EKVE Completion Postponed To End Of 2025
After a prolonged delay, the works ministry now projects that the East Klang Valley Expressway (EKVE) will be finished by December 31, 2025. It was originally scheduled to be completed in 2019, but has been delayed several times due to a variety of issues, including civil suits and rising costs.
Putrajaya and the concessionaire for the highway signed a fifth supplementary concession agreement on November 11 of last year, according to Works Minister Alexander Nanta Linggi.
Legal disputes had stalled the highway, including five civil suits pertaining to a parcel of land in Beverly Heights, Ulu Kelang. 
According to Nanta, as of January 25, 85.74% of the EKVE project had been completed. Work on the site has resumed, with a focus on completing the first section of the highway (Sungai Long-Ampang), which is expected to open in the third quarter of this year.
“Meanwhile, work on construction of Section 2 of the highway (Ampang-Ukay Perdana) is expected to resume in the second quarter of this year,” Nanta said in a written parliamentary reply.
The 24km EKVE dual carriageway connecting Sungai Long and Ukay Perdana was expected to cost approximately RM1.55 billion.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRP6928
SELANGOR
BST6190
JOHOR
JE948J
PULAU PINANG
PSF4790
PERAK
APL4185
PAHANG
CFH7041
KEDAH
KGJ390
NEGERI SEMBILAN
NEL7955
KOTA KINABALU
SJU507
KUCHING
QAB5470P
Last updated 14 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out
JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.
11-09-2026
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Would You Trust Malaysia's MLFF System To Charge The Right Car, Every Time?
Malaysia's MLFF is moving forward, but how will barrier-free tolls identify and charge the right car? Here's how RFID, ANPR and the system could work.
09-09-2026
Is "Adjusting" Used-Car Mileage Really Normal In Malaysia?
A Bro Wong-SCRUT dispute has put used-car mileage adjustment back in focus. How common is odometer tampering in Malaysia, and are buyers protected?
09-09-2026
AI Is Now Monitoring 3 Malaysian Highways - Could Automated Summonses Be Next?
AI is now monitoring BESRAYA, NPE and LEKAS, detecting traffic offences and incidents in real time. Could automated summonses eventually follow?
09-09-2026
Too Modified For Malaysian Roads? JPJ Takes Action Against 97, Seizes 37
JPJ seized 37 modified cars during Ops Ekstrem in KL, with 485 notices issued. Some owners reportedly spent up to RM150,000 on exhaust modifications.
09-09-2026
Should Malaysia Follow Singapore And Ban Holding Phones While Driving?
Malaysia is being urged to consider stricter rules on holding phones while driving, similar to Singapore's proposed approach. Here's what the law says.
08-09-2026
Show More
trending_flat