Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Prime Minister Datuk Seri Anwar Ibrahim calls for the expedited completion of the Pan Borneo Highway project in Sabah, emphasising the importance of avoiding further delays. He has delegated responsibility to the state government to ensure the project, which benefits the people of Sabah, is completed as quickly as possible.
"Pan Borneo Highway in Sarawak is nearly finished, but Sabah's section is still lagging. We've agreed with the Sabah state government to expedite it," Anwar stated.
He also mentioned that the task of overseeing this matter has been entrusted to Works Minister Datuk Seri Alexander Nanta Linggi and Deputy Prime Minister Datuk Seri Fadillah Yusof, stressing his desire for rapid progress so that the people of Sabah can benefit from this multi-billion-ringgit project, the longest highway in Malaysia.
-full_normal.webp)
Unlike toll highways in Peninsular Malaysia, the Pan Borneo Highway in Sabah and Sarawak is toll-free, provided by the government for the public. As of July 29, Nanta reported that Phase 1A of the Pan Borneo Highway in Sabah was 77.41% complete, with full completion expected by 2026. As of now 11 of the 15 work packages have not yet been finished, with four already finished.
Anwar said that, in regards to project delays, he would not take any justifications from any of the parties concerned. He reported on continuing conversations amongst different governmental levels about current problems such as acute poverty, water, flooding, electricity, and infrastructure.
Anwar also added that although problems like potholes that prevent pupils from going to school and improvised suspension bridges made of thin planks were passed down from the previous government, it is the responsibility of the current administration to address them rather than making excuses.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQB3862
SELANGOR
BSK4081
JOHOR
JYL6541
PULAU PINANG
PRW985
PERAK
APC7938
PAHANG
CFE2693
KEDAH
KGD1929
NEGERI SEMBILAN
NEH6934
KOTA KINABALU
SJN8792
KUCHING
QAB5844M
Last updated 26 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
RON 97
RM 3.28
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.10
+0.03
EURO 5 B7
RM 3.30
+0.03
Last updated 20 Nov, 2025
Related News
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
PMX: Perodua EV Launch Confirmed This Month, Set to Be “National Agenda”
PMX confirms Perodua’s first EV will launch by month-end, and will be elevated to a “national agenda”.
11-11-2025
Bateri Madani Launched - New Low-Cost MF Car Battery Option
Sejamas World rolled out Bateri Madani - a maintenance-free car battery range priced from RM130.
06-11-2025
PMX Takes a Ride in "The Beast’ During ASEAN Summit
The Cadillac One, returned to Malaysia for the 47th ASEAN Summit as President Trump broke protocol by inviting PM Anwar Ibrahim aboard.
26-10-2025
Latest News
SPYSHOT: Proton e.MAS 7 PHEV Sighted! – Launching Next Year?
Proton e.MAS 7 PHEV sighted undergoing road tests in camouflage. Will PRO-NET launch it next year?
25-11-2025
Nationwide Checks Find No Shortchanging of RON95
Authorities confirm petrol stations are dispensing RON95 fuel accurately across the country.
25-11-2025
Man Killed After 100KG Detached Metal Shaft Strikes Car
A 63-year-old man lost his life when a heavy metal shaft fell from a truck and pierced his vehicle’s windshield.
25-11-2025
PLUS Activates Contra Lane On Elite Until Nov 27
A nightly contra lane will run between Bandar Saujana Putra and Putrajaya with lane diversions in place.
25-11-2025
KTMB Diverts Passengers From Arau Station As Floods Worsen In Perlis
Flooded roads have forced KTMB to temporarily shift ETS boarding and alighting from Arau to Kodiang Station.
25-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Isuzu Malaysia Opens New 4S Centre in Balakong
Isuzu Malaysia has opened its new 4S centre in Balakong, operated by SV Prestige Auto.
24-11-2025
Show More
trending_flat