Pan Borneo Highway Project Will Be Completed This Year - Nanta
The Minister of Works, Datuk Seri Alexander Nanta Linggi, announced that 98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed.
According to him, the construction work can be completed this year even though some design modifications are still necessary due to soil issues at the relevant locations.
"That's the reason the project's work progress hasn't reached 100%," the minister stated at a press conference on Thursday at the Public Works Complex in this city, following the delivery of his New Year's mandate and monthly assembly with the ministry's staff.
Nanta also stated that, with regard to the Sabah LPB project, the work progress for Phase 1A, which comprises 15 work packages, had reached nearly 87%.
"For the Phase 1B package, which involves 19 work packages, it is in the tender process," he added. The minister also revealed that the West Coast Expressway, which includes the Perak alignment, is expected to open the following month. It will relieve traffic during the holiday seasons by providing an alternate route to the North-South Expressway (PLUS).
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPU7961
SELANGOR
BSJ3944
JOHOR
JYH9702
PULAU PINANG
PRU6724
PERAK
APB6637
PAHANG
CFD7042
KEDAH
KGC5490
NEGERI SEMBILAN
NEH3381
KOTA KINABALU
SJN409
KUCHING
QAB3250M
Last updated 11 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.18
-0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.93
EURO 5 B7
RM 3.13
Last updated 09 Oct, 2025
Related News
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta
The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.
16-09-2025
Nanta: MYJalan Will Become National Road Database
MYJalan app set to evolve from complaint channel to key tool in managing Malaysia’s road network.
29-08-2025
NPE Extension Deal Inked, RM1.4b+ Project Starts Q4 2025
NPE extension project costing over RM1.4b promises to cut travel time by up to 25 minutes and integrate with KL’s Traffic Master Plan 2040.
28-08-2025
JKR Set To Use Solar Lights In Over 1,000 Accident Hotspots
JKR steps up safety measures with nationwide solar lighting at over 1,000 accident hotspots.
11-08-2025
RM20 Million Allocated to Upgrade Federal Highway Motorcycle Lanes – KKR
A total of RM20 million will be allocated to upgrade the motorcycle lanes on the Federal Highway, the Works Ministry says.
08-08-2025
RM25 Million Allocated to Light Up Dark Federal Roads – KKR
The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.
07-08-2025
Latest News
Budget 2026: Two-Day 50% Toll Discount For Deepavali
Highway users will enjoy a two-day half-price toll discount during Deepavali.
10-10-2025
Budget 2026: Over RM48b Set Aside For Sabah, Sarawak Highways
PM Anwar announces major allocation for road and highway projects in Sabah and Sarawak, including the Pan Borneo Highway.
10-10-2025
Budget 2026: Tax-Free Cars from Langkawi & Labuan Will Be Limited to RM300K
Tax-free cars from Langkawi and Labuan will only be limited to RM300,000 in value from Jan 1, 2026, onwards.
10-10-2025
Budget 2026: Govt Confirms Introduction of Lemon Law in Malaysia
Budget 2026: Malaysia to Introduce Lemon Law to Strengthen Consumer Protection for Car Buyers
10-10-2025
Over 10 Million Malaysians Benefit From BUDI95 Targeted Fuel Subsidy
MOF says more than 10 million Malaysians have redeemed subsidised RON95 petrol under the BUDI95 scheme.
10-10-2025
2025 Proton X50 Charts Over 5,000 Deliveries in 40 Days
With over 5,000 deliveries made in just 40 days, the all-new 2025 Proton X50 retains its crown as the king of compact SUVs.
10-10-2025
Ops Lancar Activated For Deepavali Traffic Surge
Over 2.1 million vehicles are expected on the road as police launch Ops Lancar from Oct 17–21 to ensure smooth travel.
10-10-2025
JPJ: No Interference in JPJeBid, Number Resale Are Private Deals
JPJ insists its online plate-bidding system is clean, scalpers and resellers act outside JPJ’s jurisdiction.
10-10-2025
Show More
trending_flat