Pan Borneo Highway Project Will Be Completed This Year - Nanta
The Minister of Works, Datuk Seri Alexander Nanta Linggi, announced that 98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed.
According to him, the construction work can be completed this year even though some design modifications are still necessary due to soil issues at the relevant locations.
"That's the reason the project's work progress hasn't reached 100%," the minister stated at a press conference on Thursday at the Public Works Complex in this city, following the delivery of his New Year's mandate and monthly assembly with the ministry's staff.
Nanta also stated that, with regard to the Sabah LPB project, the work progress for Phase 1A, which comprises 15 work packages, had reached nearly 87%.
"For the Phase 1B package, which involves 19 work packages, it is in the tender process," he added. The minister also revealed that the West Coast Expressway, which includes the Perak alignment, is expected to open the following month. It will relieve traffic during the holiday seasons by providing an alternate route to the North-South Expressway (PLUS).
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQN6329
SELANGOR
BSM8273
JOHOR
JYS3382
PULAU PINANG
PSA1697
PERAK
APF5734
PAHANG
CFF5301
KEDAH
KGE5401
NEGERI SEMBILAN
NEJ6419
KOTA KINABALU
SJQ5620
KUCHING
QAB3518N
Last updated 01 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
50% Toll Discount Nationwide for CNY 2026
50% toll discount on selected highways from Feb 14–15 to ease CNY travel.
09-02-2026
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta
Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.
03-12-2025
Review Underway For 12 Loss-Making Highways - Nanta
Works Ministry will conduct a detailed review of the issue involving 12 highway concessions that recorded losses last year.
28-11-2025
Govt Mulls Putting Streetlight Upkeep Under Concessionaires
Government may soon place highway streetlight upkeep under concessionaires for quicker, more organised repairs.
21-11-2025
Latest News
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Updated Fuel Prices From 26 February To 4 March
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 26 February to 4 March, 2026, the rates are as such.
25-02-2026
APAD to Investigate Kelana Jaya LRT Breakdowns, Prasarana Ordered to Explain
Transport Minister has directed APAD to probe recent Kelana Jaya LRT disruptions and warned action may be taken against Prasarana.
25-02-2026
Chery TIGGO CROSS HEV Grand Prize Winner Announced
Joan Gan became the grand prize winner of a Chery TIGGO CROSS HEV, chosen from over 1,300 participants in Chery Malaysia’s year-end PHEV lucky draw.
24-02-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
Johor–Singapore RTS Link Fare Expected at RM15 to RM22 Per Trip
Transport Minister Anthony Loke says the RTS Link could cost between RM15 and RM22 per journey, with fares to be announced in 2H2026.
23-02-2026
Show More
trending_flat