WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.

Kumeran Sagathevan

Share via

WCE-Sec-7-(3).jpg


According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.

This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.


WCE-Sec-7-(6).jpg


"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."

Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.


WCE-Sec-7-(5).jpgWCE-Sec-7-(2).jpg


Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.

Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.



Source: BERNAMA



Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY4570

SELANGOR

BSK132

JOHOR

JYK7403

PULAU PINANG

PRV5269

PERAK

APC3966

PAHANG

CFE842

KEDAH

KGC9082

NEGERI SEMBILAN

NEH5632

KOTA KINABALU

SJN5895

KUCHING

QAB4928M

Last updated 09 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.20

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.02

+0.07

EURO 5 B7

RM 3.22

+0.07

Last updated 06 Nov, 2025

Related News

Auto News

WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025

Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.

Auto News

Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents

The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.

Auto News

Hauliers Warn WCE Delays Hurting Logistics and Economy

The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.

29-09-2025
Auto News

West Coast Expressway On Track For 2027 Completion

The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.

27-08-2025
Auto News

Hauliers Demand Swift WCE Land Fix

Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.

11-08-2025
Auto News

230km Southern WCE Feasibility Study To Conclude By Dec

Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.

08-08-2025
Auto News

WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.

Auto News

Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE

Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.

24-03-2025

Latest News

Auto News

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025
Auto News

KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced

KLIMS 2026 set to retain ‘Beyond Mobility’ theme, over 20 key participating brands confirmed too.

07-11-2025
Auto News

Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash

The Cabinet is reviewing new safety measures for FRU vehicles following the tragic Teluk Intan crash.

07-11-2025
Auto News

JPJ Targets Firms Hiring Unlicensed Foreign Drivers

JPJ will launch operations nationwide to take action against companies employing foreigners without valid driving licences.

07-11-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.