Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers (AMH) has raised concerns over delays in completing Section 3 of the West Coast Expressway (WCE) near Kampung Jawa, warning that the setback is hurting the logistics sector and the wider economy.
AMH executive secretary Mohamad Azuan Masud told Kosmo that the unfinished stretch has not only prevented the full opening of the WCE but also disrupted the smooth flow of cargo movement from the north to the south, particularly routes leading to Port Klang.

“The impact of this delay is no longer limited to just one section. It has disrupted the logistics flow from north to south, including delivery schedules to Port Klang.
“As a result, travel times are longer, fuel costs are rising, and accident risks have also increased.
“All these factors ultimately drive up logistics costs, which will create a chain effect on the prices of essential goods for the public,” he said in the daily news report.

Azuan further cautioned that prolonged delays could undermine investor confidence in Malaysia’s ability to deliver major infrastructure projects on schedule.
“When completion dates are announced but still not achieved, it can create a negative perception among investors,” he added.
The WCE, once fully operational, is expected to serve as a crucial alternative to the North-South Expressway and strengthen connectivity between northern states and Port Klang, a key logistics hub.

However, repeated delays in completing certain sections have raised frustration among industry players who depend on the route to ease congestion and improve delivery efficiency.
AMH has called on the authorities to give the issue serious attention and urged for a clear, realistic completion timeline to be announced and strictly followed.
Source: Kosmo.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQA1749
SELANGOR
BSK1860
JOHOR
JYL1422
PULAU PINANG
PRV6805
PERAK
APC5142
PAHANG
CFE1594
KEDAH
KGC9865
NEGERI SEMBILAN
NEH6011
KOTA KINABALU
SJN6648
KUCHING
QAB5170M
Last updated 15 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
+0.05
RON 97
RM 3.25
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.07
+0.05
EURO 5 B7
RM 3.27
+0.05
Last updated 13 Nov, 2025
Related News
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
230km Southern WCE Feasibility Study To Conclude By Dec
Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.
08-08-2025
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims
WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.
13-06-2025
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
Latest News
BYD Sees 2025 YTD Sales Total Reach 11,097 Units – 70% YoY Up From 2024
BYD Cars Malaysia discloses its 2025 YTD toral sales have reached 11,097 units, marking a 70% YoY increase from 2024.
14-11-2025
KLIA Aerotrain To Stop Nightly From Nov 15 For Reliability Upgrades
KLIA’s Aerotrain will be suspended nightly from 9PM to 7AM starting Nov 15 for reliability upgrades.
14-11-2025
Kelana Jaya LRT Weekend Disruptions For Upgrades
Rapid KL will upgrade the Kelana Jaya Line signalling system on Nov 15–16 and 29–30.
14-11-2025
GWM Malaysia Accelerates Localisation Drive To Strengthen Supply Chain
GWM Malaysia strengthens local partnerships and production to support the nation’s new-energy mobility ambitions.
14-11-2025
Upgraded Mitsubishi Eon Auto Mart 3S Centre Reopens in Melaka
Mitsubishi Motors Malaysia, together with Eon Auto Mart, announces the relocation and upgrade of its outlet in Melaka.
14-11-2025
PLUS Implements Night Contra-Flow On Elite Highway For Pipe Work
Motorists on the Elite Highway should expect a contra-flow from Nov 17–20 for pipe work.
14-11-2025
Flat Rate, Rule of 78, Reducing Balance: How Hire-Purchase Loans Really Work
We break down a RM100,000 loan over seven years to show how reducing balance interest saves you money.
14-11-2025
Genting Highlands Set To Introduce Vehicle Fee to Boost Safety
Motorists heading to Genting Highlands will soon pay a fee to fund maintenance and safety on the 24 km private road.
13-11-2025
Show More
trending_flat