Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.
Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.
To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.
![]()
Nanta also provided updates on the various packages of the project:
- Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
- Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
- Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
- Package 4: Kampung Relong to Raub, is 63.69% complete.
- Package 5: Raub to Bentong has been opened to users.
- Package 6: Bentong to LPT Junction, is 30.07% complete.

He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030).
Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.
Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.
Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQD6251
SELANGOR
BSK8460
JOHOR
JYM7844
PULAU PINANG
PRW5639
PERAK
APD3739
PAHANG
CFE4586
KEDAH
KGD4342
NEGERI SEMBILAN
NEH8960
KOTA KINABALU
SJP2851
KUCHING
QAB7425M
Last updated 16 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
KKR Seeking RM20 Million To Build R&R Along LTU Highway
Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.
11-10-2024
Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway
Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.
12-04-2024
LTU Section 5A: Raub Bypass Opens On Friday
The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01
08-03-2024
Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project
The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).
31-03-2023
Two Million Road Users Set To Enjoy Toll-Free LTU
A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.
27-01-2023
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta
Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.
03-12-2025
Review Underway For 12 Loss-Making Highways - Nanta
Works Ministry will conduct a detailed review of the issue involving 12 highway concessions that recorded losses last year.
28-11-2025
Latest News
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
Bollards Are There for Your Safety, Not Decoration - DBKL
DBKL is reminding the public that bollards play a crucial role in keeping pedestrians safe.
15-12-2025
Experts Call For Stricter Rules, Defensive Driving As Road Deaths Rise
Negligent driving caused over 1,200 fatalities this year, prompting calls for tougher enforcement and smarter driver education.
15-12-2025
New KTM Komuter Timetable Starts Jan 1 Amid Track Works
KTMB will roll out a revised KTM Komuter schedule from Jan 1 due to ongoing KVDT2 works.
15-12-2025
Govt Rules Out Tiered RON95 Pricing After 300 litres
Government rules out tiered RON95 prices under BUDI95, keeps RM1.99 for first 300 litres
12-12-2025
Hyundai Partners EON, Expands Local Network
Hyundai and EON have signed a LOI to open two new dealerships in Klang Valley and Penang.
12-12-2025
Perodua Traz/Nexis D66B Set to Debut on December 17
The long-awaited Perodua Traz/Nexis D66B SUV is set to make its official debut later on December 17, 2025.
12-12-2025
Show More
trending_flat