WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
-full_normal.webp)
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
-full_normal.webp)
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
-full_normal.webp)
-full_normal.webp)
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQH493
SELANGOR
BSL5342
JOHOR
JYP4533
PULAU PINANG
PRX4557
PERAK
APD9647
PAHANG
CFE7096
KEDAH
KGD7390
NEGERI SEMBILAN
NEJ2372
KOTA KINABALU
SJP6734
KUCHING
QAB9850M
Last updated 09 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
-0.02
RON 97
RM 3.11
-0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.89
-0.05
EURO 5 B7
RM 3.09
-0.05
Last updated 08 Jan, 2026
Related News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
Latest News
MyDigital ID Becomes Mandatory Login For MyNIISe From Jan 15
From Jan 15, Malaysians must use MyDigital ID as the single login to access the MyNIISe immigration app.
09-01-2026
Hyundai Tucson Headlines CNY Promotions, Priced From RM125,888
Hyundai Malaysia announced festive CNY promotions, sees Hyundai Tucson tagged from RM125,888 and more.
09-01-2026
Proton B&P Fire: No Casualties, Incident Under Investigation
Proton acknowledges fire incident that occurred at its B&P facility, says investigation underway and no casualties reported.
08-01-2026
Fallen Tree Disrupts KTMB Services Again, Safety Concerns Grow
Another track obstruction has caused major delays on KTM routes, renewing concerns over tree management and rail safety.
08-01-2026
Fourth-Gen Kia Carnival Facelift Teased – Launching Soon?
Kia Malaysia has just dropped a teaser image showcasing the facelifted fourth-gen Carnival MPV. Launching soon?
08-01-2026
Public Transport Ridership Surges, Safety Delays Remain A Challenge
Prasarana’s record-breaking passenger numbers in 2025 show that public confidence in public transport is back on track.
08-01-2026
AirAsia Fixed Fares from RM328 for CNY & Raya 2026
AirAsia sets fixed fares from RM328 for CNY & Raya 2026 holidays, aims to make festive travels easier and more affordable.
08-01-2026
RM100m Shortfall Hits My50 Pass, Govt Pledges Continuation
Despite a RM100 million funding gap, the govt has reaffirmed its commitment to keeping the My50 public transport pass in place.
08-01-2026
Show More
trending_flat