346
PULAU PINANG
PRR3461
PERAK
ANW4750
PAHANG
CFB9583
KEDAH
KGA8415
NEGERI SEMBILAN
NEG1752
KOTA KINABALU
SJL1797
KUCHING
QAB4843L
Last updated 07 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
-0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
-0.03
EURO 5 B7
RM 2.94
-0.03
Last updated 05 Jun, 2025
Related News
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion
ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.
16-01-2025
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection
WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.
29-11-2024
WCE Extension Banting-Gelang Patah Set To Provide NSE Alternative
WCE, which will connect Banting to Gelang Patah, is set to reduce the traffic congestion on the NSE.
04-11-2024
Selangor MB Proposes Extension Of WCE To KLIA
Selangor MB proposed that WCE be extended to Kuala Lumpur International Airport.
28-10-2024
Toll Collection On Section 1 Of WCE To Commence On Monday
Toll collection will begin on the WCE (Section 1) from 12.01am on Monday (Sept 30).
28-09-2024
WCE Section 1 Is Toll-Free Until Sept 29 Ahead Of National Day
Public Works Minister Datuk Seri Alexander Nanta Linggi announced that users of the WCE passing through the Banting Interchange Section 1 are eligible for free toll starting tonight at 12.01 until Sept 29, 11.59pm.
30-08-2024
Latest News
Render: Can A New Third-Gen Proton Perdana Thrive Today?
Artist @theottle renders Geely A7-based third-gen Proton Perdana, and it makes us wonder if it can thrive today…
06-06-2025
5,000 Retrenched As Petronas ‘Reinvents’ Itself
Petronas ‘reinvents’ itself, job cuts totalling up to 5,000 people, promotion freeze, and revamped processes comes in wake of which.
06-06-2025
Govt Mulling Housing Projects Above Train Stations To Tackle Traffic Jam
The government is considering constructing residential buildings above train stations to reduce traffic congestion.
06-06-2025
PDRM Deploys Op Lancar Ahead of Aidiladha Festive Period
PDRM deploys thousands of its officers for Op Lancar to ensure safe and smooth traffic flow during this Aidiladha festive period.
06-06-2025
Two Of 10 New ETS Train Sets Delivered To KTMB
Two of 10 new ETS sets, valued at RM400 million, have already been delivered to KTMB.
06-06-2025
Govt's "Road To Rail" Project Aims To Lower Lorry-Related Crashes
MOT is working on the "Road to Rail" initiative to enhance road safety and lower heavy vehicle accidents.
06-06-2025
AWAS System Under Fire: Malaysia’s Road Safety Debate
Malaysians blast AWAS system, accuses govt of prioritising fines over fixing fatal lorry risks.
06-06-2025
Scheduled Maintenance Works On Besraya Highway Until Nov 30
Besraya highway reportedly set to see maintenance works performed nightly until Nov 30, prompting lane closures in stages.
05-06-2025
Show More
trending_flat