Hauliers Demand Swift WCE Land Fix

The Association of Malaysian Hauliers (AMH) has raised concerns over delays in finishing Section 3 of the West Coast Expressway, which stretches from Banting to Klang and Shah Alam.
The setback, caused by unresolved land acquisition issues in Kampung Jawa, is affecting hauliers nationwide.
AMH’s executive secretary Mohamad Azuan Masud, described the stretch as a crucial link intended to reduce congestion along the Federal Highway and Shah Alam Expressway, especially for trucks traveling between industrial areas and Port Klang.

“With this section unfinished, hauliers have no choice but to use heavily congested routes, leading to longer journeys, more fuel consumption, and increased vehicle maintenance,” Azuan explained.
According to WCE Sdn Bhd, 70 percent of land compensation payments for Kampung Jawa were made by September 2023 under the Land Acquisition Act.
The company denied any claims of forced evictions, highlighting that some landowners have refused to leave the area despite compensation being paid over 20 months ago, causing construction delays on this essential highway link.

Azuan recognised the challenges in land acquisition but urged all parties to work together for the country’s economic benefit.
“This project plays a key role in supporting Malaysia’s logistics sector and maintaining the nation’s competitive edge,” he said.
Azuan also called on the Ministry of Works, Malaysian Highway Authority, and highway concessionaires to intensify efforts to resolve outstanding land matters and keep the project on track.
“For transporters depending on Port Klang, any delay causes significant disruptions,” he added.
-full_normal.jpg)
The AMH also reaffirmed its commitment to collaborate with authorities and stakeholders to minimise the impact and help ensure the expressway’s timely completion.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQM1970
SELANGOR
BSM5340
JOHOR
JYR5875
PULAU PINANG
PRY7324
PERAK
APF3221
PAHANG
CFF3478
KEDAH
KGE3875
NEGERI SEMBILAN
NEJ5389
KOTA KINABALU
SJQ3151
KUCHING
QAB2485N
Last updated 17 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
RON 97
RM 3.10
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.99
+0.03
EURO 5 B7
RM 3.19
+0.03
Last updated 12 Feb, 2026
Related News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
230km Southern WCE Feasibility Study To Conclude By Dec
Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.
08-08-2025
Latest News
2026 Car Tint Guide: Top Brands Malaysians Recommend
We’ve rounded up the 5 best car tints to keep your cabin comfy, protect your skin, and maintain privacy.
16-02-2026
Tesla Malaysia Completes First Vehicle Delivery in East Malaysia
Tesla Malaysia has completed its first official vehicle delivery in East Malaysia at its pop-up experience centre in Kuching.
16-02-2026
MAA: Jan 2026 New Vehicle Sales Down by 29% at 64,298 Units
Jan 2026 saw a total of 64,298 units of new vehicles being sold, marking a 29% decrease over the previous month.
16-02-2026
Jetour Malaysia Launches Owners Club, T2 Previewed at First Gathering
JETOUR Malaysia launches its owners club with a Genting convoy drive and exclusive preview of the upcoming T2 SUV.
16-02-2026
West Coast Expressway Expects 35% Traffic Surge for CNY
WCE anticipates 160,000 vehicles daily during the Chinese New Year festive rush, a 35% increase compared to last year.
14-02-2026
Chery Malaysia’s 2026 Plans Detailed – Four New Models, 30% CSH Sales, Gen 4 Outlet
Chery Malaysia’s 2026 vision will see the automaker launching four new models, and 30% of its sales coming from CSH models.
13-02-2026
Zeekr Malaysia Set To Release Three New Models In 2026
Zeekr Malaysia confirm plans to release three new models locally this year, could include 9X as ‘new flagship’ offering too.
13-02-2026
Traffic Nightmare Hits Klang Valley, Economy Feels the Burn
Commuters face unprecedented jams as KL and Selangor grind to a halt this festive season.
13-02-2026
Show More
trending_flat