EKVE Completion Postponed To End Of 2025
After a prolonged delay, the works ministry now projects that the East Klang Valley Expressway (EKVE) will be finished by December 31, 2025. It was originally scheduled to be completed in 2019, but has been delayed several times due to a variety of issues, including civil suits and rising costs.
Putrajaya and the concessionaire for the highway signed a fifth supplementary concession agreement on November 11 of last year, according to Works Minister Alexander Nanta Linggi.
Legal disputes had stalled the highway, including five civil suits pertaining to a parcel of land in Beverly Heights, Ulu Kelang. 
According to Nanta, as of January 25, 85.74% of the EKVE project had been completed. Work on the site has resumed, with a focus on completing the first section of the highway (Sungai Long-Ampang), which is expected to open in the third quarter of this year.
“Meanwhile, work on construction of Section 2 of the highway (Ampang-Ukay Perdana) is expected to resume in the second quarter of this year,” Nanta said in a written parliamentary reply.
The 24km EKVE dual carriageway connecting Sungai Long and Ukay Perdana was expected to cost approximately RM1.55 billion.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQP8147
SELANGOR
BSN2653
JOHOR
JYS9633
PULAU PINANG
PSA4553
PERAK
APF8441
PAHANG
CFF6947
KEDAH
KGE7124
NEGERI SEMBILAN
NEJ7387
KOTA KINABALU
SJQ7302
KUCHING
QAB3959N
Last updated 13 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
EKVE 91% Completed, To Be Opened In Stages In 2024 - Works Ministry
The East Klang Valley Expressway EKVE is 91% complete, according to the Works Ministry.
08-03-2023
EKVE 91% Completed, To Be Opened In Stages In 2024 - Works Ministry
The East Klang Valley Expressway EKVE is 91% complete, according to the Works Ministry.
08-03-2023
50% Toll Discount Nationwide for CNY 2026
50% toll discount on selected highways from Feb 14–15 to ease CNY travel.
09-02-2026
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta
Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.
03-12-2025
Review Underway For 12 Loss-Making Highways - Nanta
Works Ministry will conduct a detailed review of the issue involving 12 highway concessions that recorded losses last year.
28-11-2025
Govt Mulls Putting Streetlight Upkeep Under Concessionaires
Government may soon place highway streetlight upkeep under concessionaires for quicker, more organised repairs.
21-11-2025
RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta
The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.
12-11-2025
Latest News
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Show More
trending_flat