Hauliers Warn WCE Delays Hurting Logistics and Economy

Anis

Share via

Untitled-design---2025-09-29T112411.684.png The Association of Malaysian Hauliers (AMH) has raised concerns over delays in completing Section 3 of the West Coast Expressway (WCE) near Kampung Jawa, warning that the setback is hurting the logistics sector and the wider economy.

AMH executive secretary Mohamad Azuan Masud told Kosmo that the unfinished stretch has not only prevented the full opening of the WCE but also disrupted the smooth flow of cargo movement from the north to the south, particularly routes leading to Port Klang.


Banting-Interchange-of-the-West-Coast-Expressway_20240927215154_bernama_0.jpg
“The impact of this delay is no longer limited to just one section. It has disrupted the logistics flow from north to south, including delivery schedules to Port Klang.

“As a result, travel times are longer, fuel costs are rising, and accident risks have also increased.

“All these factors ultimately drive up logistics costs, which will create a chain effect on the prices of essential goods for the public,” he said in the daily news report.

WCEhighway.jpg
Azuan further cautioned that prolonged delays could undermine investor confidence in Malaysia’s ability to deliver major infrastructure projects on schedule.

“When completion dates are announced but still not achieved, it can create a negative perception among investors,” he added.

The WCE, once fully operational, is expected to serve as a crucial alternative to the North-South Expressway and strengthen connectivity between northern states and Port Klang, a key logistics hub. 

TMRAMN2807234.jpeg
However, repeated delays in completing certain sections have raised frustration among industry players who depend on the route to ease congestion and improve delivery efficiency.

AMH has called on the authorities to give the issue serious attention and urged for a clear, realistic completion timeline to be announced and strictly followed.



Source: Kosmo.


Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPT6512

SELANGOR

BSJ1416

JOHOR

JYH3848

PULAU PINANG

PRU3892

PERAK

APB4514

PAHANG

CFD5897

KEDAH

KGC4252

NEGERI SEMBILAN

NEH2369

KOTA KINABALU

SJM8254

KUCHING

QAB2518M

Last updated 29 Sep, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.21

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.93

EURO 5 B7

RM 3.13

Last updated 25 Sep, 2025

Related News

Auto News
West Coast Expressway On Track For 2027 Completion

West Coast Expressway On Track For 2027 Completion

The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.

27-08-2025
Auto News
Hauliers Demand Swift WCE Land Fix

Hauliers Demand Swift WCE Land Fix

Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.

11-08-2025
Auto News
230km Southern WCE Feasibility Study To Conclude By Dec

230km Southern WCE Feasibility Study To Conclude By Dec

Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.

08-08-2025
Auto News
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.

Auto News
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE

Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE

Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.

24-03-2025
EV
WCE Section 2 Opens with 240 kW DC Handal Charging Station

WCE Section 2 Opens with 240 kW DC Handal Charging Station

WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.

Auto News
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.

Auto News
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection

WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection

WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.

Latest News

Auto News
Loke: Child Seat Could Have Saved Baby in Bukit Kajang Tragedy

Loke: Child Seat Could Have Saved Baby in Bukit Kajang Tragedy

A child seat could have saved the toddler’s life in Bukit Kajang Toll Plaza crash, says Transport Minister Loke.

Auto News
Prime Minister Anwar Ibrahim Inaugurates Terminal Bersepadu Gombak

Prime Minister Anwar Ibrahim Inaugurates Terminal Bersepadu Gombak

Prime Minister Datuk Seri Anwar Ibrahim inaugurated the launch of the Terminal Bersepadu Gombak earlier today.

29-09-2025
Auto News
No More Warnings For Traffic Offenders From Oct 1

No More Warnings For Traffic Offenders From Oct 1

Police will shift from warnings to full enforcement against traffic offenders beginning Oct 1

29-09-2025
Auto News
DBKL To Rope In Scrap Dealers To Tackle Abandoned Car Surge

DBKL To Rope In Scrap Dealers To Tackle Abandoned Car Surge

Overcrowded depots and mounting complaints push DBKL to consider outsourcing abandoned vehicle disposal.

29-09-2025
Auto News
Penang Traffic Woes Persist Despite PTMP - Penang Gerakan

Penang Traffic Woes Persist Despite PTMP - Penang Gerakan

Penang Gerakan urges an independent review of the PTMP, saying poor planning has worsened traffic instead of easing it.

29-09-2025
Auto News
Hauliers Warn WCE Delays Hurting Logistics and Economy

Hauliers Warn WCE Delays Hurting Logistics and Economy

The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.

29-09-2025
Auto News
Tawau Airport Upgrade Will Be Closely Monitored, Set For 2028 Completion - Loke

Tawau Airport Upgrade Will Be Closely Monitored, Set For 2028 Completion - Loke

Tawau Airport’s RM120.9m upgrade aims to boost capacity, improve facilities, and enhance connectivity by 2028.

29-09-2025
Auto News
Budi95: Complaints Emerge Over Eligibility, MOF Assures Fix

Budi95: Complaints Emerge Over Eligibility, MOF Assures Fix

A small number of Malaysians with valid MyKad and licences reported problems accessing the new fuel subsidy.

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.