WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPM4876
SELANGOR
BSG7495
JOHOR
JYE4583
PULAU PINANG
PRT719
PERAK
ANY6825
PAHANG
CFD467
KEDAH
KGB6291
NEGERI SEMBILAN
NEG6315
KOTA KINABALU
SJL9999*
KUCHING
QAB8361L
Last updated 02 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims
WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.
13-06-2025
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion
ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.
16-01-2025
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection
WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.
29-11-2024
WCE Extension Banting-Gelang Patah Set To Provide NSE Alternative
WCE, which will connect Banting to Gelang Patah, is set to reduce the traffic congestion on the NSE.
04-11-2024
Selangor MB Proposes Extension Of WCE To KLIA
Selangor MB proposed that WCE be extended to Kuala Lumpur International Airport.
28-10-2024
Toll Collection On Section 1 Of WCE To Commence On Monday
Toll collection will begin on the WCE (Section 1) from 12.01am on Monday (Sept 30).
28-09-2024
Latest News
JPJ: RM3 Million Rolls-Royce Among 53 Vehicles Seized
JPJ Ops Luxury 2.0 sees 53 high-end vehicles, including a Rolls-Royce Cullinan and Lamborghini Huracan, seized over expired road tax and insurance.
02-08-2025
Malaysian-Bound Toyota Yaris Cross Receives 5-Star ASEAN NCAP Score
The DNGA-based Toyota Yaris Cross just received a five-star score for the ASEAN NCAP crash test. Coming to Malaysia soon?
02-08-2025
Chery’s Lepas Brand Entering Malaysia Soon? ‘Official’ IG Page Sighted
New ‘official’ IG page we sighted by chance indicates Chery’s new Lepas sub-brand is set to enter Malaysia very soon.
01-08-2025
Govt Looking To Revive MEX II Highway With New Completion Plan
The government is working with bondholders to restart the long-delayed MEX II Highway.
01-08-2025
2025 Proton X50 Facelift Sees 999 Units Shifted In 5 Days
2025 Proton X50 Facelift sees 999 units delivered in just five days, production hits 2,000 units mark as of end of July too.
01-08-2025
Bridgestone Turanza 6 Tyres Launched in Malaysia – 14 to 21 Inches, EV-Ready
Bridgestone Malaysia has introduced the new Turanza 6 tyres in Malaysia, with sizes ranging from 14 to 21 inches.
01-08-2025
Johor Proposes RTS2 Link Between Iskandar Puteri and Tuas
With Bukit Chagar terminal nearing completion, Johor eyes new RTS2 link to Tuas to further ease cross-border travel.
01-08-2025
PAC to KKR: Avoid Costly Missteps in Delayed MLFF Rollout
PAC wants KKR to ensure no hidden costs to government or road users in the upcoming MLFF toll system rollout.
01-08-2025
Show More
trending_flat