WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPG4263
SELANGOR
BSF5053
JOHOR
JYA4985
PULAU PINANG
PRR4956
PERAK
ANW6749
PAHANG
CFC1439
KEDAH
KGA9426
NEGERI SEMBILAN
NEG2387
KOTA KINABALU
SJL3071
KUCHING
QAB5149L
Last updated 17 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
EURO 5 B7
RM 2.94
Last updated 12 Jun, 2025
Related News
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims
WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.
13-06-2025
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion
ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.
16-01-2025
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection
WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.
29-11-2024
WCE Extension Banting-Gelang Patah Set To Provide NSE Alternative
WCE, which will connect Banting to Gelang Patah, is set to reduce the traffic congestion on the NSE.
04-11-2024
Selangor MB Proposes Extension Of WCE To KLIA
Selangor MB proposed that WCE be extended to Kuala Lumpur International Airport.
28-10-2024
Toll Collection On Section 1 Of WCE To Commence On Monday
Toll collection will begin on the WCE (Section 1) from 12.01am on Monday (Sept 30).
28-09-2024
Latest News
Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax
RON95 petrol subsidies to be rationalised ahead of 2026 carbon tax rollout, comes as part of Malaysia’s energy transition.
17-06-2025
Malaysian Single-Mom Truckers Make Local Headlines
In a male-dominated industry, 39-year-old Irzunika Idris and 40-year-old Marlia Ramli became truck drivers to support their kids.
17-06-2025
Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included
The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.
17-06-2025
PRO-NET Opens Three New Proton e.MAS & smart Dealerships
PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.
17-06-2025
FT Dept, JPJ Told To Deal With Abandoned Vehicles
FT Dept and JPJ ordered to review and improve laws on abandoned vehicle disposal in KL and Putrajaya.
17-06-2025
Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised
JPJ suspends Gerik crash bus driver’s PSV licence as investigations rule out technical failure.
17-06-2025
PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza
PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).
16-06-2025
RON95 Petrol Subsidy Rationalisation Will Proceed – PMX
The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.
16-06-2025
Show More
trending_flat