EKVE Completion Postponed To End Of 2025

Anis

Share via

image-full_normal---2024-03-22T064455.583.jpg After a prolonged delay, the works ministry now projects that the East Klang Valley Expressway (EKVE) will be finished by December 31, 2025. It was originally scheduled to be completed in 2019, but has been delayed several times due to a variety of issues, including civil suits and rising costs.

Putrajaya and the concessionaire for the highway signed a fifth supplementary concession agreement on November 11 of last year, according to Works Minister Alexander Nanta Linggi.

Legal disputes had stalled the highway, including five civil suits pertaining to a parcel of land in Beverly Heights, Ulu Kelang. image.png
According to Nanta, as of January 25, 85.74% of the EKVE project had been completed. Work on the site has resumed, with a focus on completing the first section of the highway (Sungai Long-Ampang), which is expected to open in the third quarter of this year.

“Meanwhile, work on construction of Section 2 of the highway (Ampang-Ukay Perdana) is expected to resume in the second quarter of this year,” Nanta said in a written parliamentary reply.

The 24km EKVE dual carriageway connecting Sungai Long and Ukay Perdana was expected to cost approximately RM1.55 billion. Thailand-Grants-T.M.-6-Form-Relief-For-Malaysian-Drivers-(19).png

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPW5227

SELANGOR

BSJ6194

JOHOR

JYJ8941

PULAU PINANG

PRV1324

PERAK

APB9464

PAHANG

CFD8417

KEDAH

KGC7032

NEGERI SEMBILAN

NEH4361

KOTA KINABALU

SJN3054

KUCHING

QAB3971M

Last updated 24 Oct, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.14

-0.04

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.89

-0.04

EURO 5 B7

RM 3.09

-0.04

Last updated 23 Oct, 2025

Related News

Auto News

EKVE 91% Completed, To Be Opened In Stages In 2024 - Works Ministry

The East Klang Valley Expressway EKVE is 91% complete, according to the Works Ministry.

08-03-2023
Auto News

EKVE 91% Completed, To Be Opened In Stages In 2024 - Works Ministry

The East Klang Valley Expressway EKVE is 91% complete, according to the Works Ministry.

08-03-2023
Auto News

East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta

The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.

16-09-2025
Auto News

Nanta: MYJalan Will Become National Road Database

MYJalan app set to evolve from complaint channel to key tool in managing Malaysia’s road network.

Auto News

NPE Extension Deal Inked, RM1.4b+ Project Starts Q4 2025

NPE extension project costing over RM1.4b promises to cut travel time by up to 25 minutes and integrate with KL’s Traffic Master Plan 2040.

Auto News

JKR Set To Use Solar Lights In Over 1,000 Accident Hotspots

JKR steps up safety measures with nationwide solar lighting at over 1,000 accident hotspots.

Auto News

RM20 Million Allocated to Upgrade Federal Highway Motorcycle Lanes – KKR

A total of RM20 million will be allocated to upgrade the motorcycle lanes on the Federal Highway, the Works Ministry says.

08-08-2025
Auto News

RM25 Million Allocated to Light Up Dark Federal Roads – KKR

The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.

07-08-2025

Latest News

Auto News

Proton: Sabah X50 Customers Have Nothing To Worry

Proton reaffirms after-sales for X50 model customers in Sabah through Regional Parts Centre established in Kota Kinabalu.

24-10-2025
Auto News

85 Deaths, 8,940 Crashes Recorded During Op Lancar Deepavali 2025

Road deaths fell 12% during Op Lancar Deepavali 2025, even as total crashes rose slightly to nearly 9,000 cases nationwide.

24-10-2025
Auto News

Toll Collection Begins On EKVE Section 1 This Saturday

Motorists using the EKVE Section 1 will start paying tolls from Oct 25 as the free toll period comes to an end.

24-10-2025
Auto News

JPJ Issued Over 4,000 Notices for Heavy Vehicle Speed Limiter Compliance

JPJ has issued over 4,000 notices to ensure heavy vehicles install speed limiter devices for safer roads.

Auto News

RM1.17Mil In Fines Collected From Singapore Drivers Without RFID VEP

JPJ has issued nearly 4,000 summonses to Singaporean motorists since July for failing to install RFID VEP tags.

23-10-2025
Auto News

BHPetrol Refreshes CI, Shows New Look In Bandar Tun Razak Station

Fuel retailers BHPetrol announces CI refresh, ‘new look’ now applied to key Bandar Tun Razak station.

23-10-2025
Auto News

MOF: Budi Madani Diesel Sees RM5 Billion in Annual Savings

Budi Madani Diesel subsidy rationalisation has freed up RM5 billion annually for social and development spending.

Auto News

Call For Return Of Child Car Seat Subsidy As Usage Remains Low

Bangi MP Syahredzan Johan has urged the government to bring back the child safety seat subsidy next year.

23-10-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.