WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
-full_normal.webp)
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
-full_normal.webp)
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
-full_normal.webp)
-full_normal.webp)
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRW8209
SELANGOR
BSU7592
JOHOR
JG7442J
PULAU PINANG
PSH1410
PERAK
APM6459
PAHANG
CFJ3141
KEDAH
KGJ6691
NEGERI SEMBILAN
NEM4712
KOTA KINABALU
SJU9013
KUCHING
QAB9140P
Last updated 30 Oct, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
WCE Section 1 Is Toll-Free Until Sept 29 Ahead Of National Day
Public Works Minister Datuk Seri Alexander Nanta Linggi announced that users of the WCE passing through the Banting Interchange Section 1 are eligible for free toll starting tonight at 12.01 until Sept 29, 11.59pm.
30-08-2024
WCE Highway – Smoother Drive This Aidiladha With Ample Refuelling Exits
WCE Highway could be your alternative option this coming Aidiladha travel period thanks to its ample refuelling exit options
14-06-2024
DC Handal Kempower Liquid-Cooled DCFC At WCE Taiping Now LIVE - RM1.50/kWh
DC Handal's first liquid-cooled 400 kW DCFC activated at WCE Taiping Toll Plaza, 4 Satellite, RM1.50 per kWh.
14-06-2024
WCE Section 11 (Taiping-Beruas) Opens March 12, Toll-Free Until May 11
West Coast Expressway (WCE) officially set to open Section 11 (Taiping-Beruas) stretch from March 12, will be toll-free until May 11.
11-03-2024
CNY 2024: WCE Anticipates 120,000 Vehicles & Halts All Road Works!
WCE and PDRM launched CNY Road Safety Campaign to champion road safety for a secure and smooth journey.
06-02-2024
New DC Handal 180 kW DCFC At WCE Assam Jawa Toll Plaza
DC Handal set to open new 180 kW DC charger located at WCE Assam Jawa toll plaza soon.
12-12-2023
WCE Assam Jawa Interchange Opens To Public - TOLL FREE Till 2 Jan 2024!
Assam Jawa Interchange on West Coast Expressway (WCE) Section 6 opens to the public on Tuesday, November 21, 2023 at 12:01 am
20-11-2023
Latest News
MyEG Faces RM353.13 Million Tax Assessment And Civil Suit
MyEG faces a RM353.13 million LHDN tax assessment and government civil suit. Find out what Zetrix AI disclosed and how it differs from the JPJ dispute.
30-10-2026
BYD's Penang Heritage Showroom Just Won Gold, But Not For Selling Cars
BYD Mansion Macalister in Penang wins Gold at the REKA Awards 2026. Here's why the heritage showroom earned recognition beyond selling EVs.
29-10-2026
Stolen Cables, Stranded Commuters. Is Malaysia Doing Enough To Stop It?
Malaysia plans tougher rail cable theft penalties after 1,303 hours of KTM delays and RM20.6 million in losses. Will the crackdown protect commuters?
28-10-2026
Malaysia Wants Drunk Drivers To Compensate Victims, But How Will It Work?
Malaysia plans to make convicted drunk drivers compensate victims. Here's how the proposed law could work, who may qualify and when it could take effect.
28-10-2026
Over 200,000 Vehicles Need Speed Limiters, But Malaysia Has Just 33 Approved Suppliers
Over 200,000 pre-2015 commercial vehicles need speed limiter retrofits, but Malaysia has just 33 JPJ-approved suppliers. Only 17% have recorded compliance.
28-10-2026
OMODA | JAECOO Malaysia Sharpens Technician Skills For Better After-Sales Support
OMODA | JAECOO Malaysia's Technical Skills Competition 2026 assesses technician knowledge, diagnostics and repair skills to strengthen after-sales support.
27-10-2026
Malaysia F1 Return: Sepang's 50-50 Chances And What Happens Next
Malaysia's F1 return remains 50-50 as SIC prepares a November Cabinet proposal. Here's what Sepang must overcome before the Malaysian GP can return.
27-10-2026
DENZA Balakong 4S Centre Opens, Among 3 Largest in Malaysia
DENZA opens a 3,000-sqm Balakong 4S centre with servicing, body and paint facilities, plus BYD Flash Charging planned. See its location and opening hours.
26-10-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge