Pan Borneo Highway Project Will Be Completed This Year - Nanta
The Minister of Works, Datuk Seri Alexander Nanta Linggi, announced that 98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed.
According to him, the construction work can be completed this year even though some design modifications are still necessary due to soil issues at the relevant locations.
"That's the reason the project's work progress hasn't reached 100%," the minister stated at a press conference on Thursday at the Public Works Complex in this city, following the delivery of his New Year's mandate and monthly assembly with the ministry's staff.
Nanta also stated that, with regard to the Sabah LPB project, the work progress for Phase 1A, which comprises 15 work packages, had reached nearly 87%.
"For the Phase 1B package, which involves 19 work packages, it is in the tender process," he added. The minister also revealed that the West Coast Expressway, which includes the Perak alignment, is expected to open the following month. It will relieve traffic during the holiday seasons by providing an alternate route to the North-South Expressway (PLUS).
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQB3862
SELANGOR
BSK4081
JOHOR
JYL6541
PULAU PINANG
PRW985
PERAK
APC7938
PAHANG
CFE2693
KEDAH
KGD1929
NEGERI SEMBILAN
NEH6934
KOTA KINABALU
SJN8792
KUCHING
QAB5844M
Last updated 26 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
RON 97
RM 3.28
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.10
+0.03
EURO 5 B7
RM 3.30
+0.03
Last updated 20 Nov, 2025
Related News
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Govt Mulls Putting Streetlight Upkeep Under Concessionaires
Government may soon place highway streetlight upkeep under concessionaires for quicker, more organised repairs.
21-11-2025
RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta
The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.
12-11-2025
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes
RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.
10-11-2025
New Audit Move To Keep Highway Concessionaires In Check
Works Ministry will introduce independent audits for highway concessionaires in early 2026.
04-11-2025
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta
The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.
16-09-2025
Nanta: MYJalan Will Become National Road Database
MYJalan app set to evolve from complaint channel to key tool in managing Malaysia’s road network.
29-08-2025
Latest News
SPYSHOT: Proton e.MAS 7 PHEV Sighted! – Launching Next Year?
Proton e.MAS 7 PHEV sighted undergoing road tests in camouflage. Will PRO-NET launch it next year?
25-11-2025
Nationwide Checks Find No Shortchanging of RON95
Authorities confirm petrol stations are dispensing RON95 fuel accurately across the country.
25-11-2025
Man Killed After 100KG Detached Metal Shaft Strikes Car
A 63-year-old man lost his life when a heavy metal shaft fell from a truck and pierced his vehicle’s windshield.
25-11-2025
PLUS Activates Contra Lane On Elite Until Nov 27
A nightly contra lane will run between Bandar Saujana Putra and Putrajaya with lane diversions in place.
25-11-2025
KTMB Diverts Passengers From Arau Station As Floods Worsen In Perlis
Flooded roads have forced KTMB to temporarily shift ETS boarding and alighting from Arau to Kodiang Station.
25-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Isuzu Malaysia Opens New 4S Centre in Balakong
Isuzu Malaysia has opened its new 4S centre in Balakong, operated by SV Prestige Auto.
24-11-2025
Show More
trending_flat