WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
-full_normal.webp)
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
-full_normal.webp)
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
-full_normal.webp)
-full_normal.webp)
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQE2574
SELANGOR
BSK9754
JOHOR
JYN1654
PULAU PINANG
PRW6742
PERAK
APD4546
PAHANG
CFE4872
KEDAH
KGD4808
NEGERI SEMBILAN
NEH9475
KOTA KINABALU
SJP3444
KUCHING
QAB7656M
Last updated 19 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
Latest News
Honda Malaysia’s 25th Anniversary Campaign – November Winners Announced
Honda Malaysia has announced the November winners of its 25th anniversary “Because of You” campaign.
19-12-2025
Cable Theft Paralyzes Rail Services, Prasarana Urges Action From Govt
Prasarana urges urgent nationwide measures to tackle rampant cable theft as RM20.6 million of lost has been reported.
19-12-2025
Govt Announces 50% Christmas Toll Discount On Dec 23-24
Private car users will enjoy a 50% toll discount nationwide on Dec 23, 24 as the government rolls out festive travel relief for Christmas.
19-12-2025
No Toll Hikes in 2026 As Govt Commits To Absorb Costs
No toll hikes in 2026 as the government steps in and commits to absorb costs for which.
19-12-2025
O&J Highlights J7 PHEV Capabilities Through Customer Drive
O&J's nationwide drive brings customers together showcasing the J7 PHEV's efficiency in everyday conditions.
18-12-2025
JPJ Warns Public Over Fake ‘EE’ Plate Series
JPJ clarifies that the vehicle registration series ‘EE’ circulating online is completely fake.
18-12-2025
94% of Malaysian Road Vehicles Checked are Emission-Compliant – JAS
Compliance among motor vehicles with the emission regulation has risen to 94%, the Department of Environment revealed.
18-12-2025
JPJ Summons Discount Ending, 4.9 Millions Remain Unpaid
4.9 million summonses still unpaid as JPJ’s half-price scheme nears its end.
18-12-2025
Show More
trending_flat