Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.
According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.

Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.

It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.
The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.
Source: NewStraitsTimes & FB Warga Prasarana
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPY762
SELANGOR
BSJ9016
JOHOR
JYK5764
PULAU PINANG
PRV4429
PERAK
APC3163
PAHANG
CFD9712
KEDAH
KGC8509
NEGERI SEMBILAN
NEH5261
KOTA KINABALU
SJN5354
KUCHING
QAB4754M
Last updated 03 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
New RM22.7M JPJ Kajang Office Set for 2027
The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.
23-09-2025
Loke: Accessibility, Safety Upgrades Coming To LRT Stations
Prasarana studying plans to install barriers at older LRT stations for enhanced passenger safety.
08-08-2025
New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025
Speed Limitation Device (SLD) will be compulsory for commercial vehicles starting Oct 2025 to meet national road safety targets.
13-06-2025
BYD Charges Up MOT Staff EV Adoption Effort
“Jom Pandu BYD Bersama MOT” effort sees ministry team up with BYD to drive EV transition from the inside out.
22-04-2025
JPJ Merges Motorcycle and Car Theory Modules
JPJ will introduce integrated theory module, one KPP01 theory class will cover both motorcycle and car licences.
21-04-2025
MoT Set to Work with KPDN to Ban Dummy Seatbelt Buckles
Both the MoT and KPDN will work together on banning the sale and usage of dummy seatbelt buckles.
18-02-2025
Loke: Zero Tolerance For “Protection Sticker” Against JPJ
Anthony Loke vows zero tolerance against "protection sticker" amidst widespread allegations.
15-01-2025
MOT Unveils 2025 Road Safety Strategy
MOT 2025 Roadmap: Stricter enforcement and new tech to curb heavy vehicle accidents.
07-01-2025
Latest News
RTS Link 65% Complete, First Train Arriving This Month
RTS Link connecting JB and SG is officially 65% complete, with the first train set expected to arrive this month.
03-11-2025
Toyota Skill Contest 2025 Winners Announced
Winners for the Toyota Skill Contest 2025 organised by UMW Toyota Motor have been announced.
03-11-2025
Budi95: Only 0.6% Max Out Quota, Govt Flags Unusual Purchase Near Border
Only 0.6% hit the 300L limit under BUDI95 programme with most recipients using only about 98 litres in Oct.
03-11-2025
RM600 Million Super Magnet Plant Set to Power Malaysia’s EV Ambitions
RM600 million JS Link–Lynas investment drives Malaysia’s push in downstream REE processing for EV and clean energy sectors.
03-11-2025
Datuk Abdul Rashid Musa Returns To Proton As Deputy CEO
Datuk Abdul Rashid Musa returns to Proton as Deputy CEO, succeeding Roslan Abdullah.
03-11-2025
ETS3 To Johor Bahru Set To Roll Out by Mid-December
The ETS3 line is set to launch by mid-Dec, extending the Electric Train Service from Gemas to JB.
03-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
APAD Orders Aeroline To Halt Services Over Repeated Non-Compliance
Aeroline was directed to halt trips from Nov 6 to Dec 5 after failing to relocate to approved terminals as required by APAD.
03-11-2025
Show More
trending_flat