WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
-full_normal.webp)
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
-full_normal.webp)
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
-full_normal.webp)
-full_normal.webp)
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPY4570
SELANGOR
BSK132
JOHOR
JYK7403
PULAU PINANG
PRV5269
PERAK
APC3966
PAHANG
CFE842
KEDAH
KGC9082
NEGERI SEMBILAN
NEH5632
KOTA KINABALU
SJN5895
KUCHING
QAB4928M
Last updated 09 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.02
+0.07
EURO 5 B7
RM 3.22
+0.07
Last updated 06 Nov, 2025
Related News
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
230km Southern WCE Feasibility Study To Conclude By Dec
Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.
08-08-2025
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims
WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.
13-06-2025
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
Latest News
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams
JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.
10-11-2025
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads
Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.
10-11-2025
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes
RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.
10-11-2025
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage
The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.
10-11-2025
New Leapmotor 3S Showroom Opens In Ipoh, Perak
Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.
07-11-2025
KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced
KLIMS 2026 set to retain ‘Beyond Mobility’ theme, over 20 key participating brands confirmed too.
07-11-2025
Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash
The Cabinet is reviewing new safety measures for FRU vehicles following the tragic Teluk Intan crash.
07-11-2025
JPJ Targets Firms Hiring Unlicensed Foreign Drivers
JPJ will launch operations nationwide to take action against companies employing foreigners without valid driving licences.
07-11-2025
Show More
trending_flat